O'Neil Lumber Co. v. Allied Builders Corp.

663 S.W.2d 326, 1983 Mo. App. LEXIS 3751
CourtMissouri Court of Appeals
DecidedNovember 29, 1983
DocketNo. 46503
StatusPublished
Cited by8 cases

This text of 663 S.W.2d 326 (O'Neil Lumber Co. v. Allied Builders Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Neil Lumber Co. v. Allied Builders Corp., 663 S.W.2d 326, 1983 Mo. App. LEXIS 3751 (Mo. Ct. App. 1983).

Opinion

SMITH, Judge.

Defendant Pioneer National Title Insurance Company1 appeals from a judgment against it for $18,612.79 in a jury tried contract case. We affirm.

In September 1974 four parties entered into a construction and disbursing escrow agreement. Allied was the general contractor for work to be done at “The Barn at Lucerne” in St. Louis County; Gateway West Investments, represented by Paul Londe, was the owner of the project; Pioneer Bank and Trust Company was the mortgagee; defendant (unrelated to the bank) was the escrowee. The contract provided for money to be deposited with the escrowee “for use in payment for labor, materials, services, and all other items included in [a] Schedule, all relating to the property described below and the construction of improvements thereon .... ”

In the contract plaintiff undertook to fully construct and complete the improvements to the project by March 12, 1976. It further agreed:

“To execute payment requisitions or Escrowee’s vouchers authorizing payments for labor, materials and services and to deliver to Escrowee paid bills and mechanic’s and materialmen’s lien waivers from those receiving payment ....
“To request payment of no portion of his profit until all costs of construction of improvements have been paid in full and the improvements have been accepted by Owner.”

The escrowee, which was paid for its services as such, agreed “[t]hat it will accept and use due care in disbursing funds in accordance with the terms of this agreement .... ”

The contract also provided that Escrowee “at its election, may make payments direct ly for any item required to be paid hereunder without first securing approval of Owner and/or Contractor.”

Defendant provided plaintiff with a group of blank vouchers to use. When plaintiff wanted money disbursed it would fill out a voucher indicating the recipient and amount and would send it to Mr. Londe. He in turn would forward the voucher to defendant which would sign the negotiable voucher and send it to the person or entity entitled to the payment. Unless the payment was to plaintiff, it would have [329]*329no knowledge of disbursement of funds after it had prepared the voucher and forwarded it to Londe. In addition plaintiff prepared and submitted directly to defendant monthly reports on money expended to date, amounts still available in each of the various categories of work and similar information. There was testimony that copies of the original vouchers were sent directly to defendant, although the testimony was equivocal. In July 1975, when the work was virtually complete, plaintiff sent to defendant copies of the “revised vouchers ... as well as a recap of all the money owed to the sub-contractors, suppliers, and ourselves, per Mr. Londe’s request.” These documents reflected that Londe was holding earlier vouchers for payment to O’Neil Lumber Company of $7191.83 and that there was also owing to that company $1135.96 as a final payment. Also attached were copies of vouchers for O’Neil reflecting the original vouchers being held by Londe. There were additionally recap sheets of the entire project, summaries of amounts paid, and a list of amounts still owing to the contractor, sub-contractors, and materialmen.

In September 1975 plaintiff executed an affidavit which certified that all sub-contractors and materialmen had been paid. This affidavit was necessary for the plaintiff to receive its final payment on the project. At the time of executing the affidavit plaintiff knew that all vouchers for material had been submitted to Londe and copies had been furnished defendant; plaintiff assumed those vouchers had been paid by defendant.

In January 1976 O’Neil notified plaintiff that $7503.79 was due and owing to it for materials furnished on the project. Plaintiff immediately contacted defendant which contended it had never received original vouchers for the amount owing. It did, however, have documents previously furnished by plaintiff which showed the amounts owing to O’Neil. The amount due O’Neil was exactly the amount shown on the July 1975 recap as owing to O’Neil less a bill of $824 shown on the recap as one of the two final payments due. Defendant advised plaintiff that the O’Neil claim had not been paid but that there was money in escrow to pay it. Subsequently, it was agreed between defendant and Londe that the amount to cover the O’Neil claim would not be continued in escrow and that Londe would indemnify defendant for that claim.

O’Neil sued plaintiff on its claim and plaintiff filed its third party petition against defendant. The claim of O’Neil resulted in a consent judgment between it and plaintiff for the full amount of the claim plus interest at the rate of 1.5% per month or a total judgment of $17,675.29. Plaintiff expended $937.50 in attorney’s fees in defending against the O’Neil claim. At trial the jury awarded plaintiff the amount of the consent judgment plus the attorney’s fees.

On appeal defendant raises essentially two contentions. The first is leveled against the submissibility of plaintiff’s case and as a challenge to the verdict-directing instruction. The thrust of that contention is that plaintiff did not establish or submit to the jury its compliance with the contract. This in turn is premised upon evidence that plaintiff asked for and received its final payment including profits before all costs of construction had been paid and that it failed to execute and deliver to defendant original negotiable vouchers authorizing payment to O’Neil.

It is clear that plaintiff submitted its bills during the progress of the work and these bills included plaintiff’s profits. Defendant paid these bills including the profits. The request for profits was contrary to the language of the contract. But this technical breach by plaintiff in no way affects the obligations of defendant under the contract nor its liability to plaintiff for its failure to pay O’Neil. This was not a condition precedent to defendant’s performance under the contract as defendant contends. A “condition precedent” is one that is to be performed before the agreement becomes obligatory, and which calls for the happening of some event or the performance of some act (after the terms of the contract [330]*330have been agreed on) before some act dependent thereon must be performed. Black’s Law Dictionary, Fifth Edition; Juengel Construction Co., Inc. v. Mt. Etna, Inc., 622 S.W.2d 510 (Mo.App.1981) [1, 2], Defendant’s function under the contract was to provide the mortgage holder with protection of its security for the loan. As such it undertook to disburse funds to all subcontractors and materialmen as well as the general contractor. This was to enable it to assure that the project when completed would be free from liens and claims which might jeopardize the bank’s security. It defies logic to conclude that a mere premature request for profits by plaintiff absolved defendant from all other obligations under the escrow agreement.

In addition, if there was a breach by plaintiff in requesting profits it was acquiesced in by defendant which had the obligation to refuse payment of unauthorized requests for funds.2 Finally, the evidence does not support a conclusion that this breach was in any way detrimental to defendant. The only evidence is that at the time it became aware of the O’Neil claim, defendant had available escrow funds to meet that claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Cottleville v. St. Charles County
91 S.W.3d 148 (Missouri Court of Appeals, 2002)
Autry v. Dearman
933 S.W.2d 182 (Court of Appeals of Texas, 1996)
Joseph Projects Diversified, Inc. v. Knox-Arizona Corp.
935 S.W.2d 644 (Missouri Court of Appeals, 1996)
Stavrides v. Zerjav
927 S.W.2d 486 (Missouri Court of Appeals, 1996)
State Ex Rel. Chase Resorts, Inc. v. Campbell
913 S.W.2d 832 (Missouri Court of Appeals, 1995)
Carlund Corp. v. Crown Center Redevelopment Corp.
910 S.W.2d 273 (Missouri Court of Appeals, 1995)
H.B.I. Corp. v. Jimenez
803 S.W.2d 100 (Missouri Court of Appeals, 1990)
United States v. Conservation Chemical Co.
661 F. Supp. 1416 (W.D. Missouri, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
663 S.W.2d 326, 1983 Mo. App. LEXIS 3751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneil-lumber-co-v-allied-builders-corp-moctapp-1983.