Carlund Corp. v. Crown Center Redevelopment Corp.

910 S.W.2d 273, 1995 Mo. App. LEXIS 1560, 1995 WL 520745
CourtMissouri Court of Appeals
DecidedSeptember 5, 1995
DocketWD 49430, WD 49476
StatusPublished
Cited by17 cases

This text of 910 S.W.2d 273 (Carlund Corp. v. Crown Center Redevelopment Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlund Corp. v. Crown Center Redevelopment Corp., 910 S.W.2d 273, 1995 Mo. App. LEXIS 1560, 1995 WL 520745 (Mo. Ct. App. 1995).

Opinion

ULRICH, Presiding Judge.

Elgard Corporation (Elgard) appeals from the judgment entered following jury trial in favor of J.H. Maekay Electric Company, Inc. (Maekay) for breach of a construction contract under which Elgard was the general contractor and Maekay was an electrical subcontractor. Damages of $193,120 were awarded to Maekay consisting of $7,620 for electrical work performed by Maekay and $185,500 for attorney fees incurred by Mac-kay. Elgard claims the trial court erred in (1) awarding attorney fees to Maekay under the collateral litigation doctrine; (2) submitting four claimed erroneous instructions; (3) denying its motion for judgment n.o.v., asserting that damages arising from events occurring before October 11, 1989, could not have been the result of any alleged breach of contract by Elgard; and (4) allowing submission of “irrelevant and prejudicial evidence” submitted by Carlund. Maekay appeals from the trial court’s order directing verdict in favor of Elgard on Mackay’s claim of fraudulent misrepresentation, claiming sufficient evidence supported its claim.

The original plaintiff, Carlund Corporation (Carlund), sued Maekay, Crown Center Redevelopment Corporation (Crown Center), and Elgard. Elgard and Maekay asserted counter and cross-claims. Additionally, El-gard sued Federal Insurance Company (Federal), Mackay’s surety. Carlund’s claims were stayed, and the case proceeded on the cross-claims between Maekay and Elgard, Elgard’s claim against Federal, and Mac-kay’s counterclaim against Carlund.

The judgment in favor of Maekay is affirmed in part, reversed in part and is remanded to the trial court. The order directing verdict in favor of Elgard for fraudulent misrepresentation is affirmed.

Facts

Dispute arose from a construction project at a parking garage owned by Crown Center. The project involved installation of a “cathodic protection system”, an electrical system which retards deterioration of reinforced concrete structures. Various contractors were hired to work on the project.

On June 9, 1989, Crown Center signed a written contract naming Elgard the general contractor for the Crown Center project. By letter, on June 13, 1989, Elgard engaged Maekay as prime subcontractor for the project and requested Maekay to begin work on the project in accordance with its bid. The letter stated that a written subcontract would follow. On the same day, Maekay sent a similar letter to Carlund as Mackay’s subcontractor requesting it to begin work in accordance with its bid.

On July 31, 1989, Elgard sent Maekay a formal subcontract which Maekay signed on August 31, 1989. Likewise, Maekay offered Carlund a formal contract. Carlund found the contract unacceptable and refused to sign it. Maekay never secured a signed contract, a performance bond, or a certificate of insurance from Carlund.

Disputes arose between Maekay and Car-lund. Carlund demanded further payments to continue working, and Maekay found Car-lund’s work inadequate. On October 6,1989, Carlund ceased working and left the project.

On October 10, 1989, representatives of Elgard and Carlund met in an effort to resolve the disputes and complete the project timely. The next day, October 11, 1989, Clem Firlotte and Michael Mazzuca of El-gard met with Mackay’s representatives, Jack Feeney and John Maekay. Maekay expressed its wish to engage a different subcontractor to replace Carlund. Elgard, however, agreed to relieve Maekay of the portion of its bond pertaining to Carlund, to obtain and provide written confirmation that Car-lund would not sue Maekay for work performed on the project, to hold Maekay harmless for work performed by Carlund for the entire project, and to issue an amended contract to Maekay reflecting these changes. Based on these statements, Maekay permit *276 ted Carlund to return to the job site to work under Elgard. Carlund, however, did not provide written confirmation that it would not initiate' litigation.

On October 13, 1989, Mr. Mazzuca sent a letter of intent by facsimile to Mackay outlining the terms of the agreement discussed on October 11. The letter was unsigned, and Elgard contended that it was only a summary of negotiating points which had been raised in the October 10 and 11 meetings. Elgard never issued a formal amendment to Maekay’s contract, released Mackay’s bond, or obtained a release of Mackay from Car-lund. Ultimately, Elgard terminated Car-lund on October 31, 1989, for unsatisfactory performance.

Carlund sued Crown Center, Elgard, and Mackay to enforce a mechanic’s lien, for breach of contract, and in quantum meruit. Elgard and Mackay filed cross-claims against each other asking for attorney’s fees. El-gard sought to recover fees under a contractual provision. Mackay claimed recovery of fees was justified by the collateral litigation doctrine. At trial, evidence of Elgard and Mackay’s attorney fees was introduced pursuant to the parties’ stipulation.

On the eve of trial, the trial court stayed Carlund’s claims because the company was not registered to do business in Missouri. Thus, the trial was bifurcated, and only the cross-claims between Elgard and Mackay, Mackay’s counter-claims against Carlund, and Elgard’s claims against Federal were tried.

The trial court directed a verdict in favor of Elgard on Mackay’s cross-claim for fraudulent misrepresentation. The jury returned its verdict against Elgard in favor of Mackay and awarded Mackay damages of $193,120, and judgment was entered accordingly. The award consisted of $7,620 for electrical work performed by Mackay on the project after October 11, 1989, and $185,500 for attorney fees. The award for attorney fees was in the aggregate and did not distinguish between fees incurred pursuing different claims. The judgment also included an obligation to indemnify Mackay for any damages Mackay paid to Carlund. Elgard’s and Mackay’s appeals followed.

Elgard’s Appeal

I.

As its first point on appeal, Elgard claims the trial court erred in awarding attorney fees to Mackay under the collateral litigation doctrine. It argues that the trial court improperly denied its motion for summary judgment, motion in limine, motion for directed verdict, and motion for judgment notwithstanding the verdict regarding the issue.

First, Mackay asserts the issue of attorney fees was not preserved for review on appeal because evidence of Mackay’s attorney fees was admitted at trial without objection and by stipulation. Elgard, however, argues that the issue was raised and preserved in its motion for summary judgment, motion in limine, motion for directed verdict, and motion for judgment notwithstanding the verdict. Mackay argues that denial of the motion for summary judgment and motion in limine are not reviewable on appeal and that Elgard did not raise the collateral litigation doctrine issue in its motion for directed verdict. Additionally, it claims that since the doctrine was not raised in the directed verdict motion, it cannot be raised in a motion for judgment notwithstanding the verdict.

An appellate court may not address an issue that was not put before the trial court. Stone v. City of Columbia, 885 S.W.2d 744, 747 (Mo.App.1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Baum v. Helget Gas Products, Inc.
440 F.3d 1019 (Eighth Circuit, 2006)
Volker Court, LLC v. Santa Fe Apartments, LLC
130 S.W.3d 607 (Missouri Court of Appeals, 2004)
Killion v. Bank Midwest, N.A.
987 S.W.2d 801 (Missouri Court of Appeals, 1998)
Dice v. Darling
974 S.W.2d 641 (Missouri Court of Appeals, 1998)
Hayward v. City of Independence
967 S.W.2d 650 (Missouri Court of Appeals, 1998)
Chesus v. Watts
967 S.W.2d 97 (Missouri Court of Appeals, 1998)
State ex rel. Mid-Missouri Limestone, Inc. v. County of Callaway
962 S.W.2d 438 (Missouri Court of Appeals, 1998)
State v. Myszka
963 S.W.2d 19 (Missouri Court of Appeals, 1998)
City of Kansas City, Inc. v. Hayward
954 S.W.2d 399 (Missouri Court of Appeals, 1997)
VanBooven v. Smull
938 S.W.2d 324 (Missouri Court of Appeals, 1997)
Stewart v. Kirkland
929 S.W.2d 321 (Missouri Court of Appeals, 1996)
Estate of Gantt v. Baldwin
927 S.W.2d 957 (Missouri Court of Appeals, 1996)
Prosser v. Rethorn
928 S.W.2d 364 (Missouri Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
910 S.W.2d 273, 1995 Mo. App. LEXIS 1560, 1995 WL 520745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlund-corp-v-crown-center-redevelopment-corp-moctapp-1995.