Onalaska Electrical Heating, Inc. v. Schaller

288 N.W.2d 829, 94 Wis. 2d 493, 1980 Wisc. LEXIS 2509
CourtWisconsin Supreme Court
DecidedMarch 4, 1980
Docket77-300
StatusPublished
Cited by24 cases

This text of 288 N.W.2d 829 (Onalaska Electrical Heating, Inc. v. Schaller) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Onalaska Electrical Heating, Inc. v. Schaller, 288 N.W.2d 829, 94 Wis. 2d 493, 1980 Wisc. LEXIS 2509 (Wis. 1980).

Opinion

CONNOR T. HANSEN, J.

On November 5, 1976, Onalaska Electrical commenced an action against Robert A. Schaller on an account stated. In its brief complaint, Onalaska Electrical alleged that it and Schaller had engaged in certain business transactions and on September 30, 1975, they agreed to the balance resulting therefrom; that Onalaska Electrical rendered a statement thereof and Schaller did not object to it; and that the amount of $14,852.54 was due and owing from Schaller on the account stated. The answer of Schaller was a general denial of the allegations of the complaint that set forth a cause of action on an account stated.

The issues on appeal relate to alleged trial court error in limiting the admission of evidence to that which concerned the question of whether the parties had in fact entered into a contract of an account stated.

Schaller was a developer of various business enterprises and over a period of years Onalaska Electrical had *496 done considerable work for Sehaller on different projects. Onalaska Electrical kept ledger cards on the various projects and periodically sent Sehaller invoices or statements.

As of April 29, 1974, the account was paid in full. Subsequent to this date, in June, 1974, Sehaller requested that Onalaska Electrical send him statements containing a more detailed breakdown of the charges for labor and materials. Such statements were sent to him for each of three projects in progress and in the latter half of 1974. Payments continued to be made on the account after April 29, 1974, but arrearages began to accumulate. Finally, in January of 1975, Onalaska Electrical ceased to do any work for Sehaller. At that time, the ledger kept by Onalaska Electrical showed a balance of $23,096.28 due from Sehaller on the various projects then in progress.

After January, 1975, Robert Whiteman, the president and sole stockholder of Onalaska Electrical, made many attempts to get the account paid. All parties agree that in June or July, 1975, Robert Whiteman, Gladys Hocken-berry, bookkeeper for Onalaska Electrical, and Sehaller and his wife held a final meeting to discuss settlement of the account. 1

There is a conflict between the parties as to what transpired at this June or July, 1975, meeting. Based upon the testimony of the parties, evidence presented, and reasonable inferences to be drawn therefrom, the trial court found that the parties had entered into an account stated at this meeting, and judgment was entered accordingly.

At this meeting Sehaller, among other things, complained about a 10 percent add-on to the cost of equipment furnished by Onalaska Electrical and an increase *497 in labor charges. As a result, Onalaska Electrical agreed to discount certain items from the $23,096.28 which was due according to their ledgers. After making certain adjustments, the figure of $13,141.91 was presented to Sehaller, and Whiteman and Hockenberry both testified that the parties agreed that the balance due on the account was $13,141.91. They testified that a statement of the account showing the adjustments was given to Schal-ler and that he promised to pay the account in the amount agreed upon. A couple of months later Onalaska Electrical commenced sending Sehaller statements for the amount agreed upon plus an additional monthly interest charge. They continued to send Sehaller these monthly statements until this action was commenced in November, 1976. 2 After the meeting Sehaller never responded to the statements sent to him or made any payments on the account.

Sehaller and his wife, Irene Sehaller, testified that a final meeting was held in June or July of 1975 in an attempt to get the account settled, and that figures were discussed. They denied, however, that an agreement regarding the account was reached at that meeting. They testified that the statement of the account showing a balance due of $13,141.91 was not presented to them at the meeting, but it was sent to them by mail within 10 days or two weeks after the meeting.

The trial court found that an agreement was reached between the parties to settle the account at $13,141.91, and made its findings of fact and conclusions of law, the pertinent portions of which are:

“FINDINGS OF FACT
*498 “3.) That the parties entered into an agreement for the electrical work on the home and project of defendants and that invoices were sent to the defendant for the labor and material which was incurred as the project progressed.
“4.) That invoices which had been submitted to the defendant had been paid as of April 29, 1974.
“5.) That in June or July of 1975, the account according to plaintiff’s books had a balance of $23,096.28.
“6.) That in June or July of 1975, there was a meeting between plaintiff and defendant and an agreement or means of reaching agreement was agreed upon by the parties.
“7.) That adjustments made to the account by plaintiff come close to the amount defendant contends he was overcharged.
“8.) That the agreement reached at the June or July meeting was reduced to an invoice which is exhibit TO’ in the record. That within 10 days or two weeks following the meeting a copy of exhibit TO’ was mailed to defendant.
“9.) That no interest had been charged to defendant prior to the exhibit TO’ invoice.
“CONCLUSIONS OF LAW
“1.) That an agreement was reached by the parties in June or July of 1975, to compromise their account at $13,141.91.
“2.) That plaintiff is entitled to judgment against defendant in the amount of $13,141.91 with interest at the legal rate from October 30, 1975, plus the costs and disbursements of the action.”

Judgment was thereupon entered awarding Onalaska Electrical damages in the amount of $13,141.91, together with interest, costs and disbursements, in the total amount of $14,522.52.

On appeal, Sehaller presents three issues: (1) Did the trial court err in excluding certain evidence, (2) was there sufficient evidence to prove the existence of an account stated, and (3) should a new trial be granted in the interest of justice?

*499 Schaller first argues that the trial court abused its discretion by restricting the evidence to the issue of whether the parties had in fact struck a balance and thereby entered into a contract, either express or implied, on an account stated. 3 It is the position of Schaller that the trial court committed prejudicial error when it excluded evidence which reflected on the quality of the workmanship and reasonableness of the charges by Onalaska Electrical on some of the projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. J. G., III
Court of Appeals of Wisconsin, 2026
Bakley v. Edgerton
2018 WI App 62 (Court of Appeals of Wisconsin, 2018)
State v. Timothy L. Finley, Jr.
2016 WI 63 (Wisconsin Supreme Court, 2016)
Stevenson v. Stevenson
2009 WI App 29 (Court of Appeals of Wisconsin, 2009)
Estate of Newgard Ex Rel. Newgard v. Bank of America
2007 WI App 161 (Court of Appeals of Wisconsin, 2007)
Global Steel Products Corp. v. Ecklund Carriers, Inc.
2002 WI App 91 (Court of Appeals of Wisconsin, 2002)
Rumage v. Gullberg
2000 WI 53 (Wisconsin Supreme Court, 2000)
Stan's Lumber, Inc. v. Fleming
538 N.W.2d 849 (Court of Appeals of Wisconsin, 1995)
Plesko v. Figgie International
528 N.W.2d 446 (Court of Appeals of Wisconsin, 1994)
Ivalis v. Curtis
496 N.W.2d 690 (Court of Appeals of Wisconsin, 1993)
Milwaukee Journal v. Call
450 N.W.2d 515 (Court of Appeals of Wisconsin, 1989)
State v. Friday
434 N.W.2d 85 (Wisconsin Supreme Court, 1989)
In Interest of Baby Girl K.
335 N.W.2d 846 (Wisconsin Supreme Court, 1983)
C. R. Ex Rel. Herrick v. American Standard Insurance
333 N.W.2d 121 (Court of Appeals of Wisconsin, 1983)
Elkhorn Area School District v. East Troy Community School District
327 N.W.2d 206 (Court of Appeals of Wisconsin, 1982)
Amoco Oil Co. v. Cardinal Oil Co., Inc.
535 F. Supp. 661 (E.D. Wisconsin, 1982)
Village of Big Bend v. Anderson
308 N.W.2d 887 (Court of Appeals of Wisconsin, 1981)
Kollasch v. Adamany
299 N.W.2d 891 (Court of Appeals of Wisconsin, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
288 N.W.2d 829, 94 Wis. 2d 493, 1980 Wisc. LEXIS 2509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/onalaska-electrical-heating-inc-v-schaller-wis-1980.