Oil Screw Noah's Ark v. Bentley & Felton Corp.

322 F.2d 3, 1964 A.M.C. 59
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 15, 1963
DocketNo. 20058
StatusPublished
Cited by11 cases

This text of 322 F.2d 3 (Oil Screw Noah's Ark v. Bentley & Felton Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oil Screw Noah's Ark v. Bentley & Felton Corp., 322 F.2d 3, 1964 A.M.C. 59 (5th Cir. 1963).

Opinion

JOHN R. BROWN, Circuit Judge.

Indigenous to her name and the scriptural tradition that all things must come in pairs, the NOAH’S ARK is back again to provide the second of a pair of appeals from a pair of trials involving a pair of claims for salvage and for damage done by the salvors. On the prior appeal, 5 Cir., 1961, 292 F.2d 437, 1961 AMC 1641, we reversed and remanded the case for a further trial on the “crucial matters occurring after the Noah’s Ark slipped off the sand dredge.” We affirmed much, however. Thus we said: “Established by the Trial Court’s findings and action by us are two things requiring no further inquiry: (1) valuable salvage services were rendered by the Cudjoe to the Noah’s Ark; and (2) the salvor was guilty of negligence for which it is legally responsible in casting off the Noah’s Ark without warning.” Reserved for the new trial and determination by the District Court on remand were the questions of the “amount of the salvage award, the extent to which is should be diminished if at all, the extent and nature of damage sustained by the Noah’s Ark for which the salvor is legally responsible under the applicable standards * * 292 F.2d 437, 443.

On the retrial based on the former record as supplemented by further oral testimony from only two live swearers, one a professional salvor, the other a marine surveyor, and each of whom had testified on the former trial, a different Judge arrived at these conclusions. The award to the salvors was fixed at $7500 based on a value of $20,000 for the NOAH’S ARK and $40,000 for the salvor CUDJOE. But out of a cross claim of some $18,000 for damages (and detention) for the NOAH’S ARK, only $1,931.91 was found to be attributable to the grounding.1 On striking the balance, the vessel owners are required to pay about $5500 to salvors for saving a vessel having a value of not more than $3000 as the result of damage sustained in the grounding and the subsequent sinking nine hours after the negligent act of the salvor.

At the outset, we must emphasize that it is not our function to retry these cases as we once could do. The clearly erroneous concept applies to admiralty as well as civil causes. Compagnia Maritima La Empressa, S. A. v. Pickard, 5 Cir., 1963, 320 F.2d 829. But for nautical as well as land-based litigation, we must also emphasize that such a review affords a greater latitude than would an appeal from a jury verdict. In the latter it is a question of substantial evidence. In the former, there is still the qualitative factor of the truth and right of the case — the impression [6]*6that a fundamentally wrong result has been reached. W. R. B. Corp. v. Geer, 5 Cir., 1963, 313 F.2d 750, 753.

Apart from valuation of the salvage service and the manner or extent to which it was to be diminished or lost by subsequent negligence of the salvor, there were two principal fact issues sent back for decision. First was the question whether the sinking of the NOAH’S ARK some nine hours after she fetched up against the dock could reasonably have been avoided by affirmative action on the part of her crew and owner. Second, assuming an answer to the first that sinking could have been avoided, there was the problem of distinguishing between those damages caused by the grounding, on the one hand, and those resulting from the subsequent sinking (and raising) of the vessel.

As to the first, the record is in some respects more positive than it was on the first trial. The professional salvor Glad-ding was recalled and testified at length in open court. He was positive that, while he successfully engaged in four or five other salvage jobs that same night, he had both time and facilities with which to pull the NOAH’S ARK off of the dock and tow her to a place of at least relative safety in the harbor. And there is no doubt that Gladding was around the dock about 9:00 p. m. available, so he says, to be employed. The Judge found that around 6:00 p. m. Gladding’s salving tugs were docked in the harbor a short distance away and were fully manned, equipped and available to remove the NOAH’S ARK. He also found that had “Mr. Gladding been contacted, salvage efforts could have been commenced in a matter of minutes and could have been completed before any damage more than minor scraping of the bottom and side could have occurred.” On this there was the further finding that “the failure to take any steps to save or protect this vessel after it had grounded constituted negligence on the part of the crew of the ‘NOAH’S ARK.’ This negligence was not foreseeable by the salvor and became a supervening proximate cause of all damage thereafter suffered by the vessel. The ‘ARK’ was in charge of her master and fully manned, and the master and crew were obligated to see to the safety of their own vessel, as they easily could have done by the reasonable exercise of ordinary seamen’s skills.”

To the extent this was a fact conclusion that Gladding was available and was capable of pulling the NOAH’S ARK away from the dock, we do not feel that there is sufficient basis for completely rejecting it. In effect Judge Dyer arrived at the same conclusion as did Judge Lieb earlier. Of course the matter is not free from doubt for the record now, as it did earlier, contains the pessimistic appraisal of the situation by the Feltons, who were both knowledgeable and interested. See 292 F.2d 437, 443.

But we find no basis whatsoever for the further conclusion that had Gladding “been contacted, salvage efforts could have been commenced in a matter of minutes and could have been completed before any damage more than minor scraping of the bottom and side could have occurred.” Stated most favorably to the salvor, Gladding never fixed the time it would take to remove the NOAH’S ARK from this dang'er at less than a couple of hours. Indeed, most of the questions to the marine surveyor witness eliciting expert opinions to distinguish specific items of damage caused by the grounding, rather than the subsequent sinking, were generally couched in terms of the vessel being pulled away by about 9:00 o’clock or in a couple of hours, etc. Consequently, it is overwhelmingly established that considerable time would have been taken. More than that, time brought damage. The angry sea was at work. The bow of the vessel had smashed into the dock. The outrigger boom was lashing about wildly doing extensive damage to the building on the adjacent pier. From the nature of this vessel, a small wooden hull being pounded against the rocky bottom, smashing against the adjacent dock and wallowing in seas being driven by near hurricane winds, it is certain that substantial dam[7]*7age was being done minute by minute during all of this time. The CUDJOE is responsible for all of this, and the uncertainties arise not from the fact of damage, but the calculation of consequences. See International Union of Operating Engineers, Local 653 v. Bay City Erection Co., 5 Cir., 1962, 300 F.2d 270, 272.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
322 F.2d 3, 1964 A.M.C. 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oil-screw-noahs-ark-v-bentley-felton-corp-ca5-1963.