Ohio Valley Environmental Coalition, Inc. v. United States Army Corps of Engineers

716 F.3d 119, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2013 WL 1987234, 76 ERC (BNA) 1557, 2013 U.S. App. LEXIS 9753
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 15, 2013
Docket12-1999
StatusPublished
Cited by4 cases

This text of 716 F.3d 119 (Ohio Valley Environmental Coalition, Inc. v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Valley Environmental Coalition, Inc. v. United States Army Corps of Engineers, 716 F.3d 119, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2013 WL 1987234, 76 ERC (BNA) 1557, 2013 U.S. App. LEXIS 9753 (4th Cir. 2013).

Opinions

Affirmed by published opinion. Judge NIEMEYER wrote the opinion, in which Chief Judge TRAXLER and Judge

WILKINSON joined. Judge WILKINSON wrote a separate concurring opinion.

OPINION

NIEMEYER, Circuit Judge:

In connection with a proposed surface coal mine adjacent to Reylas Fork (a stream) in Logan County, West Virginia, the West Virginia Department of Environmental Protection (“WVDEP”) issued Highland Mining Company a permit under the Surface Mining Control and Reclamation Act (“SMCRA”) to do the mining, finding that the proposed mine would not cause material damage to the hydrologic regime. The WVDEP also issued a water quality certification under § 401 of the Clean Water Act (“CWA”), concluding that the proposed mine would not cause or contribute to violations of the State’s EPA-approved water quality standards, as well as a National Pollutant Discharge Elimination System (“NPDES”) permit under CWA § 402, finding that the proposed sediment pond for the mine would not have significant adverse effects. Finally, the U.S. Army Corps of Engineers (the “Corps”) issued a fill permit under CWA § 404, authorizing Highland Mining to place rock overburden into the adjacent valley of Reylas Fork as part of the mining process. The Corps issued the permit without an environmental impact statement, finding that the fill would not have a substantial cumulative impact on the water quality in the relevant watershed.

Four environmental groups (collectively, the “Environmental Coalition”) commenced this action to challenge the fill permit issued under CWA § 404. The Environmental Coalition contends that the Corps, in conducting its analysis for the § 404 permit, “materially misapprehended” the baseline conditions in the relevant watershed, thus corrupting its analysis of [122]*122the cumulative impact that the mine would have on the streams in the watershed. It also contends that the Corps acted arbitrarily and capriciously in determining that the valley fill would not have a significant cumulative impact on the water quality in the relevant watershed.

The district court evaluated the data considered by the Corps, the Corps’ analysis, and the Corps’ conclusions and found that the Corps did not misapprehend the baseline conditions in the relevant watershed. Ohio Valley Envtl. Coalition, Inc. v. U.S. Army Corps of Eng’rs (“OVEC ”), 883 F.Supp.2d 627, 642-44 (S.D.W.Va.2012). It also found that the Corps analyzed a “wide array of evidence about water quality” to reach a reasoned decision that the individual and cumulative environmental impacts of the Corps’ CWA § 404 permit would not rise to the level of significance required to trigger the need for an environmental impact statement. Id. at 645. As the district court concluded, “[t]he Corps has analyzed the cumulative impacts, ‘articulated a satisfactory explanation for its conclusion,’ and thus has not acted arbitrarily or capriciously.” Id. (quoting Ohio Valley Envtl. Coalition v. Aracoma Coal Co., 556 F.3d 177, 209 (4th Cir.2009)).

For the reasons that follow, we affirm.

I

The mining operation proposed at the Reylas mine would involve removing mountaintop rock that covers the coal seams to be mined, placing the rock in the adjacent valley, extracting the coal, and replacing the rock on the mountaintop. See Bragg v. W. Va. Coal Ass’n, 248 F.3d 275, 286 (4th Cir.2001) (describing the process). Because the rock is broken up as it is removed from the mountaintop, its volume swells such that all of the rock would not be needed to restore the mountaintop. The excess rock, or overburden, would accordingly be left in the valley as permanent fill. See Kentuckians for the Commonwealth, Inc. v. Rivenburgh, 317 F.3d 425, 431 (4th Cir.2003). A sediment pond, as was typical, would be constructed below the valley fill to collect water until the valley fill is stabilized. See Aracoma Coal, 556 F.3d at 186. In connection with the Reylas mine, the overburden rock would be deposited in a valley that includes a stream called Reylas Fork. Reylas Fork flows into Bandmill Hollow, which in turn flows into Dingess Run. The Dingess Run watershed was the relevant area for assessing the mine’s cumulative impact.

To operate the Reylas mine, Highland Mining obtained a SMCRA permit from the WVDEP, a state agency that has assumed “exclusive jurisdiction over the regulation of surface coal mining and reclamation operations” on nonfederal lands. 30 U.S.C. § 1253(a). Highland Mining also obtained from the WVDEP a permit under CWA § 401, certifying that the discharge from the mine will be consistent with the State’s water-quality standards, and a permit under CWA § 402, authorizing the discharge of pollutants other than dredged or fill material into navigable waters. Finally, Highland Mining obtained a permit under CWA § 404 from the Corps to allow “the discharge of dredged or fill material into the navigable waters at specified disposal sites.” 33 U.S.C. § 1344(a).

Under guidelines issued by the EPA, the Corps could issue a § 404 permit only after concluding that the mining activity would not cause or contribute to violations of the State’s water-quality standards or to the significant degradation of waters of the United States. 40 C.F.R. § 230.10(b)(1), (c). In making that assessment, it had to comply with the National Environmental Policy Act (“NEPA”) and take a “hard look” at the potential environmental conse[123]*123quences of the activity. See Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). NEPA required federal agencies such as the Corps to prepare an environmental impact statement (“EIS”) for major federal actions that significantly affect the quality of the human environment. 42 U.S.C. § 4332(C). To decide if an EIS was required, the Corps had to prepare an environmental assessment. 33 C.F.R. § 230.10; 40 C.F.R. § 1501.3. If, after conducting the assessment, the Corps found that the proposed project would not, either individually or cumulatively, have a significant impact on human health or the environment, it could make a “finding of no significant impact” (“FONSI”), obviating the need for preparing an EIS. 33 C.F.R. § 230.11; see also 40 C.F.R. § 1508.13 (describing the contents of a FONSI).

Before evaluating Highland Mining’s application for a § 404 permit, the Corps gave public notice of the application and invited comment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
S.D. West Virginia, 2026
Coal River Mountain Watch v. Putnam
S.D. West Virginia, 2025
Forestwatch v. Lint
135 F. Supp. 3d 477 (D. South Carolina, 2015)
Kipperman v. Berg (In re Berg)
532 B.R. 162 (S.D. California, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
716 F.3d 119, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2013 WL 1987234, 76 ERC (BNA) 1557, 2013 U.S. App. LEXIS 9753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-valley-environmental-coalition-inc-v-united-states-army-corps-of-ca4-2013.