Ohio Edison Co. v. Public Utilities Commission

423 N.E.2d 438, 67 Ohio St. 2d 230, 21 Ohio Op. 3d 144, 1981 Ohio LEXIS 570
CourtOhio Supreme Court
DecidedJuly 15, 1981
DocketNo. 80-1509
StatusPublished
Cited by2 cases

This text of 423 N.E.2d 438 (Ohio Edison Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Edison Co. v. Public Utilities Commission, 423 N.E.2d 438, 67 Ohio St. 2d 230, 21 Ohio Op. 3d 144, 1981 Ohio LEXIS 570 (Ohio 1981).

Opinion

Per Curiam.

The focal point of this case is whether the costs resulting from the appellant-NACCO interim agreement, designed to ensure NACCO a $1,644 per ton profit and to assist NACCO in making capital improvements, are includable fuel costs, pursuant to Ohio Adm. Code 4901:1-11-01 (D). 1 In answering this question, we are mindful of the fact [232]*232that appellant, pursuant to R. C. 4909.191 (C),2 has the burden of demonstrating that its costs are fair, just and reasonable. It should also be noted that this court will not disturb the findings and order of the commission unless it appears from the record that such findings and order are manifestly against the weight of the evidence and are so clearly unsupported by the record as to show misapprehension or mistake or willful disregard of duty. Cleveland Elec. Illuminating Co. v. Pub. Util. Comm. (1975), 42 Ohio St. 2d 403, paragraph eight of the syllabus, certiorari denied 423 U. S. 986.

R. C. 4909.191 (D)3 empowers the commission to order a customer refund if a utility’s rates result from, inter alia: errors, imprudent or unreasonable fuel procurement policies and practices, or such other practices, policies, and factors as the commission considers appropriate. We have reviewed the entire record in this case and conclude that the commission’s order is amply supported by the facts.

Initially, the record demonstrates that, whether inadvertently or otherwise, appellant paid NACCO an amount in ex[233]*233cess of the $1,644 per ton profit that was agreed upon in the interim agreement. Despite the fact that appellant evidently believed that the $1,644 figure included, the 23.4 cents per ton profit, the evidence proves that appellant paid NACCO $1,644 per ton and an additional 23.4 cents per ton. In effect, appellant tendered a double profit payment to NACCO.

Secondly, there is simply no question, based on this record, that appellant paid NACCO for capital improvements which NACCO failed to make.

In essence, then, appellant (1) paid NACCO more than NACCO was due and (2) paid NACCO for structural improvements that never materialized. Hence, the commission correctly concluded that these overpayments were made in contravention of R. C. 4909.191 (D).

We note, significantly, that much of the evidence upon which the commission relied in making its findings and order was evidence directly supplied by appellant itself, through its own audits, investigations, studies and witnesses.

We categorically reject appellant’s contention that it is entitled to recover its actual fuel cost expenditures. R. C. 4909.191 (C) unambiguously entitles appellant to fair, just and reasonable costs. Appellant’s “actual cost” theory, if pursued to its logical conclusion, would enable a utility and a supplier to contract for fuel at disproportionately inflatedprices and pass these artificial costs along to the customers. This we refuse to legitimatize. As this court recently and unanimously stated in Ohio Power Co. v. Pub. Util. Comm. (1978), 54 Ohio St. 2d 342, 344:

“* * * Fuel adjustment clauses are not and may not be permitted to become a carte-blanche authorization to an electric utility to pass through to its tariff customers expenses other than fuel costs fairly attributable to the production of the service to those customers. * * *

“We perceive that the requirement of fairness which compels adjustment in rates to compensate utilities for escalating fuel costs also compels retrospective reconciliation to exclude charges identifiably resulting from unreasonable computations or inclusions.”

Finally, we are unable to find—and are unwilling to create —precedent establishing the proposition that the commission [234]*234was under a duty to defer its proceedings and order until appellant and NACCO resolved their contractual dispute, either through private negotiation or litigation. We note, parenthetically, that, while the commission issued its order on July 9, 1980, the appellant’s litigation with NACCO, in the Court of Common Pleas of Belmont County, did not commence until September of 1980, approximately five months after the commission’s hearings concluded and two months after the issuance of the commission’s order. 4 While the commission and this court recognize that appellant has considerable discretion in pursuing its legal rights against NACCO, we do not believe that the customers’ right to a refund of unjustifiable fuel charges is contingent on the ultimate disposition of the NACCO claim. In our judgment, the critical consideration in cases of this nature is the customers’ right to adequate utility service and facilities at just and reasonable rates. See, e.g., C & SOE v. Pub. Util. Comm. (1980), 64 Ohio St. 2d 175.

For all the foregoing reasons, we find that appellant’s costs resulting from the interim agreement with NACCO are not includable fuel costs. The commission correctly concluded that the charges resulting therefrom were not fair, just and reasonable. These conclusions are consistent with the manifest weight of the evidence and amply supported by the record. Cleveland Elec. Illuminating Co. v. Pub. Util. Comm., supra. Accordingly, the order of the commission is affirmed.

Order affirmed.

Celebrezze, C. J., W. Brown, Sweeney, Locher, Holmes and C. Brown, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
423 N.E.2d 438, 67 Ohio St. 2d 230, 21 Ohio Op. 3d 144, 1981 Ohio LEXIS 570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-edison-co-v-public-utilities-commission-ohio-1981.