Columbus & Southern Ohio Electric Co. v. Public Utilities Commission

413 N.E.2d 1208, 64 Ohio St. 2d 175, 18 Ohio Op. 3d 389, 1980 Ohio LEXIS 860
CourtOhio Supreme Court
DecidedDecember 23, 1980
DocketNo. 80-503
StatusPublished
Cited by3 cases

This text of 413 N.E.2d 1208 (Columbus & Southern Ohio Electric Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus & Southern Ohio Electric Co. v. Public Utilities Commission, 413 N.E.2d 1208, 64 Ohio St. 2d 175, 18 Ohio Op. 3d 389, 1980 Ohio LEXIS 860 (Ohio 1980).

Opinions

Per Curiam.

Appellant asserts that appellee’s refusal to authorize its recovery of the full cost of the emergency energy period violates due process by the taking of private property without just compensation.

We find no merit in appellant’s contention.

Appellant asserts that the Fifth and Fourteenth Amendments to the United States Constitution and Sections 1,16 and 19 of Article I of the Ohio Constitution have been violated by the refusal to allow recovery of the non-fuel costs.

Initially, it is noted that the appellee, by and through its statutory powers, has consistently disallowed utility companies, including appellant, from recovering the non-fuel costs associated with the emergency period in the instant cause. (See Re Ohio Edison Company, case No. 77-1249-EL-AIR et al. [November 17,1978], opinion and order at pages 21-22; Re Monongahela Power Company, case No. 78-625-EL-FAC [177]*177[November 22, 1978], opinion and order at pages 16-17, and cases cited therein.)

It is undisputed that appellee did order appellant, as well as other utility companies, to purchase energy power in order to prevent curtailment or interruption of service during the emergency period.

Dispositive of appellant’s claim of an unjust taking of private property is the fact that appellee simply ordered appellant to do only that which appellant had a statutory obligation to provide for the public.

R. C. 4905.22, which reads in the imperative, states that appellant must furnish adequate service to its customers, and provides as follows:

“Every public utility shall furnish necessary and adequate service and facilities, and every public utility shall furnish and provide with respect to its business such instrumentalities and facilities, as are adequate and in all respects just and reasonable. All charges made or demanded for any service rendered, or to be rendered, shall be just, reasonable, and not more than the charges allowed by law or by order of the public utilities commission, and no unjust or unreasonable charge shall be made or demanded for, or in connection with, any service, or in excess of that allowed by law or by order of the commission.”

Therefore, appellee imposed no new or additional obligations upon appellant but rather reaffirmed existing statutory obligations. Therefore, there was no taking of private property and, thus, no due process violations.

Furthermore, it is noted that the purpose of appellee’s order directing the “purchase [of] all available power” was simply to preserve the integrity of the interconnected network of facilities among electric utility companies. The failure of one utility to maintain an adequate level of reserve power could initiate a regional blackout, which would adversely affect even those utilities with sufficient coal supplies. Therefore, ap-pellee’s order, in effect, gave appellant an unquantified benefit by assuring that no other utility’s failure to provide energy would adversely reflect upon the appellant’s ability to provide future services.

Finally, it is noted that a public utility has no constitutional [178]*178right to recover past and unrecovered costs through present and future rates. Bluefield W. W. & Improvement Co. v. Public Service Comm. (1923), 262 U. S. 679.

For the foregoing reasons, the order of the Public Utilities Commission is affirmed.

Order affirmed.

Celebrezze, C. J., W. Brown, P. Brown, Sweeney, Locher and Dowd, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Office of Consumers' Counsel v. Public Utilities Commission
453 N.E.2d 584 (Ohio Supreme Court, 1983)
Dayton Power & Light Co. v. Public Utilities Commission
447 N.E.2d 733 (Ohio Supreme Court, 1983)
Ohio Edison Co. v. Public Utilities Commission
423 N.E.2d 438 (Ohio Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
413 N.E.2d 1208, 64 Ohio St. 2d 175, 18 Ohio Op. 3d 389, 1980 Ohio LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-southern-ohio-electric-co-v-public-utilities-commission-ohio-1980.