O'Hare v. District of Columbia

18 Ct. Cl. 646, 1883 U.S. Ct. Cl. LEXIS 23, 1800 WL 1351
CourtUnited States Court of Claims
DecidedMay 28, 1883
DocketNo. 24
StatusPublished
Cited by2 cases

This text of 18 Ct. Cl. 646 (O'Hare v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Hare v. District of Columbia, 18 Ct. Cl. 646, 1883 U.S. Ct. Cl. LEXIS 23, 1800 WL 1351 (cc 1883).

Opinion

OPINION.

Scofield, J.,

delivered the opinion of the court:

In this case the parties are wide apart. The demands of the claimant, according to his amended brief, amount to $15,017.78. The defendant, while contesting them all except $4,002.02, sets up counter-claims amounting to $13,049.30. In disposing of the disputed items we are required to revise and rejudge the [677]*677decisions, settlements, and allowances made by the Board of Public Works, or by the Commissioners, engineers,, and auditor of the District, or by the Board of Audit. The accounts are numerous and stale,, and the evidence scanty, confused, and contradictory.

In matters of counter-claim the burden of proof is upon the defendant. Evidence that would not justify a finding for the claimant were he in the affirmative of the issue may still be too weak to justify a finding against him where the defendant is in the affirmative. Under this rule we have been constrained to leave undisturbed payments- of a questionable character which have been authorized by some of those officers.

The three items of claim set out in finding Y are not in controversy. They amount to $4,002.02.

The first item in dispute is dependent upon the construction to be given to claimant’s agreement to “receive the prices established and paid by the Board of Public Works” in the several extensions of contract No. 835, taken in connection with the modification presented in finding II. Contract No. 835 is in finding I, and its many extensions in finding III. The claimant contends that all these extensions are brought under the 20 per cent, modification, and for all sewer work done under them he is entitled to 20 per cent, upon the prices allowed in the original contract No. 835. The defendant has already paid all but the 20 per cent. The 20 per cent, additional on the work done amounts to $5,530.69. The following is the modification :

Extension of contract.
No. 835.
It is hereby agreed that this contract, .with its various terms, conditions, and stipulations (except as respects the time of execution), shall he modified and extended so as to embrace an increase of twenty per centum upon the prices in the foregoing contract.
Witness our hands and seals the eighteenth day of October, A. D. 1873.

Here is one of the extensions. So far as this question is concerned, they are all alike:

Extension of contract Eo. 835.
June 17, 1875.
For and in consideration of the stipulations hereinafter contained, it is agreed, by and between the Commissioners of the District of Columbia and [678]*678Owen O’Hare, that contract No. 835 in tlie series of contracts made by the Board of Public Works of the District of Columbia be,' and the same is hereby, extended, with its various terms, conditions,' and stipulations, to embrace the following works viz: Lay and put down a 12-inch pipe-sewer in the alley in the square No. 278.
It is further agreed that the said Uwen O’Hare shall receive the prices established and paid by the Board of Public Works for work of similar character; provided that payment shall be made in the bonds issued by the sinking-fund commissioners of the District of Columbia, under and by virtue of section 7 of the act of Congress approved June 20, 1874, which bonds shall be accepted and received at their par value.

We do not understand that tbe “prices established and paid by the Board of Public Works” refer simply to the prices agreed upon in contract No. 835, either by itself or with its modification. Independent of that particular contract, the Board had established a scale of prices, as shown in finding IX, to which that contract itself conformed. If it had been the intention to pay the prices of No. 835, with the 20 per cent, modification, it was not only unnecessary, but confusing, to insert the words “prices established and paid.” They seem to have been inserted to avoid such a conclusion. If the parties had so agreed, they would most certainly have added “ with 20 per cent, additional.”

At that time claimant had two other contracts, as appears in finding IY, dated August 13, 1873, and September 1, 1873. They were for sewer work at the prices named in the original of No. 835. He did not even request to have the prices increased. He made another contract for similar work December 1, 1873, at the same prices. These contracts also had extensions in which it was stipulated that claimant should “receive the prices established and paid by the Board of Public Works,” not the prices agreed to in No. 835. That contract conformed to the standard prices, but it did not establish them. At that time the claimant himself must have understood the extensions as the defendant now understands them, for he settled all this work at the established prices, not only without complaint but without any suggestion that he was entitled to 20 per cent. more. This item of the claim must therefore be rejected. In arriving at this conclusion, we consider the modification as it stands in the findings. The question as to its reformation is discussed in another place.

The second item of claim consists of an alleged undermeasure[679]*679ment of tbe excavation in sewer trenchés. The facts appear in-finding IY. For pipe sewers, the width of the trenches was not. definitely fixed by contract, nor by the subsequent direction of the engineers; nor was it the practice of the engineers to measure the amount of excavation by the size of the trench. They measured or calculated according to an arbitrary rule, called in engineering parlance a constant. The constant adopted and followed by the engineers, under the Board of Public Works assumed the trench to be 20 inches wider at the bottom than the pipe, with a slope upward and outward of one foot in ten. To the contractor a narrow trench had some advantages and some disadvantages. He had to move less earth, but the danger of caving was increased and the safety and comfort of the workmen diminished. He might have his choice, but, whether wide or narrow, by this constant the trench yielded the same amount of measured excavation. Under contract No. 835 the claimant made narrow trenches, but' during the administration of the Board of Public Works the excavations were measured by this constant and he was paid accordingly. At the time the Board was abolished there was some of this excavation not yet measured. The Commissioners, under the advice of Lieutenant Hoxie, adopted a different constant, arbitrary like the other, but approximating more nearly the actual excavation. By this constant claimant’s allowance for excavation was greatly diminished. He remonstrated earnestly, but finally accepted the amount offered.

By the terms of the contract the parties were to abide the measurement of the engineers, but this, as we held in the Neitzey Case (17 C. Cls. R., 111), is not conclusive. The claimant having incurred the danger and inconvenience of narrow trenches while the former constant was in practice, was entitled to be paid by it for all work done prior to the change. The amount to be allowed is $309.55.

The sewer excavations subsequent to the change of constant were under extensions made long after.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richtman v. United States
47 Ct. Cl. 483 (Court of Claims, 1912)
Barnes v. District of Columbia
22 Ct. Cl. 366 (Court of Claims, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
18 Ct. Cl. 646, 1883 U.S. Ct. Cl. LEXIS 23, 1800 WL 1351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohare-v-district-of-columbia-cc-1883.