Neitzey v. District of Columbia

17 Ct. Cl. 111
CourtUnited States Court of Claims
DecidedDecember 15, 1881
StatusPublished
Cited by6 cases

This text of 17 Ct. Cl. 111 (Neitzey v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neitzey v. District of Columbia, 17 Ct. Cl. 111 (cc 1881).

Opinion

Nott, J.,

delivered the opinion of the court:

The claimant has brought his action against the District of Columbia to recover $269.34, and the defendant has set up matters by way of counter-claim to the amount of $3,194.87. As to the claimant’s demand, it is conceded that he should recover. The real controversy grows out of the counter-claim.

[122]*122As to the first item of that counter-claim, $111.87, it arose in settlement of the same contract upon which the claimant sues, and it is a clear case of overpayment in mistake of fact, the mistake, moreover,' being clerical; i. e., the writing of 1,554 instead of 1,654. illhe court has not the slightest doubt of the defendant’s right to have it deducted from the claimant’s recovery. Graver and more doubtful questions spring out of the second and third items of the counter-claim, which are to recover back $2,740.40 and $342.60 for overpayments made in mistake of fact upon another and distinct contract. The essential facts relating to the former of these two counter-claims are these:

The board of public works of the former government of this District entered into a great number of contracts with many different contractors for grading, paving, and otherwise improving the streets of Washington. These contracts were prepared by the board and were upon printed blanks, and often were substantially in the same language. They provided that payments should be made upon the estimates and certificates of the chief engineer of the .board, and each contractor expressly agreed that no money should become due and payable under his contract “ exceptupon the certificate of said engineer,” and that he should not be entitled to demand or receive payment for any portion of his work “except in the manner set forth in this agreement.” The agreements also contained an article expressly declaring that the measurements should be made “by the engineer of the board or his assistant.”

In a word, these contracts belong to the class where the parties agree that a third person, ordinarily an architect or engineer, shall act as arbitrator between them in determining the quantity and quality of the work, and the contractor agrees to produce the engineer’s certificate of approval as a condition precedent to demanding payment. If the cases came into court to be determined according to the letter of each'contract, there could not be a doubt as to the effect of these provisions. But now we must take judicial cognizance of the fact that the contractors with the board of public works went to Congress for relief; that they asserted that the other contracting party had been delinquent in making payments; that they represented that in consequence of the haste in which measurements and estimates were made by the engineers and officers of the Dis[123]*123trict grave mistakes bad been made; and that they conceded that they had no legal remedy against the District, and appealed to the conscience of Congress as their only hope of redress. We also know that these appeals and these representations went on for years, and that the contracts, the proceedings and acts of the board of public works, the proceedings and acts of the board of audit, the accounts between- the parties, the estimates of the engineers, and every conceivable thing relating to the controversies were reported and made known to Congress. With this knowledge brought home in every conceivable way to every member of the two houses of Congress, the District-claims Act, 16th June, 1880 (1 Supplmt. B. S., 562), was passed. We cannot suppose that Congress passed that act in ignorance of the law of contracts or with the intent that this class of claimants should be turned out of court without legal redress. On the contrary, we believe that the statute is to be interpreted by the principle reiterated by this court in the Caldera Gases (15 C. Cls. B., 546), the Dahlgren Case (16 id., 30), and the case of Braden & Angus (td., 389,411), and that Congress as the supreme legislative power of the District, speaking for and in the stead of the defendant, agreed to waive the condition precedent prescribed by the contracts and to consent to an adjudication upon the merits.

In the present case, the defendant has established the fact that the claimant was paid in 1872 for laying 14,138]) square yards of Belgian pavement on Twelfth street. The fact is also established, to the satisfaction of the court, that the measurement then certified to by the defendant’s engineers was erroneous; that but 13,254 square yards were laid, and that there was consequently an error of 884 yards for which the claimant was overpaid. But his counsel strenuously contended on the hearing that this branch of the counter-claim must fail because the remeasurement had not been made by either of the engineers designated by the contract as the person who should make all measurements under it.

It may be conceded that that would be the result if the par-* ties had come into court in their original plight, with nothing between them but the contract as they originally made it; but they now come into court with what is substantially a subsequent agreement, that is to say, under the Act 1880, to the ■ terms, and conditions of which they have both consented, the [124]*124one by bringing Ms action, tbe other by the enactment of its supreme legislature; and the real question is, whether the benefit conferred by the act on the claimant in striking out, in effect, this clause of the contract is reciprocal, and whether, when the claimant has brought into court one contract, the defendant may bring into court another.

It must be conceded by all parties, it cannot be doubted by an3 rational mind, that the general purpose of Congress was to do justice between these parties. It cannot be supposed that Congress intended to throw down technicalities which stood in the way of the claimant and leave them standing in the wajr of the defendant. The legislative intent could not have been that a contractor might pick out one of a dozen distinct transactions ami bring it into court and recover a judgment upon it if he were really indebted to the District in the other eleven. Still, the practical question which follows is, whether Congress have effected this purpose of doing absolute justice between the parties by appropriate legislation, or whether it has been left a casus omissus.

The claimant brings his action to recover a balance due to him upon one contract, and the defendant seeks to recover back an alleged overpayment made upon another contract. This is not a defense in any manner growing out of the transaction which the claimant has brought into court, but is a distinct cause of action and must be sustained, if it can be sustained at all, as a cross-action seeking affirmative relief, under that provision of the Act 1880 (§3) which says that the Attorney-General shall have authority to defend the District of Columbia against all such claims in like manner as he is now by law required to defend the United States in said court, ioith the same power to interpose counter-claims and offsets.”

This term counter-claim is a term unknown to the common law, and indeed was first introduced into modern statutory practice by the New York Code of Procedure of 1848. It was then criticised as being a. term unknown to any system of law, but was soon interepreted in accordance with the comprehensive signification of its words as meaning something more than set-off and embracing every cause of action of like nature which might have been the subject of a separate action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyons v. District of Columbia
19 Ct. Cl. 642 (Court of Claims, 1884)
Childs v. District of Columbia
19 Ct. Cl. 332 (Court of Claims, 1884)
Looney v. District of Columbia
19 Ct. Cl. 230 (Court of Claims, 1884)
Morgan v. District of Columbia
19 Ct. Cl. 164 (Court of Claims, 1884)
O'Hare v. District of Columbia
18 Ct. Cl. 646 (Court of Claims, 1883)
Campbell v. District of Columbia
18 Ct. Cl. 193 (Court of Claims, 1883)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ct. Cl. 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neitzey-v-district-of-columbia-cc-1881.