Opinion
CALLAHAN, C. J.
The sole issue raised in this administrative appeal is the proper interpretation of Public Acts 1995, No. 95-43, § 1 (c), now codified as General Statutes § 16-19b (c),1 which authorizes the department [20]*20of public utility control to approve an energy adjustment clause for an electric company to be superimposed on the company’s base rate schedule. The named defendant, the department of public utility control (department), approved an energy adjustment clause for the defendant Connecticut Light and Power Company (power company), in accordance with the provisions of § 16-19b (c).2 The plaintiff, the office of consumer counsel, a full participant in the hearings that led to the approval of the power company’s energy adjustment clause, appealed from the decision of the department to the Superior Court pursuant to General Statutes §§ 4-183 and 16-35.3 The plaintiff asserted that the department failed to protect ratepayer interests to the extent [21]*21required by statute, and that approval of the power company’s energy adjustment clause was arbitrary, capricious and unreasonable. The trial court concluded that the department’s factual and legal conclusions were legally and logically supportable and affirmed the department’s decision. The plaintiff appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to ourselves pursuant to Practice Book § 4023, now § 65-1, and General Statutes § 51-199 (c). We affirm the judgment of the trial court.
The following facts are relevant to the determination of this appeal. The department is a state agency authorized pursuant to title 16 of the General Statutes to regulate and supervise the operation of public service companies. The power company is a public service electric company as defined in General Statutes § 16-1 (4) and (8). It is, therefore, subject to regulation by the department. The plaintiff is “the statutory advocate for consumer interests in all matters which may affect Connecticut consumers with respect to public service companies . . . .” General Statutes § 16-2a (a).4
[22]*22Pursuant to its rate setting authority, the department, in a general rate proceeding, establishes the rate that an electric company must charge consumers. General Statutes §§ 16-19 (a) and 16-19e.5 This rate is commonly [23]*23referred to as the “base rate.” Because the base rate reflects a prospective anticipation of what rate will be [24]*24necessary adequately to compensate an electric company, it is necessary for the department to make several reasoned assumptions regarding future events in setting the base rate. The assumptions relevant to this appeal are those regarding the anticipated fuel related costs that the company will incur in the future. Among other things, the department must make a reasonable assumption regarding an electric company’s generation mix, that is, the anticipated ratio of nuclear power that will be available to the company from which to generate electricity to the amount of fossil fuel6 that the company will require in order to generate an adequate supply of electricity. The power company has been given an anticipated nuclear generation capacity factor of 72 percent by the department in its most recent rate proceeding.7 If that forecast proves to be incorrect, the power company must obtain either more or less fossil fuel than predicted to make up for the variation in the anticipated availability of nuclear power. The costs associated with obtaining fuel will vary depending on the amount, type and price of the fuel needed. The department must make certain reasonable assumptions pertaining to the cost of obtaining these fuels. If the assumptions with respect to the generation mix or the costs prove inaccurate, the base rate will not accurately reflect an electric company’s actual costs.8 If the company actually incurs lower costs than expected, receipt [25]*25of the base rate will overcompensate the company to the detriment of ratepayers. If the company’s actual costs exceed those that are expected, collection of only the base rate will result in undercompensation to the company.
In response to this potential inequity, the legislature authorized the department to adopt certain formulae for each electric company that would permit interim rate adjustments for fuel related cost variations.9 See General Statutes (Rev. to 1995) § 16-19b (a) and (g).10 These formulae were to be integrated with the base rate formula when appropriate and a new rate, either higher or lower, would be determined to reflect the actual costs incurred by the company. A fossil fuel adjustment clause allowed adjustments when costs varied because of unanticipated changes in the price of fossil fuels. General Statutes (Rev. to 1995) § 16-19b (a). A generation utilization adjustment clause worked with the fossil fuel adjustment clause and allowed rate adjustments when costs varied as a result of an unanticipated change in the generation mix. General Statutes (Rev. to 1995) § 16-19b (g).
Although accurate reflection of an electric company’s actual costs was the intended purpose of these formulae, it had become apparent in recent years that the [26]*26fossil fuel adjustment clause and generation utilization adjustment clause were not effective in adjusting the base rate downward to reduce rates when the electric company was able to operate below its anticipated costs. Thus, electric companies, but not necessarily ratepayers, were benefiting by the operation of the fossil fuel adjustment clause and generation utilization adjustment clause. In 1995, the legislature enacted § 16-19b (c) authorizing the department to approve a new energy adjustment clause to replace the fossil fuel adjustment clause and generation utilization adjustment clause then existing for each electric company. Public Acts 1995, No. 95-43, § 1 (c). The purpose of the law was to create a single formula that would operate more consistently in protecting both ratepayers and electric companies by fully tracking all fuel related costs and permitting adjustments that accurately would reflect actual costs.11 See 38 S. Proc., Pt. 5, 1995 Sess., pp. 1756-58, remarks of Senator Stephen R. Somma; 38 H.R. Proc., Pt. 4, 1995 Sess., p. 1252, remarks of Representative John W. Fonfara. Pursuant to § 16-19b (c), the department, after a hearing and a determination that the standards set forth in the statute would be met by an energy adjustment clause, approved an energy adjustment clause for the power company to replace its existing fossil fuel adjustment clause and generation utilization adjustment clause.12
[27]*27The plaintiff presents two arguments in support of its claim that the department’s approval of the power company’s energy adjustment clause was invalid. Both arguments relate to the proper interpretation of the first sentence of § 16-19b (c), in which the standard for approval of an energy adjustment clause by the department is set forth. Section 16-19b (c) provides in relevant part that “[i]f the department, after notice and hearing, determines that the adoption of an energy adjustment clause would protect the interests of ratepayers of an electric company, ensure economy and efficiency in energy production and purchase by the electric company and achieve the objectives set forth in subsection (a) of section 16-19 and in section 16-19e better than would the continued operation of a fuel adjustment clause and a generation utilization adjustment clause, the department shall approve an energy adjustment clause . . . .” (Emphasis added.) Both of the plaintiffs arguments rest exclusively on the proper statutory construction of the first clause of that sentence in which the ratepayer protection standard is set forth.
I
The plaintiff first asserts that the ratepayer protection standard set forth in § 16-19b (c) is an “intrinsic” standard that permits the department to approve only those energy adjustment clauses that protect the interests of ratepayers absolutely. The defendants argue, and the trial court agreed, that the standard is a “relative” one, requiring only that ratepayer interests need only receive greater protection under the energy adjustment clause [28]*28than they received under the former fossil fuel adjustment clause and generation utilization adjustment clause.13 According to the plaintiffs interpretation, § 16-19b (c) requires some undefined quantum of ratepayer protection that must be achieved in the abstract without any reference to the ratepayer protection available under the former fossil fuel adjustment clause and generation utilization adjustment clause.14
The plaintiff would interpret the energy adjustment clause approval standard set forth in § 16-19b (c) as if it read that the department shall grant approval of an energy adjustment clause for an electric company only if the energy adjustment clause would: (1) protect the interests of ratepayers absolutely; (2) ensure economy and efficiency absolutely; and (3) achieve the objectives set forth in §§ 16-19 (a) and 16-19e better than the continued operation of the electric company’s then existing fossil fuel adjustment clause and generation utilization adjustment clause.15 Under the plaintiffs interpretation, therefore, the § 16-19b (c) modifying phrase “better than would the continued operation of a [fossil] fuel adjustment clause and a generation utilization adjustment clause” would modify only the last clause of the [29]*29sentence relating to achieving the specified statutory objectives. According to the defendants and the trial court, that phrase must be read to modify all three of the standards set forth in the first sentence of § 16-19b (c), so that approval of an energy adjustment clause is required if the department finds, inter alia, that the energy adjustment clause would protect ratepayer interests better than would the fossil fuel adjustment clause and generation utilization adjustment clause. We agree with the defendants.
In resolving this dispute, we rely on well established mies of statutory construction. “Statutory constmction is a question of law and therefore our review is plenary. . . . We . . . must effectuate the expressed [legislative] intent. . . . [0]ur fundamental objective is to ascertain and give effect to the apparent intent of the legislature. . . . Ordinarily, if the language of a statute is plain and unambiguous, we need look no further than the words themselves because we assume that the language expresses the legislature’s intent. ... In seeking to discern that intent, we look to the words of the statute itself, to the legislative history and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to its relationship to existing legislation and common law principles governing the same general subject matter.” (Citation omitted; internal quotation marks omitted.) Charles v. Charles, 243 Conn. 255, 258-59, 701 A.2d 650 (1997); State v. Spears, 234 Conn. 78, 86-87, 662 A.2d 80, cert. denied, 516 U.S. 1009, 116 S. Ct. 565, 133 L. Ed. 2d 490 (1995).
The plain language of § 16-19b (c) suggests that the phrase “better than [the existing fossil fuel adjustment clause and generation utilization adjustment clause]” was intended to modify each of the three preceding clauses. Had the legislature intended that it modify only the last clause, it would have indicated in some fashion [30]*30that the first and second clauses were independent of the third clause and the “better than” modifier. It could have accomplished this separation of the clauses by enumeration or by placing a semicolon after each of the first two clauses to indicate that they are clearly distinct from the third clause and its purportedly exclusive modifier. In any event, for the plaintiffs interpretation to be viable, it would be necessary for the final clause to be set off in some fashion to incorporate the modifier exclusively into that final clause.
Moreover, the legislative purpose and history confirm that the legislature intended the phrase “better than [the existing fossil fuel adjustment clause and generation utilization adjustment clause]” to modify the first clause relating to the protection of ratepayer interests. In explaining the bill, Somma stated: “This bill. . . essentially eliminates the fuel adjustment clause, as well as the [generation] utilization adjustment clause, and allows the Department to establish a broader adjustment clause to authorize an electric company to modify its rates to reflect changes in those rates, and costs in those rates. Before the new clause could be adopted . . . the Department must find that it actually would better protect the ratepayers’ interests.’’ (Emphasis added.) 38 S. Proc., supra, p. 1756. When asked how the bill would ensure that an electric company would not receive an excessive rate of return, Somma responded that “the new energy adjustment clause . . . has to be found to be in the interests, better interests of the ratepayers before it’s actually adopted. . . . [T]he [department] must find that it’s first in the, in the ratepayers’ interest and would better protect them before this new clause could be adopted. . . . [T]his would better pro tect the ratepayers’ interests . . . .’’(Emphasis added.) Id., pp. 1757-58. In the three brief pages of legislative history in the Senate, Somma refers to better protecting the interests of ratepayers no less than four [31]*31times. There can be little doubt in the face of this legislative history that the legislature intended the phrase “better than [the existing fossil fuel adjustment clause and generation utilization adjustment clause]” to modify the first clause relating to protecting ratepayer interests.
In addition, the legislative purpose in adopting § 16-19b (c) lends support to our conclusion that the legislature intended that ratepayer protection under the energy adjustment clause formula be better relative to the then existing fossil fuel adjustment clause and generation utilization adjustment clause formulae. The legislature’s primary reason for adopting this legislation was dissatisfaction with the performance of the fossil fuel adjustment clause and generation utilization adjustment clause and the inability of those formulae to protect ratepayers by reducing the base rate when the electric company operated below its anticipated costs. See 38 S. Proc., supra, p. 1756. Because the fossil fuel adjustment clause and generation utilization adjustment clause were intended to protect ratepayer interests, it is reasonable to interpret § 16-19b (c) as requiring that the energy adjustment clause provide better protection than the fossil fuel adjustment clause and generation utilization adjustment clause.
We conclude that the department’s approval of an energy adjustment clause is appropriate if the department finds that the energy adjustment clause will, inter alia, protect ratepayer interests better than would the existing fossil fuel adjustment clause and generation utilization adjustment clause. The department properly interpreted § 16-19b (c) as creating a “relative” rather than an “intrinsic” standard with respect to the protection of ratepayer interests. The trial court’s affirmance of the department’s interpretation of the ratepayer protection standard in that respect was, therefore, correct.
[32]*32II
By way of an alternative argument, the plaintiff contends that the department has exceeded the scope of its statutory authority pursuant to § 16-19b (c) by approving an energy adjustment clause that “imposed risks of generation plant management on [the power company’s] ratepayers . . . .”16 By the phrase “risks of generation plant management,” the plaintiff refers to those variations in anticipated costs that occur as a result of management decisions, as opposed to variations that occur as a result of some independent action such as an act of God or market forces. Specifically at issue, according to the plaintiff, is the possibility that the energy adjustment clause might permit the power company to pass through to its ratepayers those management risks associated with the operation of its nuclear generation facilities.17 The plaintiff rests its argument on its interpretation of the ratepayer protection standard in § 16-19b (c). In the plaintiff’s view, the imposition of management risks is antithetical to the concept of ratepayer protection, even if that requirement is interpreted as relative rather than intrinsic.
[33]*33The plaintiffs argument with respect to the impermissibility of shifting economic risk is essentially twofold. The first argument focuses on the department’s factual determination. The plaintiff asserts that because the energy adjustment clause shifts more costs associated with management risks to ratepayers, the department could not conclude that the energy adjustment clause protects ratepayer interests better than do the fossil fuel adjustment clause and generation utilization adjustment clause. In its second argument, the plaintiff maintains that the ratepayer protection standard in § 16-19b (c) must be interpreted as an absolute prohibition on the imposition on ratepayers of any generation plant management risks associated with its nuclear operations. We are not persuaded by either argument.
A
The plaintiff asserts that the record demonstrates that the energy adjustment clause approved for the power company improperly passes along economic risks to ratepayers. Its means of reaching this conclusion is somewhat circuitous. First, it asserts that the energy adjustment clause proposed by the power company would impose more risk on ratepayers than would its former fossil fuel adjustment clause and generation utilization adjustment clause. It further asserts that the energy adjustment clause actually approved by the department is “substantially identical” to that which was proposed by the power company. It argues, therefore, that the energy adjustment clause actually approved passes along more economic risks than did the former fossil fuel adjustment clause and generation utilization adjustment clause and, thus, does not provide better ratepayer protection. By way of proof of its assertion that the proposed energy adjustment clause imposes more economic risks than the fossil fuel adjustment clause and generation utilization adjustment clause, the plaintiff points to a single piece of evidence [34]*34in the record. It notes that one expert testified that adopting the energy adjustment clause proposed by the power company would be beneficial for the power company because the power company would be perceived as a less risky enterprise in the financial community with the energy adjustment clause in place, with the result that it would be able to attract more capital at lower costs. In the plaintiffs view, this demonstrates that the energy adjustment clause proposed by the power company would provide less ratepayer protection than did the fossil fuel adjustment clause and generation utilization adjustment clause because if the power company is perceived as being in a better economic position, then clearly the ratepayers are in a worse position. Because the energy adjustment clause that was proposed by the power company is similar to the actual energy adjustment clause approved by the department, the plaintiff maintains that the actual energy adjustment clause must pass along more risks and provide less ratepayer protection than the power company’s fossil fuel adjustment clause and generation utilization adjustment clause.18
While the proposed and actual energy adjustment clauses may be similar in a variety of respects, the department expressly refused to adopt the power company’s proposal because it concluded that the proposal would not protect ratepayer interests sufficiently.19 The department specifically concluded that the then existing fossil fuel adjustment clause and generation [35]*35utilization adjustment clause also did not protect ratepayer interests sufficiently because “the [fossil fuel adjustment clause] does not adjust for differences in cost that result from changes in the mix of generation. The [generation utilization adjustment clause] was implemented to complement the [fossil fuel adjustment clause] by adjusting for changes in said costs. It no longer does so. . . . The [department concludes that the continued use of [the power company’s fossil fuel adjustment clause] and [generation utilization adjustment clause] do not protect the interests of [the power company’s] ratepayers . . . .” The department thereafter crafted its own energy adjustment clause for the power company, drawing on some aspects of the power company’s proposals, and approved an energy adjustment clause that it found would protect ratepayers’ interests better than the existing fossil fuel adjustment clause and generation utilization adjustment clause.20
We begin our analysis by noting that our review of an agency’s factual determination is constrained by the Uniform Administrative Procedure Act (act). General Statutes §§ 4-166 through 4-189. Specifically, General Statutes § 4-183 (j) (5) mandates that a court “shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court shall affirm the decision of the agency unless the court finds that substantial rights of the person appealing [36]*36have been prejudiced because the administrative findings, inferences, conclusions, or decisions are . . . clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record . . . We have interpreted the standard of review set forth in the act as limiting our review such that “[w]ith regard to questions of fact, it is neither the function of the trial court nor of this court to retry the case or to substitute its judgment for that of the administrative agency.” (Internal quotation marks omitted.) Connecticut Light & Power Co. v. Dept. of Public Utility Control, 219 Conn. 51, 57, 591 A.2d 1231 (1991); see DiBlasi v. Zoning Board of Appeals, 224 Conn. 823, 829-30, 624 A.2d 372 (1993). An agency’s factual determination must be sustained if it is reasonably supported by substantial evidence in the record taken as a whole. Connecticut Resources Recovery Authority v. Planning & Zoning Commission, 225 Conn. 731, 744, 626 A.2d 705 (1993); Connecticut Light & Power Co. v. Dept. of Public Utility Control, supra, 57. Substantial evidence exists if “the administrative record affords a substantial basis of fact from which the fact in issue can be reasonably inferred.” (Internal quotation marks omitted.) Connecticut Building Wrecking Co. v. Carothers, 218 Conn. 580, 601, 590 A.2d 447 (1991); Connecticut Light & Power Co. v. Dept. of Public Utility Control, supra, 57. This “substantial evidence” standard is highly deferential and permits less judicial scrutiny than a “clearly erroneous” or “weight of the evidence” standard of review. Connecticut Light & Power Co. v. Dept. of Public Utility Control, 216 Conn. 627, 640, 583 A.2d 906 (1990).
The plaintiff has failed to point to anything in the record from which we can conclude that the energy adjustment clause actually approved by the department does not protect ratepayer interests better than the former fossil fuel adjustment clause and generation utilization adjustment clause, let alone meet its heavy burden of demonstrating that the department’s factual [37]*37conclusion lacks substantial support on the whole record. Even if we assume that the plaintiff is correct and the expert testimony regarding the benefit to the power company from its proposed energy adjustment clause would carry over and be applicable to the energy adjustment clause actually adopted, we cannot conclude from that single scrap of testimony that, on the whole, the energy adjustment clause would not protect ratepayer interests better than the existing fossil fuel adjustment clause and generation utilization adjustment clause. The plaintiffs zero-sums analysis of the relationship between ratepayers and the electric company, that is, that a gain for one side necessarily entails a loss for the other, is insupportable. The ability of an electric company to attract capital at lower rates inures directly to the benefit, not the detriment, of its ratepayers. The company’s capital costs are passed through to the consumer pursuant to § 16-19e (a) (4), and if capital costs are lower, the rates charged to consumers will be lower. The department is directed by § 16-19b (c), in reference to § 16-19e (a) (4), to consider the electric company’s need “to attract needed capital and to maintain [its] financial integrity . . . .’’Although some risks may be passed through to ratepayers, the department reasonably could have concluded that the reduced capital costs sufficiently counterbalance that detriment to make the energy adjustment clause better for ratepayers than the fossil fuel adjustment clause and generation utilization adjustment clause. We conclude that the plaintiff has failed to meet its burden of proving that the record is devoid of substantial evidence to support the department’s factual determination that the power company’s approved energy adjustment clause will provide more ratepayer protection than its former fossil fuel adjustment clause and generation utilization adjustment clause.21
[38]*38B
The thrust of the plaintiffs second argument is that it is never permissible for interim cost variations, namely, costs that vary from those that were anticipated in setting the base rate at the regular rate hearing, to be passed through to ratepayers if those cost variations are attributable to management risks. It maintains that this is true regardless of whether the costs were prudently or imprudently incurred and regardless of whether the variation will inure to the benefit of ratepayers as a rate decrease or to the company as a rate increase. The plaintiff does not deny that management risks may be passed through, but asserts that it may be done only in the regular rate proceeding through the establishment of the base rate. The sole basis for the plaintiffs argument is its interpretation of the ratepayer protection standard as prohibiting these interim cost adjustments because imposing management risks on ratepayers is antithetical to the concept of ratepayer protection.22 We find no support for the plaintiffs con[39]*39stmction of § 16-19b (c) in its text, its legislative history or in the purpose underlying its adoption.23
First and foremost, it must be noted that the duty to protect ratepayer interests inures in every rate setting decision. As the plaintiff concedes, prudently incurred costs, even those attributable to management risks of nuclear facility operations, are necessary considerations in determining the base rate. See General Statutes § 16-19e. It is entirely unreasonable to conclude, therefore, that the imposition of management risks on ratepayers is contrary to the concept of ratepayer protection. Rather, it is a balancing of the interests of ratepayers and the needs of an electric company that establishes the appropriate standard for rate setting.
Moreover, the text of § 16-19b (c) belies the plaintiffs interpretation. Section 16~19b (c) provides, in relevant part, that “[t]he department shall design any such energy adjustment clause to reflect cost-efficient energy resource procurement and to recover the costs of energy that are proper for rate-making purposes and for which the department has not authorized recovery [40]*40through base rates. These costs, reflecting prudent and efficient management and operations, may include, but are not limited to, the costs of oil, gas, coal, nuclear fuel, wood or other fuels, and energy transactions with other utilities .... The department shall design the energy adjustment clause to provide for recovery of energy costs prudently incurred by an electric company in accordance with section 16-19e. . . .” (Emphasis added.) Nowhere in § 16-19b (c) does the language prohibit the recovery of fuel related costs that are attributable to management risks. We will not adopt an “interpretation [that] imports ambiguity where none is apparent, [or that] engrafts language onto the statute that appears nowhere in the text.” Connecticut Assn. of Not-for-Profit Providers for the Aging v. Dept. of Social Services, 244 Conn. 378, 395, 709 A.2d 1116 (1998).
Contrary to the plaintiffs assertion, § 16-19b (c) requires the department to design an energy adjustment clause that will enable the electric company to recover those costs not accounted for in the base rate, that is, interim cost variations, “reflecting prudent and efficient management and operations” including the costs related to nuclear fuel. (Emphasis added.) General Statutes § 16-19b (c). Additionally, the statute mandates the adoption of an energy adjustment clause that affords recovery of “energy costs prudently incurred ... in accordance with section 16-19e.” General Statutes § 16-19b (c). Section 16-19e establishes the general rate setting guidelines, which, as the plaintiff concedes, permit the department to set rates that will enable the company to recover in the base rate prudently incurred costs attributable to management decisions. Section 16-19e (a) (5) provides that “the level and structure of rates charged customers shall reflect prudent and efficient management of the franchise operation . . . .’’The language of § 16-19b (c) permitting recovery of interim [41]*41costs in accordance with § 16-19e clearly demonstrates that the department is obligated to consider the same factors in adopting interim rates as are relevant in establishing the base rate. Consequently, we find no merit in the plaintiffs assertion that management risks may be passed through in the base rate but not by interim adjustments under the energy adjustment clause. To the extent that § 16-19e permits consideration of the risks of generation plant management in establishing the base rate, so too may it be considered in establishing interim rate adjustments in adopting an energy adjustment clause pursuant to § 16-19b (c).
This textual interpretation is supported by the legislative purpose and history of the statute. The primary impetus for this legislation was concern that electric companies were incurring lower costs than were reflected in their base rate and were overcharging ratepayers. See 38 S. Proc., supra, p. 1756, remarks of Senator Somma. The legislature intended that the ratepayers should be credited with a reduction in their rate if the electric company was incurring lower costs than anticipated. It is absurd, therefore, for the plaintiff to argue that the legislature intended that no cost variations attributable to management decisions could be passed through to ratepayers when there is a decrease in the company’s costs that would inure to the benefit of ratepayers. If the company’s management has increased its efficiency and thus reduced its costs below that which was anticipated in establishing the base rate, this is precisely the type of benefit that the legislature expected to be passed through to the ratepayers.
Furthermore, the legislature was concerned that the rates collected should accurately reflect the electric company’s actual costs. Id. Its puipose was not solely to benefit ratepayers, but to provide an adjustment clause that would reflect all of the actual costs and ensure proper compensation that could not be obtained in the [42]*42absence of interim adjustments. The entire concept of interim rate adjustment clauses undermines the plaintiffs theory. The only purpose for permitting interim adjustments is to enable rates more accurately to reflect actual costs with less frequent regular rate hearings. The base rate, by its very nature as an anticipatory figure, is often an inaccurate reflection of actual costs. The only reason that adjustment clauses exist is to permit ratepayers to enjoy the benefit of lower actual costs and to protect the electric company from the burden of potential financial instability when the base rate would be inadequate compensation. If a prudently incurred fuel related cost attributable to a management risk stands to put the financial health of an electric company in jeopardy, the failure to permit an interim rate adjustment would undermine the whole purpose of adopting such clauses in the first instance.
Consequently, it would be equally absurd to conclude that the legislature intended the statute to decrease the base rate when a nuclear facility was efficiently operated but that the company was not entitled to the same protection of an increase in rates when its costs exceeded the anticipated costs, strictly as a result of prudent management decisions. “ [Compelling principles of statutory construction . . . require us to construe a statute in a manner that will not thwart its intended purpose or lead to absurd results. . . . We must avoid a construction that fails to attain a rational and sensible result that bears directly on the purpose the legislature sought to achieve.” (Internal quotation marks omitted.) Coley v. Camden Associates, Inc., 243 Conn. 311, 319-20, 702 A.2d 1180 (1997). The legislature left the determination of what costs were recoverable to the sound discretion of the department within the general standards set forth in § 16-19b (c). None of the limitations imposed include a prohibition on the recovery of a fuel related cost merely because it is [43]*43attributable to a management risk. In the absence of a showing that the department has abused its discretion or exceeded its statutory authority, we will not supplant the department’s judgment with our own.24
The plaintiffs interpretations of the ratepayer protection standard in § 16-19b (c) are unpersuasive. It has failed to identify anything in the record that would indicate an abuse of discretion by the department or the absence of substantial evidence to support the department’s factual conclusions. Furthermore, the plaintiff has not postulated a rational interpretation of § 16-19b (c) that would place the department’s action beyond the scope of its statutory authority. Consequently, we conclude that the department correctly interpreted the statutory requirements of § 16-19b (c) in approving the energy adjustment clause for the power company.
The judgment is affirmed.
In this opinion KATZ and PALMER, Js., concurred.