Oak Construction Co. v. Department of State Highways

190 N.W.2d 296, 33 Mich. App. 561, 1971 Mich. App. LEXIS 1803
CourtMichigan Court of Appeals
DecidedMay 19, 1971
DocketDocket 9761
StatusPublished
Cited by18 cases

This text of 190 N.W.2d 296 (Oak Construction Co. v. Department of State Highways) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oak Construction Co. v. Department of State Highways, 190 N.W.2d 296, 33 Mich. App. 561, 1971 Mich. App. LEXIS 1803 (Mich. Ct. App. 1971).

Opinion

Fitzgerald, J.

This appeal comes to ns from the Court of Claims. Plaintiff contracted with the State Highway Department to do certain repair work on US 10 in Pontiac, Michigan. The work began on May 21, 1963, and was completed on November 30, 1964.

On December 17, 1965, plaintiff submitted claims for “extras” to the project engineer. “Extras” are requests for compensation for necessary work done while completing the contract but not included in the contract specifications.

Final estimates of costs were completed by the project engineer on February 28, 1966, and sent to plaintiff on March 22, 1966. On April 28, 1966, plaintiff received a check from defendant covering the amount of the final estimate. This check excluded over $68,000 worth of “extras” plaintiff claimed was due him under the contract.

Pursuant to procedures set up by defendant highway department, plaintiff, on May 7, 1966, presented a list of these disputed claims to the central office adjustment board of the highway department *563 for review. The central office adjustment board rejected the claims in writing on April 1, 1968.

Subsequently, plaintiff filed a complaint in the Court of Claims for the amount of the “extras” on March 28, 1969. Defendant filed a motion for an accelerated judgment on the grounds that plaintiff had not filed a notice of claim within one year after the claim accrued as required by MCLA § 600.6431 (1) (Stat Ann 1962 Rev § 27A.6431[1]). On June 10, 1970, the lower court ruled that the defendant had not complied with MCLA § 600.6431(1) (Stat Ann 1962 Rev § 27A.6431[1]) because his claim had accrued on February 28, 1966, when the final estimate had been filed, and thus he had not filed notice of claim within the required one-year period. Plaintiff appeals as of right this ruling and dismissal of his claim.

The sole question for our determination and interpretation in this appeal is: when does a claim accrue, under the instant facts, within the meaning of MCLA § 600.6431(1) (Stat Ann 1962 Rev § 27A.6431[1]) 1

Plaintiff argues on appeal that his claim did not accrue until it was finally rejected by the central adjustment board of the highway department. He argues that as long as he was pursuing remedies within the highway department his claim had not accrued.

Defendant counters that plaintiff’s claim accrued on February 28,1966, when he received the final estimates from the project engineer.

It appears that this particular issue is one of first impression in this state, although the issue has given rise to a not inconsiderable amount of litigation in other states. See Edlux Construction Corporation v. State of New York (1937), 252 App *564 Div 373 (300 NYS 509); Mount Vernon Contracting Corporation v. State of New York (1967), 52 Misc 2d 781 (276 NYS2d 1009); Fletcher-McCarthy Construction Company, Inc. v. State of New York (1967), 53 Misc 2d 62 (277 NYS 2d 714); and Terry Contracting, Inc. v. State of New York (1967), 27 App Div 2d 499 (280 NYS2d 450).

The Court of Claims act contains two limitations. The first is that found in MCLA § 600.6431(1) which provides that a notice of claim must be filed within one year after the claim has accrued. The other is the three-year statute of limitations found in MCLA § 600.6452(1) (Stat Ann 1962 Kev § 27A.6452[1]). This section provides that an action shall be forever barred if a claim is not made within three years after the action accrues.

This' Court, in the case of Anthonsen v. State Highway Commissioner (1966), 4 Mich App 345, reconciled these two provisions by ruling that the purpose of the one-year limitation is to give the state notice of claims against it; while the purpose of the second limitation is to provide a further period of time within which the claimant may make a more specific claim against the state. The act thus provides for a short one-year limitation within which to give notice of a claim to the state and a longer three-year limitation within which a claimant must make his claim specific. Anthonsen, supra, still did not answer the question of when a claim accrues within the context of the situation now before the Court. Two other cases deal with the general problem presented but do not aid in resolving the issue before us. These are Gilliland Construction Company v. State Highway Department (1966), 4 Mich App 618, and Reich v. State Highway Commissioner (1967), 5 Mich App 509.

*565 On September 21, 1966, the Director of the State Highway Department sent a letter to state contractors setting forth the procedures to be used in requesting additional compensation for contract work. The first step there set forth was for the contractor to notify the project engineer in writing of extra work before the contractor begins the work. The second step is for the contractor, after completion of the work, to file a detailed written account of his claim with the project engineer. If the written decision of the project engineer is against the contractor, he may then take the final step of requesting review of the claim by the central office adjustment board. The central office adjustment board then reviews the claim and renders the contractor the final written decision. Any further remedy for the contractor lies with the Court of Claims.

In the case before us today, it is quite obvious that the plaintiff relied upon these internal procedures of the highway department. He thus did not file his claim in the Court of Claims until these internal procedures were exhausted.

The action of plaintiff was entirely consistent with the applicable doctrine of exhaustion of administrative remedies. That general precept holds that one must avail oneself of all administrative remedies before one seeks redress in the courts. See MCLA § 24.301 (Stat Ann 1971 Cum Supp § 3.560 [201]). Should one fail to do so, the chances are excellent that one will have his action dismissed as being premature.

To rule as defendant urges in the instant case would place plaintiff in a position that is inconsistent with our system of justice. For example, if plaintiff is required to file in the Court of Claims before he exhausts all his administrative remedies, *566 he runs a substantial risk of having his complaint dismissed for being premature. On the other hand, if plaintiff is required to exhaust his administrative remedies as set forth by the highway department, but the statute of limitations begins to run, as defendant argues here, before the exhaustion of those remedies, then plaintiff runs a substantial risk that the statute of limitations on his claim would run before the final determination of that claim by the highway department. This would, needless to say, place plaintiff in what could be most aptly termed a legal quandary.

Additionally, to hold as defendant argues here would enable defendant to defeat plaintiff’s claim by administrative delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petra Pike v. Northern Michigan University
Michigan Court of Appeals, 2019
Adr Consultants LLC v. Michigan Land Bank Fast Track Authority
932 N.W.2d 226 (Michigan Court of Appeals, 2019)
Melissa Mays v. Governor Rick Snyder
Michigan Court of Appeals, 2018
Abhe & Svboda Inc v. State of Michigan
Michigan Court of Appeals, 2017
Rainbow Construction Inc v. Howell Township
Michigan Court of Appeals, 2015
Durant v. Department of Education
313 N.W.2d 571 (Michigan Court of Appeals, 1981)
Schwartz v. Michigan Sugar Co.
308 N.W.2d 459 (Michigan Court of Appeals, 1981)
Dickerson v. Warden
298 N.W.2d 841 (Michigan Court of Appeals, 1980)
Marcou Construction Co. v. Tinkham Industrial & Development Corp.
371 A.2d 1187 (Supreme Court of New Hampshire, 1977)
Cooke Contracting Co. v. Department of State Highways 1
222 N.W.2d 231 (Michigan Court of Appeals, 1974)
Cooke Contracting Co. v. Department of State Highways
213 N.W.2d 262 (Michigan Court of Appeals, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
190 N.W.2d 296, 33 Mich. App. 561, 1971 Mich. App. LEXIS 1803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oak-construction-co-v-department-of-state-highways-michctapp-1971.