Rainbow Construction Inc v. Howell Township

CourtMichigan Court of Appeals
DecidedFebruary 24, 2015
Docket318591
StatusUnpublished

This text of Rainbow Construction Inc v. Howell Township (Rainbow Construction Inc v. Howell Township) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rainbow Construction Inc v. Howell Township, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

RAINBOW CONSTRUCTION, INC., UNPUBLISHED February 24, 2015 Plaintiff/Counter Defendant- Appellee,

v No. 318591 Livingston Circuit Court HOWELL TOWNSHIP, LC No. 12-026975-CK

Defendant/Counter Plaintiff- Appellant.

Before: MURPHY, P.J., and METER and SERVITTO, JJ.

PER CURIAM.

Defendant appeals by leave granted1 the trial court’s order denying its motion for summary disposition under MCR 2.116(C)(7) (statute of limitations). We affirm in part, reverse in part, and remand for further proceedings.

I. BASIC FACTS

This case involves an August 8, 2005, contract between plaintiff and defendant to build a public water and sanitary sewer extension. The agreement provided that the work on the sewer extension “will be substantially completed on or before June 8, 2006,” and that “time is of the essence.” Article 10.05 of the agreement provided that the rendering of a decision by defendant’s engineer on a claim, dispute, or other matter was a condition precedent to filing suit.

Plaintiff commenced the sewer extension work in a timely fashion. Plaintiff alleged, however, that it experienced successive delays and interferences with its work, all caused or permitted by defendant. One such disruption, plaintiff claimed, was the result of inaccurate project drawings that incorrectly identified the locations of underground utilities. On January 11, 2006, plaintiff submitted a notice of intent to defendant’s engineer relating to lost time and possible monetary compensation due to the utility problems encountered, and on January 18,

1 Rainbow Constr, Inc v Howell Twp, unpublished order of the Court of Appeals, entered May 27, 2014 (Docket No. 318591).

-1- 2006, plaintiff submitted a revised schedule, which provided that the project was to be completed by August 12, 2006. In response, on January 24, 2006, defendant’s engineer sent a letter to plaintiff complaining about the delay and requesting an updated schedule meeting the original June 8, 2006, deadline.

On February 7, 2006, the Livingston County Road Commission informed defendant that plaintiff was using Oak Grove Road as a staging platform against the commission’s policy. The road commission requested that plaintiff devise a safe means to protect the roadway. On February 10, 2006, plaintiff complained to defendant’s engineer regarding the cost of steel plating to protect the road pavement, as well as regarding the inadequate rights-of-way. Defendant’s engineer sent a response to plaintiff on February 17, 2006, stating that there was no indication by plaintiff in its bid for this project that the public rights-of-way were insufficient and that plaintiff should be solely responsible for the means and methods of construction.

On March 14, 2006, plaintiff sent a letter to defendant’s engineer proposing further work along Oak Grove Road and requesting an extension of time. On March 17, 2006, defendant (not the engineer) denied plaintiff’s requests, stating that neither additional payment nor extension of time to complete the work was permitted.

On June 7, 2006, plaintiff sent another letter to defendant’s engineer, identifying a number of unanticipated events beyond the control of plaintiff that impacted the schedule and providing a proposed revised schedule identifying October 3, 2006, as the project completion date. On June 8, 2006, defendant’s engineer notified plaintiff that it was in default of the contract because it had not substantially completed the work and, as a result, defendant would begin charging liquidated damages. Plaintiff protested the notice of default, alleging that it was not justified and constituted “a formal and material breach of the contract” because the delays were beyond plaintiff’s control. Plaintiff asserted that it was entitled to an extension of time to complete the project; it was substantially completed on November 9, 2006.

On December 1, 2006, plaintiff submitted a claim to defendant’s engineer for $41,580 for additional costs incurred for using steel plating compelled by the road commission to protect the roads. In response, defendant’s engineer issued a proposed change order dated December 19, 2006, agreeing to pay plaintiff the claimed amount, in exchange for a full release of the claim. On December 1, 2006, plaintiff submitted another claim for $11,475, relating to additional costs incurred to remove buried Comcast cables that were not shown on the original contract plans. Plaintiff also submitted a claim on November 14, 2007, for $22,363.91 for costs incurred to use undercut/stone refill beyond the bedding specification for a pipe installation. Plaintiff thereafter requested additional monies, including $1,431.50 for paving a driveway at Oak Grove Road, $153,000 for “[l]iquidated damages to be rescinded,” and $70,000 as a “bonus” enhancement.

-2- On February 22, 2008, defendant sent a letter to plaintiff suggesting a meeting in the near future to resolve any remaining disagreements the parties had.2 Defendant’s March 28, 2008, letter to plaintiff acknowledged that plaintiff’s claim for $1,431.50 regarding the driveway paving and other claims had been “submitted.” On April 9, 2008, the parties attended a conference and discussed the claims in dispute, but the negotiation reached an impasse and no change order was issued.

The trial court concluded that the statute of limitations did not begin running until after the April 2008 meeting and that plaintiff’s August 2, 2012, lawsuit was timely.

II. ANALYSIS

Defendant contends that plaintiff’s claim for breach of contract was barred by the applicable statute of limitations. We review de novo an order granting or denying summary disposition. Nuculovic v Hill, 287 Mich App 58, 61; 783 NW2d 124 (2010). A party is entitled to summary disposition under MCR 2.116(C)(7) if the opposing party’s claims are barred under the applicable statute of limitations. When reviewing a motion for summary disposition made pursuant to MCR 2.116(C)(7), “[t]he Court must consider affidavits, pleadings, depositions, admissions, and any other documentary evidence submitted by the parties, to determine whether a genuine issue of material fact exists.” Nuculovic, 287 Mich App at 61. The contents of the complaint will be accepted as true unless specifically contradicted by other documentary evidence submitted by the parties. Bryant v Oakpointe Villa Nursing Ctr, Inc, 471 Mich 411, 419; 684 NW2d 864 (2004). If no material facts are in dispute and reasonable minds could not differ regarding the legal effect of the facts, the issue of whether the statute of limitations bars a plaintiff’s claim is a matter of law. Guerra v Garratt, 222 Mich App 285, 289; 564 NW2d 121 (1997) (citations and quotation marks omitted).

The limitations period for a claim of breach of contract is six years. MCL 600.5807(8). “A claim accrues, and the limitations period begins to run, when the claim may be brought. For a breach of contract action, the limitations period generally begins to run on the date that the breach occurs.” Seyburn, Kahn, Ginn, Bess, Deitch and Serlin, PC v Bakshi, 483 Mich 345, 355; 771 NW2d 411 (2009) (citation omitted).

The goal of contract interpretation is to determine and enforce the intent of the parties, as expressed in the contract. Shay v Aldrich, 487 Mich 648, 660; 790 NW2d 629 (2010). A “contract must be interpreted according to its plain and ordinary meaning.” Holmes v Holmes, 281 Mich App 575, 593; 760 NW2d 300 (2008). Clear and unambiguous contractual language must be enforced as written. Holland v Trinity Health Care Corp, 287 Mich App 524, 527; 791 NW2d 724 (2010).

2 Although this letter is not included in the lower court record, plaintiff attaches it to its appellate brief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shay v. Aldrich
790 N.W.2d 629 (Michigan Supreme Court, 2010)
Seyburn, Kahn, Ginn, Bess, Deitch & Serlin, PC v. Bakshi
771 N.W.2d 411 (Michigan Supreme Court, 2009)
Bryant v. Oakpointe Villa Nursing Centre, Inc
684 N.W.2d 864 (Michigan Supreme Court, 2004)
Guerra v. Garratt
564 N.W.2d 121 (Michigan Court of Appeals, 1997)
Holmes v. Holmes
760 N.W.2d 300 (Michigan Court of Appeals, 2008)
Williams v. Polgar
214 N.W.2d 149 (Michigan Supreme Court, 1974)
Oak Construction Co. v. Department of State Highways
190 N.W.2d 296 (Michigan Court of Appeals, 1971)
United States Fidelity & Guaranty Co. v. Black
313 N.W.2d 77 (Michigan Supreme Court, 1981)
Stephens v. Dixon
536 N.W.2d 755 (Michigan Supreme Court, 1995)
Nuculovic v. Hill
287 Mich. App. 58 (Michigan Court of Appeals, 2010)
Holland v. Trinity Health Care Corp.
791 N.W.2d 724 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Rainbow Construction Inc v. Howell Township, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rainbow-construction-inc-v-howell-township-michctapp-2015.