NVR, INC. v. MAJESTIC HILLS, L.L.C.

District Court, W.D. Pennsylvania·Decided July 21, 2023·No. 2:18-cv-01335·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA NVR, INC., ) ) Plaintiff, ) 2:18-CV-1335 ) v. ) ) MAJESTIC HILLS, LLC, et al., ) ) ) Defendants, ) v. ) ) STRNISHA EXCAVATION, INC., ) ) and MORRIS KNOWLES & ) ASSOCIATES, INC., ) )

) Third-Party Defendants, ) ) v. ) ) THE GATEWAY ENGINEERS, INC., ) ) and MAJESTIC HILLS ) HOMEOWNERS ASSOCIATION, ) )

) Third-Party Defendants. ) MEMORANDUM ORDER Before the Court are motions in limine filed by Plaintiff NVR (ECF 562, ECF 564, ECF 566) and Defendant Joseph DeNardo (ECF 568, ECF 570, ECF 572, ECF 574, ECF 576, ECF 578, ECF 580). The Court issues this omnibus order resolving the motions as follows. I. PLAINTIFF’S MOTIONS

A. Plaintiff’s motion in limine to preclude argument raising the statute-of-repose defense (ECF 562). The motion is DENIED. NVR seeks to preclude Mr. DeNardo from raising the statute of repose defense on equitable grounds and argues against its relevance and applicability to Mr. DeNardo. The Court disagrees. Much of NVR’s motion tries to relitigate issues raised at summary judgment. Berkley Assurance Co. v. Colony Ins. Co., No. 17-5433, 2019 WL 9096411, at *1 (E.D. Pa. May 7, 2019) (denying motions in limine that “are largely an attempt to relitigate issues . . . resolved at summary judgment”). The Court’s summary judgment order (ECF 539) was clear: the statute of repose is a non-waivable defense. The Court’s prior findings on the statute of repose remain in effect—that is, (1) the relevant injury is the landslide at the sidehill embankment (and damages flowing from that landslide), (2) the completion of Phase 1 occurred not later than April 2006, and (3) subsequent remedial measures and repairs do not toll the statute of repose.1 The Court also declines to exercise its discretion to preclude Mr. DeNardo from raising the defense based on judicial estoppel. See In re Kane, 628 F.3d 631, 638 (3d Cir. 2010) (“Judicial estoppel is a fact-specific, equitable doctrine, applied at courts’ discretion” and only to “avoid a miscarriage of justice.”). “Three requirements must be met before a district court may properly apply judicial estoppel. First, the party to be estopped must have taken two positions that

1 To be sure, the Court denied Defendants’ motion to amend nunc pro tunc their summary judgment briefs and for reconsideration (ECF 545) because the Court was not going to re-open summary judgment, and the motion was otherwise threadbare. While certainly inefficient, nothing prevents Mr. DeNardo from making a record and raising the statute of repose at trial, including through a Rule 50 motion for judgment as a matter of law. See Fleck v. KDI Sylvan Pools, Inc., 981 F.2d 107, 116 (3d Cir. 1992) (upholding directed verdict for defendant who raised statute of repose defense at trial). are irreconcilably inconsistent. Second, judicial estoppel is unwarranted unless the party changed his or her position in bad faith—i.e., with intent to play fast and loose with the court. Finally, a district court may not employ judicial estoppel unless it is tailored to address the harm identified and no lesser sanction would adequately remedy the damage done by the litigant’s misconduct.” Montrose Med. Grp. Participating Sav. Plan v. Bulger, 243 F.3d 773, 779-80 (3d Cir. 2001) (cleaned up). NVR argues that Mr. DeNardo tacitly acknowledged that the statute of repose doesn’t apply when he recently filed a complaint in state court seeking damages from the landslide. ECF 563, pp.6-7. But it would be a stretch to conclude that this fact alone requires judicial estoppel because: (1) JND, not Mr. DeNardo, is the party in state court; (2) allegations in a complaint aren’t typically the type of representations to a court that receive judicial-estoppel effect; and (3) it isn’t entirely clear whether the positions taken by JND in the state-court claim conflict with its position here— after all, the statute of repose applies on a contractor-by-contractor basis. These considerations counsel against applying judicial estoppel, so the Court declines to do so here. See Bulger, 243 F.3d at 786 (Judicial estoppel’s “only legitimate purpose is to remedy an affront to the court’s integrity.” (emphasis in original) (citation omitted)). B. Plaintiff’s motion in limine to preclude evidence and argument on NVR’s alleged defects in home construction and lot excavation (ECF 564). The motion is GRANTED IN PART AND DENIED IN PART. NVR argues that Mr. DeNardo cannot point to NVR’s purported negligent conduct without expert evidence. The Court agrees, in part. NVR is concerned that Mr. DeNardo will identify defects in how NVR built its homes (foundation construction, alteration of the grading by NVR, etc.). That sort of evidence would appear to require some type of expert opinion. So to the extent that Mr. DeNardo might seek to introduce that evidence, he is precluded from doing so, due to lack of any expert opinion on the issue. But it doesn’t appear that Mr. DeNardo is necessarily attempting to make such an argument. Rather, Mr. DeNardo argues that if NVR will present evidence on how he failed to monitor some of PS&R’s work regarding the grading of the lots at issue, then he should be able to show NVR’s failure to do the same thing. This sort of evidence is relevant and not unduly prejudicial, as it goes to the reasonableness of Mr. DeNardo’s conduct. And it isn’t the sort of evidence that requires expert discovery. Therefore, Mr. DeNardo may introduce this limited evidence without an expert opinion. C. Plaintiff’s motion in limine to preclude evidence and argument assigning blame to dismissed parties (ECF 566). The motion is GRANTED IN PART AND DENIED IN PART. NVR seeks to prevent Mr. DeNardo from introducing evidence of liability for defendants that were previously dismissed from this case. The Court disagrees, at least when it comes to the counts of negligence—and as explained below, the verdict slip should reflect the apportionment of liability on those counts.2 At the summary-judgment stage, both NVR and Mr. DeNardo conceded to the dismissal of certain third-party defendants (specifically, Strnisha, Morris Knowles,

2 NVR also has a breach-of-contract claim against Mr. DeNardo. The Court will not include PS&R and Alton on the verdict slip as to that claim, as the Court can find no case (in Pennsylvania or otherwise) for the proposition that liability for breach of a third-party beneficiary contract must be apportioned among the parties. Indeed, this would be contrary to basic principles of contract law because Mr. DeNardo can only be held liable for breach of contract if he, in fact, breached a contract. See Restatement (Second) of Contracts § 235 (“When performance of a duty under a contract is due[,] any non-performance is a breach.”); see also Sullivan v. United States, 625 F.3d 1378, 1381 (Fed. Cir. 2010) (“[E]ven if the Sullivans were third party beneficiaries, there is no cause of action against the Government because the Government did not breach.” (citing Restatement (Second) of Contracts § 235)). Thus, for that claim, the jury must find whether the contract existed; if it did, whether Mr. Gateway, the HOA, Mark Brashear, and Shari DeNardo) because neither continued to argue, either in briefing or at oral argument, that those parties were liable in any way for damages caused by the June 2018 landslide. ECF 539, pp. 5-6. The law of the case therefore precludes a finding of contributory negligence to those dismissed parties.

Free access — add to your briefcase to read the full text and ask questions with AI

NVR, INC. v. MAJESTIC HILLS, L.L.C., (W.D. Pa. 2023).

NVR, INC. v. MAJESTIC HILLS, L.L.C. (NVR, INC. v. MAJESTIC HILLS, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Kane
628 F.3d 631 (Third Circuit, 2010)
Dodd v. United States
545 U.S. 353 (Supreme Court, 2005)
Wicks v. Milzoco Builders, Inc.
470 A.2d 86 (Supreme Court of Pennsylvania, 1983)
In Re MCSi, Inc.
371 B.R. 270 (S.D. Ohio, 2007)
Cantiere DiPortovenere Piesse S.P.A. v. Kerwin
739 F. Supp. 231 (E.D. Pennsylvania, 1990)
COM. EX REL. CORBETT v. Snyder
977 A.2d 28 (Commonwealth Court of Pennsylvania, 2009)
Thomas H. Ross Inc. v. Seigfreid
592 A.2d 1353 (Superior Court of Pennsylvania, 1991)
AmeriPro Search, Inc. v. Fleming Steel Co.
787 A.2d 988 (Superior Court of Pennsylvania, 2001)
Raymond v. Scranton School District
142 A.2d 749 (Superior Court of Pennsylvania, 1958)
Sullivan v. United States
625 F.3d 1378 (Federal Circuit, 2010)
Diehl v. Blaw Knox
360 F.3d 426 (Third Circuit, 2004)
Fleck v. KDI Sylvan Pools, Inc.
981 F.2d 107 (Third Circuit, 1992)
Adams, D. v. Rising Sun Med. Ctr.
2020 Pa. Super. 298 (Superior Court of Pennsylvania, 2020)