Thomas H. Ross Inc. v. Seigfreid

592 A.2d 1353, 405 Pa. Super. 558, 1991 Pa. Super. LEXIS 1714
CourtSuperior Court of Pennsylvania
DecidedJune 20, 1991
Docket2534 and 2872
StatusPublished
Cited by13 cases

This text of 592 A.2d 1353 (Thomas H. Ross Inc. v. Seigfreid) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas H. Ross Inc. v. Seigfreid, 592 A.2d 1353, 405 Pa. Super. 558, 1991 Pa. Super. LEXIS 1714 (Pa. Ct. App. 1991).

Opinion

TAMILIA, Judge:

Howard A. Seigfreid, t/d/b/a Howard Seigfreid Excavating (Seigfreid), and Thomas H. Ross Inc. (Ross), bring these cross-appeals from the August 29, 1990 judgment awarding both parties contract damages plus interest.

This case arose out of a series of contracts between Ross, a general contractor, and Seigfreid, a subcontractor and owner and operator of an excavating business. In his complaint, Ross alleged Seigfreid had breached two con *562 tracts related to housing projects known as Williamstown and Williams Township and requested general and liquidated damages. Seigfreid filed an answer and counterclaim requesting general damages alleging Ross’ breach of the aforesaid contracts plus an alleged breach by Ross on the contract for the project known as Pine Meadows. Subsequent to a nonjury trial, held April 8 and 9, 1987, judgment was entered for Ross in the amount of $5,671.47 plus interest on the Williamstown project; judgment for Ross in the amount of $31,711.23 plus interest on the Williams Township project; and judgment for Seigfreid in the amount of $10,241.70 plus interest on the Pine Meadows project. The amount awarded Seigfreid reflects a set-off of $8,106.25 owed to a third party covered under the indemnity provisions of the contract between the parties. The court ruled the interest on the awards would run from May 21, 1982, the date of completion of contractual obligations, to April 9, 1987, the completion of trial. Seigfried’s post-trial motions were denied by Order dated August 7, 1990, which stated the interest would be calculated as stated in the award and would also run beginning July 18, 1989, the date of the awards. The awards were reduced to judgment on August 29, 1990. 1

Seigfreid avers the court erred by awarding liquidated damages on the Williamstown and Williams Township projects. He also contends the court erred by setting off the claim of a third party against its finding in his favor regarding the Pine Meadows project. Finally, Seigfreid argues the court committed error by not granting his motion for judgment n.o.v.

Seigfreid contends the language of the liquidated damage clause of each contract, set forth in pertinent part *563 below, precluded an award for liquidated damages unless his alleged omissions and Ross’ acts occurred at a time when the contract was in effect and Ross gave 24-hour written notice of his intent to declare the agreement in default.

5. In the event the Subcontractor shall at any time, when this contract is in effect, ... or shall fail to pay promptly when due all charges for labor and materials used in the performance of this contract, and/or the Subcontractor shall neglect to perform the work properly or shall fail to perform any provisions of this contract, ... or any other voluntary or involuntary cessation of work by the Subcontractor ... and which, in the judgment of the Contractor is causing or is likely to cause an unreasonable delay in the progress of the work to be done by the Subcontractor, the Contractor shall have the right to declare this Agreement in default after giving the Subcontractor twenty-four (24) hours written notice to the Subcontractor to make good the deficiency and after the failure of the Subcontractor to do so, may terminate the contract ... and shall finish the work by such means as he sees fit, and at the usual and prevailing price of work of this character in the community. If the unpaid balance of the contract price exceeds the expense of finishing the work, such excess shall be paid to the Subcontractor, but if such expense exceeds such unpaid balance, the Subcontractor shall pay the difference to the Contractor. Inasmuch as the injury or damage to the Contractor by reason of the failure of the performance hereunder by the Subcontractor is difficult to determine with any degree of certainty, it is agreed that in computing the expense of completing the work as above provided, there shall be added to such expense a sum equal to ten (10%) per cent of the actual money outlay for such finishing, and such amount is hereby agreed upon, fixed and determined by the parties hereto as the liquidated damages that the Contractor shall suffer by default and not by way of penalty, and that the Subcontractor agrees to pay the *564 Contractor such excess within thirty (30) days after written demand for such excess has been made by the Contractor upon the Subcontractor____

(Defendant’s Exhibit # 1.) Seigfreid argues Ross, by failing to pay him in a timely manner, breached the Williams-town and Williams Township contracts before Seigfreid refused to return to the job. With regard to the Williams-town project, Seigfreid testified and the trial court found he was aware the excavation work was behind schedule in the fall of 1981 and was notified by Ross, by mailgram, that on October 30, 1981, another subcontractor would be hired to complete the project due to the delay. Seigfreid testified there were periods between August, 1981, and October, 1981, when his equipment was not present on the job site. He also testified he received his last monthly payment from Ross in October, 1981. Seigfreid left the job site in December, 1981, and did not return. The court concluded, inter alia, Ross did not in any way cause Seigfreid’s failure to complete the work required under the contract. Rather, the court held the evidence presented supported a finding Seigfreid first breached the contract between the parties by failing to complete the work according to schedule. We find it was proper to hire another company to do the excavation when Seigfreid failed to do so, and Ross’ claim for liquidated damages was fully supported by the contract signed by the parties. As to the Williams Township project, the court made findings and conclusions similar to those stated supra. The court made no finding Ross breached the contract by failing to pay Seigfreid in a timely fashion for work completed.

In reviewing the findings of a trial judge, the successful party is entitled to have evidence viewed in the light most favorable to him, and all evidence and proper inferences favorable to him must be taken as true and all unfavorable inferences rejected, especially where the credibility of witnesses had to be weighed by the court. Short v. Metropolitan Life Ins. Co., 339 Pa.Super. 124, 488 A.2d 341 (1985). Findings of fact of a trial judge have the force and effect of *565 a jury verdict and, based upon the evidence, will not be disturbed on appeal unless they are manifestly erroneous. Id. at 127-128, 488 A.2d at 343. With these standards in mind, we find the court had sufficient evidence upon which to find Seigfreid, not Ross, first breached the contracts spawning this lawsuit by his dilatory, irresponsible conduct, and we will not disturb the court’s findings of fact.

This Court having found there to have been no breach by Ross, Seigfreid argues in the alternative Ross did not comply with the terms of the contract so as to enable him to demand liquidated damages. Specifically, Seigfreid contends Ross failed to introduce at trial any evidence to satisfy the contractual requirement of paragraph five, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blucas, M. v. Agiovlasitis, P.
179 A.3d 520 (Superior Court of Pennsylvania, 2018)
Greenville Surgical v. Arreola, R.
Superior Court of Pennsylvania, 2015
Portside Investors, L.P. v. Northern Insurance
41 A.3d 1 (Superior Court of Pennsylvania, 2011)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)
Mattiola Construction Corp. v. Commercial Union Insurance
60 Pa. D. & C.4th 412 (Philadelphia County Court of Common Pleas, 2002)
Somerset Community Hospital v. Allan B. Mitchell & Associates, Inc.
685 A.2d 141 (Superior Court of Pennsylvania, 1996)
Alberici v. Safeguard Mutual Insurance
664 A.2d 110 (Superior Court of Pennsylvania, 1995)
Spang & Co. v. USX Corp.
599 A.2d 978 (Superior Court of Pennsylvania, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
592 A.2d 1353, 405 Pa. Super. 558, 1991 Pa. Super. LEXIS 1714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-h-ross-inc-v-seigfreid-pasuperct-1991.