Norton Construction Co. v. United States Army Corps of Engineers

280 F. App'x 490
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 2, 2008
Docket07-3826
StatusUnpublished
Cited by4 cases

This text of 280 F. App'x 490 (Norton Construction Co. v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norton Construction Co. v. United States Army Corps of Engineers, 280 F. App'x 490 (6th Cir. 2008).

Opinion

GRIFFIN, Circuit Judge.

This appeal involves plaintiff Norton Construction Company’s application for a permit to construct a new landfill in an area subject to defendant United States Army Corps of Engineers’ jurisdiction. The Corps refused to process the application, citing a Congressional appropriation act that the Corps construed as forbidding it from processing applications for new landfills in this area that it considered to be within the Muskingum Watershed. Norton unsuccessfully challenged this decision in district court. The district court ruled that the Corps reasonably interpreted the statute and that the law did not violate Norton’s constitutional rights. Plaintiff Norton now appeals, and we affirm.

I.

Norton is an Ohio company that seeks to construct a landfill in Tuscarawas County, Ohio. Construction of the landfill would involve filling wetlands and streams that the parties agree fall within the jurisdiction of the Army Corps of Engineers. As such, Norton is required to apply to the Corps for a permit pursuant to § 404 of the Clean Water Act, 33 U.S.C. § 1344.

Norton applied for a § 404 permit, but the Corps returned the application without acting upon it because Congress enacted a temporary appropriations rider, which in the opinion of the Corps, prohibited the Corps from processing its application. Norton sued the Corps in the United States District Court for the Northern District of Ohio on November 5, 2003. The district court ruled initially in favor of Norton, and the Corps appealed. After the temporary appropriations rider expired, we dismissed the appeal as moot and remanded the case to the district court.

In the meantime, Congress passed, and the President signed, the Energy and Water Development Appropriations Act of 2006, Pub.L. No. 109-103, 119 Stat. 2247 (2005). Section 103 of the Act, enacted as a regular appropriations statute rather than as a temporary appropriations rider, prohibited the Corps from granting new landfill applications in the “Muskingum Watershed”:

SEC. 103. In order to protect and preserve the integrity of the water supply against further degradation, none of the funds made available under this Act and any other Act hereafter may be used by the Army Corps of Engineers to support activities related to any proposed new landfill in the Muskingum Watershed if such landfill—
(1) has not received a permit to construct from the State agency with responsibility for solid waste management in the watershed;
(2) has not received waste for disposal during 2005; and
(3) is not contiguous or adjacent to a portion of a landfill that has received waste for disposal in 2005 and each landfill is owned by the same person or entity.

Pub.L. No. 109-103, § 103, 119 Stat. 2247 (2005).

*492 Norton again requested that the Corps process its petition for a § 404 permit. The Corps ultimately determined that plaintiffs application was barred by § 103 because Norton’s proposed landfill site was located on a stream that is connected to the tributary system of the Tuscarawas River, which is itself a tributary of the Muskingum River.

Norton amended its complaint and requested injunctive relief from the district court. The district court ruled in favor of the Corps, and Norton timely appealed.

II.

The crux of this dispute centers upon the undefined term “Muskingum Watershed.” Norton argues that this term is “patently ambiguous” and the Corps improperly construed it to cover the geographic area where it seeks permission to construct a landfill.

The question of ambiguity is a threshold issue: if the statute is not ambiguous, then there is no need to defer to the agency’s interpretation; we must simply apply the statute. The Supreme Court has held that when “the intent of Congress is clear, that is the end of the matter; for the court, as well as the agency, must give effect to the unambiguously expressed intent of Congress.” Chevron U.S.A., Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837, 842-43, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). However, if the statute is “silent or ambiguous with respect to the specific issue, the question for the court is whether the agency’s answer is based on a permissible construction of the statute.” Id. at 843, 104 S.Ct. 2778.

Logically, there are three possible judicial avenues: (1) if the statute is unambiguous, then we merely apply the statute to resolve this case; (2) if the statute is ambiguous and the agency’s interpretation is reasonable, then we must adopt the agency’s interpretation; or (3) if the statute is ambiguous and either we conclude that it is inappropriate to defer to the agency, or that the agency’s interpretation is unreasonable, then we must make our own interpretation. Norton insists upon the third option, arguing that the statute is ambiguous — thus precluding the first option — and asserting that we should not defer to the Corps.

Norton bases its arguments on an assumption of ambiguity. It assumes that the court agrees that the statute is ambiguous and argues that the Corps’ interpretation is not entitled to deference. The district court ruled that the Congressional intent embodied in § 103 was not ambiguous, and thus there was no need to defer to the Corps’ interpretation: 1

[T]he Court finds that Congressional intent is clear — Section 103 was intended to apply to the Muskingum Watershed, as defined by the Muskingum River and all waters that eventually flow into the Muskingum River. This includes the full 18-county area contemplated by the Corps, including the unnamed tributary of the South Fork of Sugar Creek found on Norton’s proposed location for the Ridge Landfill.

The district court conceded that “[o]n its face, the term Muskingum Watershed reasonably accommodate[s] either party’s definition.” Further, it noted that “the legislative history is more revealing,” but the only history it identified was a statement made by a single member of Congress. The district court quoted a statement made by Congressman Ralph Regula, whose district encompassed much of the *493 area in question. Congressman Regula stated that:

The Muskingum Watershed encompasses 18 counties in Ohio and includes all of the area which drains into the Muskingum River and its tributaries where it joins with the Ohio River. Below the watershed lies an aquifer of great importance to the constituents of my district and those of surrounding areas. The threat that landfills pose to the aquifer and the watershed are too great to ignore. Remember, we are fortunate in the United States to be wellendowed with water, and we are indebted to our forebearers for creating the infrastructure to deliver potable water to our communities, farmers and industries.

151 Cong. Rec. H10360-01. The district court considered this statement to be authoritative evidence of Congressional intent, and the Corps agrees. We do not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Grevious
2022 Ohio 4361 (Ohio Supreme Court, 2022)
Tiwari v. Meier
W.D. Kentucky, 2021
United States v. Brink
795 F. Supp. 2d 565 (S.D. Texas, 2011)
Kilmer v. Leavitt
609 F. Supp. 2d 750 (S.D. Ohio, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
280 F. App'x 490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norton-construction-co-v-united-states-army-corps-of-engineers-ca6-2008.