Northwest Cascade Construction, Inc. v. Custom Component Structures, Inc.

519 P.2d 1, 83 Wash. 2d 453, 1974 Wash. LEXIS 923
CourtWashington Supreme Court
DecidedFebruary 21, 1974
Docket42862
StatusPublished
Cited by17 cases

This text of 519 P.2d 1 (Northwest Cascade Construction, Inc. v. Custom Component Structures, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Cascade Construction, Inc. v. Custom Component Structures, Inc., 519 P.2d 1, 83 Wash. 2d 453, 1974 Wash. LEXIS 923 (Wash. 1974).

Opinion

Hunter, J.

This case concerns an action brought by the respondents (plaintiffs), Northwest Cascade Construction, Inc., Russell Mowry and Dave Kuipers, against the petitioner (defendant), Custom Component Structures, Inc., for the balance due on a construction contract, plus extra compensation for additional work performed. The trial court entered judgment for the plaintiffs, and the Court of Appeals, Division One, affirmed the trial court. We granted the defendant’s petition for review.

The plaintiff, Northwest Cascade Construction, Inc., hereinafter referred to as “Northwest,” is a corporation owned and operated by its stockholders, A1 Ballard, Tom Ballard, and Paul Box. The plaintiff, Dave Kuipers, was employed as a general superintendent by Northwest, and the plaintiff, Russell Mowry, was employed by Northwest as the accountant to maintain the records and books of the business. The defendant, Custom Component Structures, Inc., hereinafter referred to as “Custom,” is a corporation engaged in manufacturing building components, and had a contract during *455 the period in question to furnish and erect certain component packages consisting of exterior walls, interior partitions, stairs, and other items for the Aero-Kenyon project in Seattle.

In October 1968, Northwest entered into an oral contract with Custom whereby Northwest was to erect certain component packages constructed by Custom for 12 buildings in the Aero-Kenyon project. At the time of entering into the contract, Northwest was a duly registered contractor under the registration of contractors act, RCW 18.27 (hereinafter also referred to as the registration act or act). Northwest commenced construction on the project under the direction of its stockholder and vice-president, Paul Box, and Dave Kuipers who was in charge of the on-the-job work for Northwest. As construction progressed, Custom was billed from time to time by Mowry, the accountant, and Northwest was paid for the work performed, covering both the principal compensation called for by the oral subcontract and for extras incident thereto.

By November 1968, Northwest had erected four out of the 12 buildings, but desired to concentrate its business activities on another project in Olympia. Consequently, Northwest' approached Kuipers and Mowry concerning their coming into the project, and an oral agreement was reached between Northwest, Kuipers and Mowry that Kuipers and Mowry were to take over and complete the construction of the remaining buildings. Custom was made aware of the arrangement between the plaintiffs that Kuipers and Mowry were to take over the project, although Custom was not informed at that time as to the exact role which Northwest was to play in the completion of the buildings. Since Kuipers and Mowry were not registered contractors under the registration act, they were to utilize the various reporting numbers of Northwest in filing state and federal reports required to be submitted, and would utilize Northwest’s registration license and bond under the registration of contractors law.

The plaintiffs Kuipers and Mowry then proceeded to *456 complete the project, and they entered into a contract with Custom whereby they were to complete the remaining buildings and to receive $13,185.60 for their work. This contract listed Paul Box, the vice-president of Northwest, as a party to the contract, although Paul Box failed to sign that agreement. During performance, Kuipers and Mowry adopted the name of “M-K Construction Company” and made billings in that name to Custom. Kuipers and Mowry also signed certain certificates that they were the only persons interested in the M-K Construction Company. Subsequent to the time when Kuipers and Mowry took over completion of the project, Paul Box, who was on the payroll account of M-K Construction Company, continued to take an active part in completing the project, and was in frequent contact with Custom’s president, John Lofgren, concerning the progress of completion of the remaining buildings. In addition, Northwest’s equipment was left on the project site, and Kuipers and Mowry made payments on part of that equipment.

Under the above circumstances, Kuipers and Mowry completed the remaining buildings, and performed certain extra work, including the replacement of defective siding and installation of window liners. The defendant Custom agreed to pay the sum of $8 per hour for extra hours expended on the replacement of siding, and the defendant further agreed to pay $280 for the installation of window liners. By March or April 1969, however, a dispute arose concerning the project, and M-K Construction Company filed a lien against Custom, which was later released. About a month later Northwest, by letter signed by Mowry, formally notified Custom that Northwest was involved in the job. Custom refused to pay the $1,335 owing on the contract for the remaining buildings, and refused to pay Kuipers and Mowry for the extra work performed on the project. Custom contended that since neither Kuipers or Mowry were registered contractors under the registration act, they were not entitled to maintain an action for the collection of *457 the amount owing under the contract under RCW 18.27.080. That section of the act provides as follows:

No person engaged in the business or acting in the capacity of a contractor may bring or maintain any action in any court of this state for the collection of compensation for the performance of any work or for breach of any contract for which registration is required under this chapter without alleging and proving that he was a duly registered contractor and held a current and valid certificate of registration at the time he contracted for the performance of such work or entered into such contract.

(Italics ours.)

In an action by the three plaintiffs against the defendant Custom, the trial court held that RCW 18.27.080 was not a defense to the bringing of the suit because the plaintiffs Kuipers and Mowry were not engaged “ ‘in the pursuit of an independent business’ ” under RCW 18.27.010, and thus did not have to register under the law. The trial court accordingly entered judgment for all three plaintiffs. Although the trial court failed to hold that the three plaintiffs could recover under RCW 18.27.020 1 on the theory that the plaintiffs constituted a joint venture, the court held that Northwest continued to have a responsibility under the contract even after Kuipers and Mowry came into the project. The court further concluded that “substantial compliance” existed under the act on the part of Kuipers and Mowry since the defendant Custom had the full protection of Northwest’s bond during the course of the construction.

The Court of Appeals, Division One, in Northwest Cascade Constr., Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dobson v. Archibald
Washington Supreme Court, 2023
Trefan Archibald, V. Gina J. Dobson
505 P.3d 115 (Court of Appeals of Washington, 2022)
Montgomery v. Engelhard
352 P.3d 218 (Court of Appeals of Washington, 2015)
B.A. Van De Grift, Inc. v. Skagit County
800 P.2d 375 (Court of Appeals of Washington, 1990)
Lobak Partitions, Inc. v. Atlas Construction Co.
749 P.2d 716 (Court of Appeals of Washington, 1988)
Frank v. Fischer
739 P.2d 1145 (Washington Supreme Court, 1987)
Haberman v. Elledge
713 P.2d 746 (Court of Appeals of Washington, 1986)
Estate of Peltomaa
Montana Supreme Court, 1981
Spry v. Miller
610 P.2d 931 (Court of Appeals of Washington, 1980)
Ram Development Co. v. La Collina, Ltd.
579 P.2d 402 (Court of Appeals of Washington, 1978)
Udall Construction Co. v. Elliott
573 P.2d 809 (Court of Appeals of Washington, 1977)
Heggen Construction Co. v. Turalba
565 P.2d 420 (Washington Supreme Court, 1977)
Expert Drywall, Inc. v. Brain
564 P.2d 803 (Court of Appeals of Washington, 1977)
Rose v. Tarman
561 P.2d 1129 (Court of Appeals of Washington, 1977)
Bremmeyer v. Peter Kiewit Sons Co.
555 P.2d 1183 (Court of Appeals of Washington, 1976)
Dunkelberger v. Baker
533 P.2d 433 (Court of Appeals of Washington, 1975)
Martinson v. Publishers Forest Products Co.
521 P.2d 233 (Court of Appeals of Washington, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
519 P.2d 1, 83 Wash. 2d 453, 1974 Wash. LEXIS 923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-cascade-construction-inc-v-custom-component-structures-inc-wash-1974.