B.A. Van De Grift, Inc. v. Skagit County

800 P.2d 375, 59 Wash. App. 545, 1990 Wash. App. LEXIS 403
CourtCourt of Appeals of Washington
DecidedNovember 5, 1990
Docket25531-2-I
StatusPublished
Cited by4 cases

This text of 800 P.2d 375 (B.A. Van De Grift, Inc. v. Skagit County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B.A. Van De Grift, Inc. v. Skagit County, 800 P.2d 375, 59 Wash. App. 545, 1990 Wash. App. LEXIS 403 (Wash. Ct. App. 1990).

Opinion

Pearson, J. *

B.A. Van de Grift, Inc. (Van de Grift) appeals from a summary judgment in favor of respondent Skagit County (Skagit). Van de Grift contends that material factual issues remain regarding its claims against Skagit following cancellation of a road construction contract. We disagree and affirm the dismissal.

The materials submitted to the trial court, viewed in the light most favorable to Van de Grift, establish the following *547 sequence of events. On August 13, 1985, Skagit entered into a road construction contract with Crown for work on a portion of the Lake Cavanaugh Road. The project was to be completed in 40 days.

In mid-October 1985, work on the project ceased, at least in part because of bad weather. About 10 percent of the work had been completed; Crown had used 38 of the 40 days allotted for the project. Skagit officials expressed some dissatisfaction with Crown's progress on the project.

Sometime in February 1986, Robin LaRue, a supervising engineer for the Skagit County Public Works Department, contacted John J. King, Crown's principal, to determine if Crown intended to complete the project. King indicated to LaRue that Crown wished to complete the project and would hire appellant Van de Grift as a new subcontractor. According to Van de Grift, Skagit officials agreed to grant Crown a 30-day extension on the contract, provided that Van de Grift take over responsibility for completing the project, and promised to pay Van de Grift "in accordance with Crown's contract."

On March 17,1986, Crown and Vein de Grift entered into a road construction agreement in which Van de Grift undertook to perform all of Crown's obligations on the Lake Cavanaugh Road project "as if it were the original contracting party." The agreement provided, among other things, that Crown would arrange with Skagit to have further payment checks issued jointly to Crown and Van de Grift. Skagit maintains that it did not learn of the agreement until sometime after July 30,1986.

On May 2, 1986, Skagit officials approved Crown's request to subcontract to Van de Grift 12 enumerated items comprising 27.8 percent of the Lake Cavanaugh Road project. Van de Grift began work on the project on about May 5, 1986. Skagit issued at least one check jointly to Crown and Van de Grift, but then, apparently at Crown's request, issued checks made out solely to Crown.

On July 18, 1986, Skagit requested that Van de Grift cease work on the project; less than 10 percent of the *548 project remained to be completed. On July 30, 1986, Skagit informed Crown by letter that it was terminating the contract "for failure to prosecute the work continuously to completion with promptness and diligence." Skagit subsequently arranged for the remaining work to be completed.

At about the time that Skagit canceled the contract with Crown, Van de Grift learned that its contractor's registration certificate had lapsed in November 1985. Van de Grift's registration was reinstated in May 1987. Van de Grift was not licensed, bonded, or insured during the period that it worked on the Lake Cavanaugh Road project.

On August 6, 1986, Van de Grift filed the instant action against Crown and John J. King, alleging that Crown had breached the terms of its agreement with Van de Grift. On April 4, 1988, Van de Grift filed an amended complaint for damages against Skagit, alleging that Skagit had agreed to the substitution of Van de Grift for Crown on the Lake Cavanaugh Road project and that Skagit had breached the terms of the novation by refusing to permit Van de Grift to complete the project. Van de Grift also alleged it was entitled to recover from Skagit as a third-party beneficiary of a contract modification between Crown and Skagit and on the basis of promissory estoppel.

On December 11, 1989, the trial court granted Skagit's motion for summary judgment, dismissing Van de Grift's claims against Skagit on three grounds: (1) that Van de Grift's action was barred for failure to comply with the contractor registration requirements of RCW 18.27; (2) that no valid contract arose between Van de Grift and Skagit; and (3) that Van de Grift had no enforceable rights as a third party beneficiary under the contract between Crown and Skagit. This appeal followed.

Van de Grift first contends that the trial court erred in determining that its action against Skagit was barred by the Washington contractors registration act, RCW 18.27. In order to obtain a certificate of registration, a contractor must, among other things, provide evidence of a surety bond and public liability insurance (or provide an assigned *549 account). RCW 18.27.040, .050. In order to maintain an action for breach of contract or for compensation, a contractor must generally be duly registered:

No person engaged in the business or acting in the capacity of a contractor may bring or maintain any action in any court of this state for the collection of compensation for the performance of any work or for breach of any contract for which registration is required under this chapter without alleging and proving that he was a duly registered contractor and held a current and valid certificate of registration at the time he contracted for the performance of such work or entered into such contract.

RCW 18.27.080.

A contractor need not, however, always demonstrate literal compliance with the requirements of RCW 18.27 in order to maintain an action. "Substantial compliance" is sufficient

so long as the compliance satisfies the legislative purpose behind the registration act to protect the public against "unreliable, fraudulent, and incompetent contractors."

Northwest Cascade Constr., Inc. v. Custom Component Structures, Inc., 83 Wn.2d 453, 460, 519 P.2d 1 (1974) (quoting Murphy v. Campbell Inv. Co., 79 Wn.2d 417, 486 P.2d 1080 (1971)); see also RCW 18.27.140. The legislative purpose underlying RCW 18.27 is satisfied when the contractor seeking to maintain an action has met the bonding and insurance requirements of RCW 18.27,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arctic Stone, Ltd. v. Dadvar
112 P.3d 582 (Court of Appeals of Washington, 2005)
Williamson, Inc. v. Calibre Homes, Inc.
23 P.3d 1118 (Court of Appeals of Washington, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
800 P.2d 375, 59 Wash. App. 545, 1990 Wash. App. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ba-van-de-grift-inc-v-skagit-county-washctapp-1990.