Northrop Grumman Systems Corporation v. United States
Opinion
No. 12-286C (Filed: October 17, 2022) NOT FOR PUBLICATION
***********************
NORTHROP GRUMMAN SYSTEMS CORPORATION, Motion for Reconsideration, Plaintiff, Delay damages;
Concurrent v. delay. THE UNITED STATES,
Defendant.
********************** *
ORDER ON MOTION FOR RECONSIDERATION
On June 27, 2022, the court, after trial, entered an order adjudicating plaintiff’s complaint and defendant’s cross-claim in this breach of contract action. We rejected much of plaintiff’s affirmative claim for breach of contract damages, although we awarded $66,713,926.25 1 plus interest, reflecting the amount plaintiff was due as the contract balance plus several smaller discrete cost items and minus the government’s proven discrete cost claims. We rejected virtually in whole defendant’s counter-claim for damages associated with delay and breach through non-performance, with the exception of several more minor discrete cost claims. Judgment was deferred pending the parties’ calculation of interest under the Contract Disputes Act.
1 That amount, stated in the conclusion of our trial opinion, was the result of a minor clerical error in the tally of the sum of the discrete cost items proven by defendant. As pointed out in the parties’ joint status report of July 18, 2022, the correct amount owed to plaintiff is $66,708,926.25. That error will be corrected in the order for judgment.
Pending is defendant’s motion for reconsideration, limited to the court’s finding that defendant had not proved any entitlement to delay damages. We directed plaintiff to file a response. The matter is fully briefed. For the reasons set out below, we deny the motion for reconsideration. While we reject on the merits defendant’s request that we reconsider entitlement, we alternatively reopen for the sole purpose of making additional findings with respect to the damages aspect of the counter-claim.
I. Defendant’s Delay Claim—Entitlement
Defendant’s request for reconsideration rests primarily on our statement in the trial opinion that the government’s scheduling expert provided “no basis on which we could calculate our own measure of damages for the period of time during which defendant was not concurrently delaying the final FAT test.” 160 Fed. Cl. 744, 778 (2022). Defendant now cites other testimony from Mr. McGrath 2 as evidence upon which the court could craft a reasonably certain measure of damages for the period of delay prior to the Postal Service’s insistence on the CASTR changes. The evidence cited now is comprised of Mr. McGrath’s testimony regarding the mounting delay beginning with Northrop’s initial FAT failure in August 2008, which continued until June 2009, when the Postal Service made its CASTR demand, and the planning schedules prior to June 2009, which, according to defendant, show the “baked-in” delay as of each of the planning schedules. 3 This comparison between planning schedules and the Mod. 2 schedule of deployment results in 385 machine months, which can be multiplied by Mr. Lesch’s lost savings per machine month figure of $142,916 to net delay damage of $55,022,660, defendant argues now.
Plaintiff answers that the court did not ignore any of the planning schedules, nor any testimony from Mr. McGrath, and thus there is no basis on which reconsideration can be granted under the rules—the evidence is neither new nor was it ignored such that it would constitute plain error. See Bishop v. United States, 26 Cl. Ct. 281, 285-86 (1992). Further, Northrop argues that the assertion that the government’s damages period could be shifted to the eight months prior to the CASTR changes directive is new and is thus inappropriate to raise in a post-trial motion. We agree.
2 As defendant points out, we inadvertently referred to Mr. McGrath as Mr. McGovern in the trial opinion. 3 Defendant also argues that plaintiff essentially admitted the same in its second certified claim by adopting a “but-for” schedule that showed Northrop’s delay for this period.
As we noted in our trial opinion, defendant has not heretofore claimed “entitlement . . . to the eight months of time after the initial FAT failure but before its CASTR directive.” Id. at 778 n.28. Its delay damages theory prior to trial, during trial, and in its post-trial briefing was based on the 10 months of ultimate delay to deployment of the final machine. It cannot recover for that delay, however, because it too delayed the project by insisting on CASTR changes prior to retesting, which delayed the project for a year. Id. at 778. Nothing in defendant’s motion calls into question those findings. As such, reconsideration is unavailable.
Mr. McGrath’s testimony regarding the various planning schedules is likewise unavailing as a basis for reconsideration because, as we noted in our opinion, he did not consider the impact of CASTR-related delays in his conclusions regarding accumulated delay. We disagreed with his conclusion that CASTR was unrelated to the ultimate delay of the machines. We cannot, after-the-fact, filet and reassemble the record of his testimony to provide a new basis for a delay finding based on assumptions not made by him.
Further, as Northrop points out in its response to the present motion, the bulk of the now-claimed 385 lost machine months were incurred after the beginning of the Postal Service-caused delay period. The general rule is that a party cannot recover for delay during a period in which it was concurrently delaying the project. E.g. Blinderman Const. Co., Inc. v. United States, 695 F.2d 552, 559 (Fed. Cir. 1982). In the abstract, a party might be able to establish damages in similar circumstances, even when the delayed events take place during the concurrent period, due to a root cause analysis which shows that the delay was solely the other party’s fault and was incurred prior to the period of concurrency. Here, however, Mr. McGrath’s analysis lacks this sort of nuance. He did not consider the effect of CASTR change-caused delay. The court, thus, has no basis on which to conclude that any of the now-asserted lost savings were solely due to plaintiff’s failure to pass FAT. We deny reconsideration on this issue.
II. Defendant’s Proof of Damages for Delay
Because we rejected defendant’s entitlement to delay, it was unnecessary for us to address damages. We noted, however, that “we have serious misgivings about how defendant calculated the financial impact of each month of delay in machine delivery.” 160 Fed. Cl at 788 n.29. In its motion for reconsideration, defendant challenges that aside and argues that it had demonstrated a means of calculating the value of each month of plaintiff’s delay in delivering each machine. We reopen our prior findings
for the purpose of making additional, albeit presumably unnecessary, findings to support our skepticism.
In our earlier opinion, and to some extent additionally explained above, our fundamental difficulty with defendant’s damage theory is that it was not presented in a complete fashion. There was never a coherent connection made between the collective claim for ten months of delay, the individual month by month claims for each allegedly delayed machine, and the performance calendar. Nevertheless, even if at least one month of delay for at least one machine had been established, defendant never satisfactorily proved what that month of delay cost the Postal Service.
Free access — add to your briefcase to read the full text and ask questions with AI
Northrop Grumman Systems Corporation v. United States (Northrop Grumman Systems Corporation v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.