Northern Pac. Ry. Co. v. Goss

203 F. 904, 122 C.C.A. 198, 1913 U.S. App. LEXIS 1219
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 22, 1913
DocketNos. 3,790, 3,792
StatusPublished
Cited by9 cases

This text of 203 F. 904 (Northern Pac. Ry. Co. v. Goss) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Pac. Ry. Co. v. Goss, 203 F. 904, 122 C.C.A. 198, 1913 U.S. App. LEXIS 1219 (8th Cir. 1913).

Opinion

VAN VALKENBURGH, District Judge

(after stating the facts as above). For convenience the several causes of action will be taken up in their inverse order:

[909]*909[1] 1. It is agreed that upon the completion of the work defendant owed the plaintiffs a balance of $2,220.84 on contract price and for extra work. This was due and payable March 30, 1909; therefore, legal interest should run from that date, unless circumstances intervened which justified the railway company in withholding payment. The defendant coupled its tender with insistence upon a receipt releasing defendant from all claims of every kind and description arising out of or connected with the contract or its obligations. It based this demand upon the following provision of the contract:

“When in the opinion of the chief engineer this contract shall have boon performed, he shall so certify in writing and give a final estimate and a statement of the balance unpaid; and the company will within thirty days thereafter pay the full amount so found unpaid. The contractor will at final payment execute, acknowledge and deliver to the company under his hand and seal a valid discharge from all claims and demands growing out of or connected with this contract.”

The contract had been performed, and the engineer made the required certificate February 28th. While the language of the receipt conforms 'to the contract requirement, nevertheless the claims for damages, arising out of the collapse of the building, were then pending and unadjusted. In view of that situation, plaintiffs might well have declined to sign a receipt so sweeping in its terms. We agree with the court below that these claims, although in a sense arising out of the contract, were not connected with the performance of the work, and were not intended to be covered by the clause requiring a release as a condition to payment of the final estimate. For this reason interest from March 30, 1909, was properly allowed.

2. The second and third causes of action present the same questions, and will be considered together. The liability of an owner for damages incidental to the erection of buildings upon his property varies according to the circumstances of the case and the relationship of the parties. This has led to confusion and apparent conflict in the decided cases. The English rule, as stated by M<r. Hudson in his late work on Building Contracts, is that the contractor has no remedy against either architect or employer if the plans and specifications turn out to be unworkable, unless he has obtained some express warranty as to their nature and quality. Both parties must make their own calculations, and if one does not inquire into the matter, or runs the risks, he must take the consequences. While this statement is probably too broad to be accepted as the rule in the courts -of this country, it must be said to embody the basic principle involved, and departures must be in the nature of exceptions arising under special circumstances; otherwise great instability and confusion would be introduced into all building transactions, great or small, public or private, atid the doctrine thus announced would be constantly invoked to repair losses due to incompetency and improvidence. Certain it is that the contractor must be held to the exercise of reasonable care and the employment of reasonably essential and recognized methods of work. He must make such examination and assume such risks as, the general nature of the work and the situation of the parties impose upon him. The law does not raise in his favor such [910]*910an implied warranty as will excuse the contractor from all practical responsibility.

[2] In this connection it will not be unprofitable to restate the general principles to be deduced from a careful examination of the American decisions. An owner through his architect or engineer cannot erect upon his own property a structure so frail as to be a menace to life and limb of the public, and hence a nuisance, and avoid responsibility upon the ground of having taken counsel of those supposed to be skilled in that field of knowledge. This rule, though .harsh, is sustained by reasons of public policy. Wilkinson v. Steel & Spring Works, 73 Mich. 405, 41 N. W. 490. So an owner who presents plans and specifications which contain serious defects not patent to an ordinary mechanic, and not discoverable by ordinary diligence upon inspection, is liable to the contractor for damages resulting from such latent defects, where the plans are complex and involved, where the contractor is held to strict performance of specifications, and where the owner through his architect or engineer retains a controlling direction and supervision exclusive of direction in the contractor. In such cases the guaranty raised by the law is that the architect or engineer has sufficient learning, experience, skill, and judgment properly to perform the work, and that such plans, drawings, and specifications are suitable and efficient for the purpose designed. If they fall short of this, the owner is liable, and cannot shield himself behind the presumed skill and the advice of his agent, but such agent may be liable to his employer for shortcomings in the nature of malpractice. Bentley v. State, 73 Wis. 416, 41 N. W. 338.

Where the contractors build according to the prescribed plan furnished by the employer, they are not responsible for consequences resulting from any defect in the plan in a suit against them by the owner, as for a cistern that is not water tight (Porter v. Wilder & Son, 62 Ga. 520); or for insufficient strength in steel designed and specified (Murphy et al. v. Liberty Nat. Bank, 184 Pa. 208, 39 Atl. 143), or for a leak^ reservoir (Filbert v. City of Philadelphia, 181 Pa. 530, 37 Atl. 545); if the contractor follows the plans and uses good material (MacKnight Flintic Stone Co. v. City of New York, 160 N. Y. 72, 54 N. E. 661; Bush v. Jones, 75 C. C. A. 582, 144 Fed. 942, 6 L. R. A. [N. S.] 774). Nor are contractors responsible for what may happen afterwards to a building if they have followed the plans and used proper material and good workmanship. Clark v. Pope et al., 70 Ill. 128. This would include the case of a building completed, but not formally turned over, if it collapsed from its own , inherent weakness due to defective plans.

[3] A contractor, however, owes the duty to examine the plans and judge of their sufficiency, and may be bound by his contract even if parts specified be insufficient; especially is this true if he has made full examination and guarantees that the work can be done. Giles et al. v. Foundry Co. (Tex. Civ. App.) 24 S. W. 546. He is bound to discover defects that are reasonably discoverable or patent. Siebert v. Leonard, 17 Minn. 433 (Gil. 410). He is not excused by misunderstanding plans, as his entering into the contract implies that he understands. Clark v. Pope et al., 70 Ill. 128. All this is true if he [911]*911has experts at his command by whom the plans could be inspected and passed on (Thorn v. Mayor & Commonalty of London L. R., 1 Appeals Cases, 120); or has large experience and presumed competency, or holds himself out to have such, and the contrary is not known to the employer; or if the work is so simple that it cannot be presumed to have defects not readily discoverable to one who would undertake the work. Unforeseen difficulty, however great to the performance of a building contract, will not excuse a breach by the contractor. Dermott v. Jones, 2 Wall. 1, 7, 17, 17 L. Ed. 762; Simpson v. U.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Balder v. Haley
441 N.W.2d 539 (Court of Appeals of Minnesota, 1989)
Lewis v. Anchorage Asphalt Paving Co.
535 P.2d 1188 (Alaska Supreme Court, 1975)
Banducci v. Frank T. Hickey, Inc.
209 P.2d 398 (California Court of Appeal, 1949)
Rubin v. Coles
142 Misc. 139 (City of New York Municipal Court, 1931)
McKellar Real Estate & Investment Co. v. Paxton
269 P. 1035 (Utah Supreme Court, 1928)
State Bank v. Pew
195 P. 852 (Montana Supreme Court, 1921)
Jennings v. United States
264 F. 399 (Eighth Circuit, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
203 F. 904, 122 C.C.A. 198, 1913 U.S. App. LEXIS 1219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-pac-ry-co-v-goss-ca8-1913.