Northern Border Pipeline Co. v. Federal Energy Regulatory Commission

129 F.3d 1315, 327 U.S. App. D.C. 203, 1997 U.S. App. LEXIS 33855
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 2, 1997
DocketNos. 96-1442, 96-1444
StatusPublished
Cited by4 cases

This text of 129 F.3d 1315 (Northern Border Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Border Pipeline Co. v. Federal Energy Regulatory Commission, 129 F.3d 1315, 327 U.S. App. D.C. 203, 1997 U.S. App. LEXIS 33855 (D.C. Cir. 1997).

Opinion

Opinion for the Court filed by Circuit Judge SILBERMAN.

SILBERMAN, Circuit Judge:

Northern Border Pipeline Company and Natural Gas Pipeline Company of America petition for review of orders of the Federal Energy Regulatory Commission directing Northern Border to record the cost of a gas pipeline facility it had purchased from Natural in accordance with FERC’s Uniform System of Accounts. We deny the petition.

I.

In the late 1980s, Northern Border and Natural each considered building a pipeline to connect the end of Northern Border’s system in Ventura, Iowa to an existing Natural line near Harper, Iowa. This direct link was important because it would allow Northern Border to deliver gas directly to Natural facilities, bypassing pipelines operated by a third company, thereby avoiding an additional charge to reach Natural’s line. Natural began construction on its version of this project in June of 1990. Northern Border then dropped its own plan and instead reached agreement with Natural to purchase the new line. Natural placed the line into service on January 18,1991, and thereafter successfully applied to FERC for a certificate of public convenience to operate it under Section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c) (1994).

Northern Border, pursuant to the purchase agreement, sought the Commission’s permission to buy and operate the line. Following a proceeding at which Northern Border’s customers were provided with an opportunity to comment on the proposed transaction, FERC approved Northern Border’s application to purchase the line from Natural for approximately $78 million — a price that reflected the amount it had cost Natural to construct the facility — and granted the company its own Section 7(c) certificate to operate the line. The sale was consummated on November 1, 1992, approximately 20 months after the line had entered into service. As required, both Northern Border and Natural submitted their accounting journal entries for the purchase and sale of the line to FERC’s Chief Accountant. Natural’s proposed entries reflected a gain of $3,092,388 on the sale, the amount it recorded as accumulated depreciation for the 20 months the line had been in operation at the time of the sale. But Northern Border did not record any accumulated depreciation in its submission.

The specific accounting procedures governing a natural gas company’s purchase of an existing gas facility are found in Gas Plant Instruction No. 5 of the Commission’s Uniform System of Accounts. 18 C.F.R. pt. 201, at 526-27 (1997). A company must record the cost of acquiring a facility in a number of steps, one of which is to transfer the depreciation applicable to the original cost of the facility to a separate account, “Accumulated Provision For Depreciation of Gas Utility Plant.” Northern Border, despite its acknowledgment that the line had depreciated by approximately $3 million at the time of the purchase, did not transfer any accumulated depreciation.

The Commission, affirming its Chief Accountant, determined that Northern Border had violated its rules and directed petitioner to comply. This is not just a technical bookkeeping dispute; the Commission points out that Northern Border’s failure to comply with the Uniform System resulted in its customers paying immediately higher rates. Most companies charge customers according to a “stated rate” tariff, a specific numeric rate approved by FERC. Northern Border, however, charges its customers according to a formula tariff. This means that Northern Border’s rate is automatically calculated by a FERC-approved formula, which includes the specific cost elements on which charges to customers will be based. This ratebase includes capital expenditures for facility acquisition. Because Northern Border failed to record the accumulated depreciation, according to the Commission the company overstated its ratebase by approximately $3 million, which, in turn raised Northern Border’s rates higher than they would have been had the company complied with the Uniform Sys[1318]*1318tem.1 FERC, therefore, ordered Northern Border to refund this overcharge to its customers.

II.

The concept of original cost accounting is a bedrock principle of the Uniform System. Original cost accounting rests on the notion that the purchaser of a facility simply inherits the previous owner’s “claims to a return of and on the capital originally devoted to the public service.” United Gas Pipe Line Co., 25 F.P.C. 26, 64 (1961), rev’d and remanded on other grounds sub nom. Willmut Gas and Oil Co. v. FPC, 299 F.2d 111 (D.C.Cir.1962). In this case, it required Northern Border to report the purchased facility’s depreciated original cost, defined as the cost to Natural less accumulated depreciation. Under FERC’s ratemaking policies, a natural gas company’s rates are tied to its capital investment in facilities used for service. Absent original cost accounting, “all that pipelines would have to do to raise rates and obtain greater income would be to buy utility properties from another at a price higher than original cost and in this very simple way increase the cost of service to consumers.” Arkla Energy Resources, 61 F.E.R.C. ¶ 61,004, at 61,038, 1992 WL 424016 (1992). A company, however, is not always prohibited from recovering that amount of the purchase price in excess of depreciated original cost. It can do so by proving that “consumer benefits relative to the excess amount [paid] accrued to rate payers.” United Gas Pipe Line, 25 F.P.C. at 63. This is known as the United test.

Northern Border puts to us three grounds supporting its claim that FERC’s orders are arbitrary and capricious. First, the company argues — quite implausibly— that its proposed accounting entries actually comply with the Uniform System. The Commission’s Gas Plant Instruction No. 5B(2) requires the recording of a facility’s depreciation in a separate account if “applicable to the original cost of the properties purchased.” 18 C.F.R. pt. 201, at 526 (1997). Northern Border contends that the line’s depreciation from the time it entered into service until the sale was consummated is somehow “not applicable” to the original cost of the line because Natural had never recovered such depreciation costs from its ratepayers. FERC had approved Natural’s proposal to offer service on the line without adding the line’s cost to its ratebase (the net value of a utility’s investment upon which it is permitted to earn a rate of return).

FERC, however, does not interpret its own regulations to link the “applicability” of a purchased facility’s depreciation to the question of whether the facility’s previous owner has recovered any depreciation from its customers. If the facility has depreciated below its original cost, that is enough to require a separate recording of that depreciation. Since “[w]e afford substantial deference to the Commission’s interpretations of its own regulations, deferring to the agency unless its interpretation ‘is plainly erroneous or inconsistent with the regulations],’ ” Bluestone Energy Design, Inc. v. FERC, 74 F.3d 1288, 1292 (D.C.Cir.1996) (citations omitted), we see nothing unreasonable in FERC’s rather straightforward reading of its own Gas Plant Instruction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Texas Electric Cooperative, Inc. v. FERC
90 F.4th 579 (D.C. Circuit, 2024)
No Bdr Pipel Co v. FERC
129 F.3d 1315 (D.C. Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
129 F.3d 1315, 327 U.S. App. D.C. 203, 1997 U.S. App. LEXIS 33855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-border-pipeline-co-v-federal-energy-regulatory-commission-cadc-1997.