Colorado Interstate Gas Co. v. Federal Energy Regulatory Commission

146 F.3d 889, 330 U.S. App. D.C. 376, 1998 U.S. App. LEXIS 13352, 1998 WL 326856
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 23, 1998
Docket97-1214 and 97-1215
StatusPublished
Cited by2 cases

This text of 146 F.3d 889 (Colorado Interstate Gas Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colorado Interstate Gas Co. v. Federal Energy Regulatory Commission, 146 F.3d 889, 330 U.S. App. D.C. 376, 1998 U.S. App. LEXIS 13352, 1998 WL 326856 (D.C. Cir. 1998).

Opinion

STEPHEN F. WILLIAMS, Circuit Judge:

Under the regulatory regime now applicable to interstate pipelines, not only pipelines but other actors in the gas industry (such as independent marketers) may hold entitlements to pipeline capacity. Non-pipeline actors are free to acquire additional capacity entitlements without advance approval by the Federal Energy Regulatory Commission. But in the decisions under review here, the Commission ruled that an interstate pipeline seeking to acquire capacity rights on another pipeline (“offsystem capacity”) could do so only with the advance approval of the Commission. Because the Commission failed to offer a reasoned explanation for this difference in treatment, we remand the case for further proceedings.

Historically, natural gas pipelines bought natural gas at the wellhead and carried it to various markets for resale. As part of its effort to shift to “light-handed regulation” of the gas industry under the Natural Gas Act, the Commission in its Order No. 636 required interstate pipelines to “unbundle” their sales role from their transportation role. The Commission’s purpose was to ensure that pipelines’ natural monopoly over the transportation grid did not give them an unfair advantage over non-pipeline sellers of gas. See generally United Distribution Companies v. FERC, 88 F.3d 1105, 1125-27 (D.C.Cir.1996) (describing Order No. 636). To facilitate the unbundling process, Order No. 636 required pipelines to assign the capacity rights they held on upstream pipelines (i.e., on pipelines closer to the point of production) to their existing firm transportation customers, except for a limited amount of capacity needed for operational purposes such- as keeping line pack in balance. 1 See Order No. 636-A, FERC Stats. & Regs. ¶ 30,950, at 30,566-67 (Aug. 3, 1992). FERC reasoned that if pipelines were allowed to retain upstream capacity on other pipelines, they could inhibit the development of a competitive sales market by favoring their sales function or otherwise making it more difficult for downstream customers to buy from producers at competitive prices. See UDC, 88 F.3d at 1136.

Texas Eastern Transmission Company asked FERC for a declaration that Order No. 636 did not establish a per se rule prohibiting interstate pipelines from holding capacity on other pipelines. On January 31, 1996 the Commission issued an order agreeing with Texas Eastern. Texas Eastern Transmission Corp., 74 FERC ¶ 61,074, at 61,220 (1996) (“January Order”). It observed that Order No. 636’s rationale for requiring pipelines to assign upstream capacity had lost much of its force, since most pipelines had already implemented the un-bundling requirement. Id. “The transition to unbundled sales is now complete,” the Commission found, “and pipelines and their shippers have become more accustomed to doing business in the unbundled environment.” Id. Further, FERC recognized that “pipelines and their shippers face a dynamic and rapidly changing market,” in which “acquisition of new upstream or downstream capacity may offer a mechanism for interstate pipelines to provide shippers with access to new supply and market areas.” Id. A per se ban on acquisition of offsystem capacity would force pipelines interested in serving new markets to physically expand their own capacity, a decision that “could result in duplicative and unnecessary facilities contrary to the Commission’s goal of meeting new demand with both the least cost and least environmental impact.” Id. Allowing pipelines to acquire offsystem ca *891 pacity could also produce benefits for the acquiring pipeline’s shippers, the Commission concluded, allowing them to deal with a single pipeline and thus “avoid the administrative burdens of contracting, billing, scheduling, nominating, balancing, and dealing with penalties on multiple pipelines.” Id.

Nonetheless, the Commission said that any pipeline intending to acquire upstream or downstream capacity must secure advance Commission approval of the proposed service. Id. at 61,221. The Commission justified this requirement by reference to a variety of concerns. There appeared to be four basic ones. First, the acquiring pipeline might control customer choices or tie use of the acquired capacity to other pipeline or pipeline affiliate services. Second, depending on the treatment of the costs, rate changes might result that had adverse impacts on customers of the acquiring pipelines, on firms competing with the acquiring pipeline’s marketing affiliate, or on customer choices among supply basins. Third, there might be preferential treatment of the acquiring pipeline over the customers of the selling pipeline (presumably by the selling pipeline, but the Commission does not identify the actor). Fourth, some adverse effects might flow from the way the capacity would be managed or otherwise integrated into the existing open access operations of the acquiring pipeline. Here the Commission expressed particular concern about access to receipt and delivery points on the acquired capacity. Id. at 61,220-21.

Two interstate pipelines, Colorado Interr state Gas Company and ANR Pipeline Company, petitioned for rehearing. They contended that the Commission’s case-by-case authorization requirement discriminated against pipelines, since the Commission permits non-pipeline shippers to acquire capacity and ship gas on any pipeline without prior approval. They pointed to existing regulatory safeguards by which the Commission can guard against the concerns that purportedly justify the prior authorization requirement, arguing that these safeguards already place greater controls on pipelines than on non-pipeline shippers. The delay and uncertainty engendered by the pre-approval requirement, they said, would inflict a competitive disadvantage on the pipelines, hobbling their efforts to make prompt commitments to firm deals.

In the second order under review the Commission denied the rehearing petition, repeating many of the' arguments on which it relied in its initial order. Texas Eastern Transmission Corp., 78 FERC ¶ 61,277, at 62,161-62 (1997) (“Rehearing Order”). In addition, it reasoned that because a pipeline’s acquisition of offsystem capacity was an alternative to construction of duplicate facilities, Commission review was appropriate for the reasons justifying advance review of such construction. Id. at 62,161. CIG and ANR petitioned for review in this court.

The Commission does not seriously contest that the delay associated with case-by-case authorization practically eliminates any opportunity for pipelines to compete in the increasingly important market for short-term transportation services. Even for long-term transactions, the requirement hinders pipelines’ efforts to make prompt and reliable commitments. And it generally hampers their ability to participate in the Commission’s “capacity release” program, under which shippers who hold firm transportation capacity can release it to others when it is unneeded. See 18 C.F.R. § 284.243.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
146 F.3d 889, 330 U.S. App. D.C. 376, 1998 U.S. App. LEXIS 13352, 1998 WL 326856, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colorado-interstate-gas-co-v-federal-energy-regulatory-commission-cadc-1998.