North Wind Construction Services, LLC v. Campos EPC, LLC

District Court, D. Idaho·Decided July 18, 2023·No. 4:21-cv-00096·Unknown

Opinion

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF IDAHO

NORTH WIND CONSTRUCTION SERVICES, LLC, a Delaware limited Case No. 4:21-cv-00096-DCN liability company, MEMORANDUM DECISION AND Plaintiff, ORDER

v.

CAMPOS EPC, LLC, a Colorado limited liability company,

Defendant.

I. INTRODUCTION Before the Court is Plaintiff North Wind Construction Services, LLC’s Motion in Limine to Exclude Certain Testimony and Opinions of Defendant Campos EPC, LLC’s Expert Witness, Myron Temchin. Dkt. 75. Because oral argument would not significantly aid its decision-making, the Court will decide the motion on the briefing. Dist. Idaho Loc. Civ. R. 7.1(d)(1)(B). For the reasons below, the Motion is GRANTED in PART and DENIED in PART. II. BACKGROUND Plaintiff North Wind Services, LLC (“North Wind”) is a general contractor. Defendant Campos EPC, LLC (“Campos”) is an engineering firm that helps contractors estimate the costs of construction. In 2017, North Wind was considering submitting a bid to construct a water treatment plant in Tennessee for the Department of Energy (“DOE”). Dkt. 41, at 2. To that end, it asked Campos to provide estimation services to help formulate its bid. North Wind asked Campos to “provide quantity take-offs and estimates for structural concrete, soil excavation/backfill, and structural steel” for two major portions of the plant: the Headworks Facility and the Treatment Facility. Id.

Campos returned a proposal for scope of work.1 After some back-and-forth, North Wind sent Campos a contract (the “Agreement”), which Campos executed. This Agreement incorporated a set of general provisions providing that Campos would “be responsible for the professional quality and technical accuracy” of its estimates. Dkt. 1, at 7 (emphasis added).

Campos prepared and submitted estimates that did not factor in structural concrete for the Headworks Facility. North Wind uncritically incorporated Campos’s concrete-less estimates into its bid, which won the DOE contract. Dkt. 49, at 4; Dkt. 41–1, at 6. When North Wind began soliciting subcontractors to source and pour the concrete for the plant, it discovered that its bid had significantly underestimated the amount of concrete required.

North Wind raised the discrepancy with Campos and filed this lawsuit for breach of contract. At issue is whether Campos’s estimates were of professional quality and technically accurate. In response to North Wind’s Motion for Summary Judgment, Campos filed an expert report from an engineer named Myron Temchin. Dkt. 49-5. Temchin’s report stated Campos’s estimates were of professional quality and technically

accurate within the guidelines of the Association for the Advancement of Cost Engineering (“AACE”), (id. at 20–35), and that North Wind mismanaged its estimating process, which

1 To the extent certain background information is omitted here, the Court incorporates the facts as outlined in its summary judgment order by reference. See generally Dkt. 67. caused errors and omissions in its bid to the DOE (id. at 37–40). The Court declined to grant summary judgment on certain elements of North Wind’s breach of contract claim, finding that “professional quality” and “technical accuracy” were

ambiguous terms the jury would need to define. Dkt. 67, at 20. It also declined to exclude Temchin’s written report, finding it was relevant and reliable and thus admissible under Federal Rule of Evidence 702. Dkt. 67, at 14. The Court acknowledged, however, that parts of Temchin’s report were a fit subject for a motion in limine. Id. at 11, 14. North Wind now moves to exclude certain material in Temchin’s report, as well as certain testimony it

anticipates Temchin will offer at trial. Dkt. 75. III. LEGAL STANDARD A motion in limine is a procedural mechanism to limit in advance testimony or evidence in a particular area.” United States v. Heller, 551 F.3d 1108, 1111 (9th Cir. 2009). Because “[a]n in limine order precluding the admission of evidence or testimony is an

evidentiary ruling,” United States v. Komisaruk, 885 F.2d 490, 493 (9th Cir. 1989) (citation omitted), “a district court has discretion in ruling on a motion in limine.” United States v. Ravel, 930 F.2d 721, 726 (9th Cir. 1991). IV. ANALYSIS North Wind moves to exclude seven items of testimony or opinion from the jury:

(1) Temchin’s written report; (2) testimony or opinion that the Agreement incorporated the AACE guidelines; (3) testimony or opinion that the AACE guidelines are industry standards helpful in interpreting the ambiguous terms; (4) opinions on contract interpretation; (5) opinions on Campos’s motivations, intent, or state of mind; (6) testimony about the character of Campos’s employees Jacob Decker and Anthony Aguilar; and (7) Figure 2 and Table 5 of Temchin’s Report. The Court considers each item in turn. 1. Written expert report

North Wind argues that Temchin’s written report is hearsay and should be excluded as such. Campos responds that it has no intention of introducing the report as an exhibit at trial. Dkt. 76, at 2. The Court will hold Campos to this position. The written report may not be admitted as an exhibit.2 This is consistent with the Court’s trial practice. Written reports are hearsay and duplicative of oral testimony and do not come into evidence.

2. Opinions on Incorporation of AACE Guidelines North Wind moves to preemptively exclude any testimony or argument suggesting that the AACE guidelines were incorporated into the Agreement. The Court has already found that the AACE guidelines were not incorporated into the Agreement. Dkt. 67, at 20. It would be misleading to testify or argue otherwise, and Campos has stipulated that it will

not. Dkt. 76, at 3. Thus, Neither Campos nor Temchin may testify or argue at trial that the AACE guidelines were expressly incorporated into the Agreement. 3. Opinion that the AACE Guidelines are Industry Standard North Wind moves to exclude any argument that the AACE guidelines are industry standards that could help determine the meaning of “professional quality” or “technical

accuracy.” Idaho law allows custom and trade usage to inform the interpretation of ambiguous contract terms when “the evidence will be helpful in clarifying the ambiguity.”

2 As described below, this ruling will not prevent material from the report from being introduced, including graphics. Perkins v. Highland Enterprises, Inc., 817 P.2d 177, 182 (Idaho 1991), partially superseded by statute on other grounds as stated in Shore v. Peterson, 204 P.3d 1114, 1122 (Idaho 2009). Evidence of such custom may be offered to a factfinder so long as it satisfies

the Rules of Evidence. See, e.g., Isaak v. Journey, 15 P.2d 1069, 1072 (Idaho 1932) (holding trial court did not err by admitting or refusing to strike testimony from three witnesses seeking to establish a trade usage or custom); Itek Corp. v. Chicago Aerial Indus., Inc., 274 A.2d 141, 143 (Del. 1971) (relying on Isaak, 15 P.2d at 1072) (“It is . . . entirely proper for [an expert] to define an uncommon term according to the customs and usages of

Free access — add to your briefcase to read the full text and ask questions with AI

North Wind Construction Services, LLC v. Campos EPC, LLC, (D. Idaho 2023).

North Wind Construction Services, LLC v. Campos EPC, LLC (North Wind Construction Services, LLC v. Campos EPC, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Susan Alexis Komisaruk
885 F.2d 490 (Ninth Circuit, 1989)
United States v. Francis Ravel
930 F.2d 721 (Ninth Circuit, 1991)
Shore v. Peterson
204 P.3d 1114 (Idaho Supreme Court, 2009)
Perkins v. Highland Enterprises, Inc.
817 P.2d 177 (Idaho Supreme Court, 1991)
United States v. Heller
551 F.3d 1108 (Ninth Circuit, 2009)
Itek Corporation v. Chicago Aerial Industries, Inc.
274 A.2d 141 (Supreme Court of Delaware, 1971)
Pinnacle Engineers, Inc. v. Heron Brook, LLC.
86 P.3d 470 (Idaho Supreme Court, 2004)
City of Pomona v. Sqm North America Corporation
750 F.3d 1036 (Ninth Circuit, 2014)
Isaak v. Journey
15 P.2d 1069 (Idaho Supreme Court, 1932)
United States v. James Wells
879 F.3d 900 (Ninth Circuit, 2017)