Pinnacle Engineers, Inc. v. Heron Brook, LLC.

86 P.3d 470, 139 Idaho 756, 2004 Ida. LEXIS 28
CourtIdaho Supreme Court
DecidedFebruary 26, 2004
Docket29181
StatusPublished
Cited by7 cases

This text of 86 P.3d 470 (Pinnacle Engineers, Inc. v. Heron Brook, LLC.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinnacle Engineers, Inc. v. Heron Brook, LLC., 86 P.3d 470, 139 Idaho 756, 2004 Ida. LEXIS 28 (Idaho 2004).

Opinion

EISMANN, Justice.

This is an appeal from a judgment awarding the pláintiff as damages sums due for professional engineering services, denying the defendant relief on its counterclaims, and awarding the plaintiff costs and attorney fees. We affirm the judgment of the district court.

I. FACTS AND PROCEDURAL HISTORY

On August 19, 1999, the appellant Heron Brook, LLC, (Heron Brook) and the respondent Pinnacle Engineers, Inc., (Pinnacle) entered into a written contract under which Pinnacle agreed to perform engineering work on a subdivision that Heron Brook was developing. Heron Brook agreed to pay Pinnacle $21,580.00 to perform six specified phases of the work and to pay for work on two additional phases on a time-and-materials basis. Between August 1999 and April 2000, a number of disputes involving alleged billing errors and the quality of work being done arose between the parties regarding Pinnacle’s performance of the contract. Pinnacle completed its work under the contract on November 27, 2001. On December 11, 2001, it recorded a claim of lien against the subdivision, contending that Heron Brook had failed to pay $6,970.42 of the amount due for Pinnacle’s services. In January, Heron Brook executed a cash bond to have the lien released. On February 19, 2002, Pinnacle filed this action seeking to recover $6,970.42, plus attorney fees. On March 7, 2002, Heron *758 Brook filed an answer and counterclaim seeking unspecified damages for breach of contract, negligence, and. unjust enrichment and an order requiring Pinnacle to produce “as-built drawings.”

This case was tried to the district court, and on November 1, 2002, it issued its memorandum decision finding in favor of Pinnacle both on its complaint and on Heron Brook’s counterclaim. Judgment was ultimately entered awarding Pinnacle damages in the sum of $6,182.85, court costs in the sum of $2,191.30, and attorney fees in the sum of $61,846.38. Heron Brook timely filed this appeal.

II. ISSUES ON AJPPEAL

A. Are the trial court’s findings of fact clearly erroneous?
B. Did the trial court fail to consider the factors listed in Rule 54(e)(3) when awarding attorney fees?
C. Is Pinnacle entitled to an award of attorney fees on appeal?

III. ANALYSIS

A trial court’s findings of fact will not be set aside on appeal unless they are clearly erroneous. Bramwell v. South Rigby Canal Co., 136 Idaho 648, 39 P.3d 588 (2001); IDAHO R. CIV. P. 52(a). When deciding whether findings of fact are clearly erroneous, this Court does not substitute its view of the facts for that of the trial court. Id. It is the province of the trial court to weigh conflicting evidence and to judge the credibility of witnesses. Rowley v. Fuhrman, 133 Idaho 105, 982 P.2d 940 (1999). On appeal, this Court examines the record to see if challenged findings of fact are supported by substantial and competent evidence. Id. Evidence is regarded as substantial if a reasonable trier of fact would accept it and rely upon -it in determining whether a disputed point of fact has been proven. Bramwell v. South Rigby Canal Co., 136 Idaho 648, 39 P.3d 588 (2001).

A. Are the Trial Court’s Findings of Fact Clearly Erroneous?

1. Standard of care. In its contract with Heron Brook, Pinnacle agreed to perform its work in a 'manner consistent with the standard of skill and care ordinarily exercised by civil engineers in Boise, Idaho. Heron Brook contended that Pinnacle’s work fell below that standard in four respects, thereby constituting- a breach of the contract and negligence and entitling Heron Brook to a refund based upon unjust enrichment to the extent that its payments exceeded the reasonable value of Pinnacle’s work. The district court found that Pinnacle’s work did not fall below the standard of care applicable to civil engineers in Boise, Idaho. Heron Brook contends that the district court’s finding is clearly erroneous.

The plans drafted by Pinnacle for the project included a street elevation error pf six tenths of a foot, two storm-drain pipes imper-missibly intersecting, and two drainage swa-les that could not be constructed in the space available with the side slopes shown. There was expert, testimony that none of these errors was below the standard of care. Heron Brook argues, however, that the testimony of its expert was uncontradicted that even if it was not below the standard of care to commit the errors, it was below the standard of care nqt to pay the cost incurred by Heron Brook to correct the errors.

When the court is the trier of fact, its duties include determining the credibility of witnesses, the weight to be given their testimony, its probative effect, and the inferences and conclusions to be drawn from their testimony. Levin v. Levin, 122 Idaho 583, 836 P.2d 529 (1992). The opinion of an expert is not binding on the trial court, and, as long as it does not act arbitrarily, the trial court may reject expert testimony even when it is uncontradicted. Id.; Simpson v. Johnson, 100 Idaho 357, 597 P.2d 600 (1979).

Heron Brook’s expert witness initially defined the standard of care as “a level of services provided to our clients and the public, in accordance with the skills that are ordinarily exercised by engineers in our area.” That definition does not include paying to remedy errors that do not fall below *759 the standard of care. When first asked about an engineer being financially responsible for a mistake that did not breach the standard of care, the expert responded that the engineer’s obligation to pay for the mistake was based upon maintaining good client relations.

Q: How would you be responsible financially but not have that be below the standard of care?
A: I suppose the best answer is, in good client relations, is the best answer. There are certain times things come up during the construction of the project that you may not have been able to discover during the process of that event. And I don’t consider that breaching the standard of care requirement, but your clients had some financial obligation to perhaps something could have been discovered. And so I personally feel I have some financial obligation to help rectify that situation.

Although the expert later testified that in his opinion the standard of care required Pinnacle to pay the expenses incurred by Heron Brook to correct the errors, even if the errors themselves did not violate the standard of care, the trial court was not required to accept that testimony.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rome v. State
431 P.3d 242 (Idaho Supreme Court, 2018)
Hodge v. Waggoner
425 P.3d 1232 (Idaho Supreme Court, 2018)
Manwaring Investments, L.C. v. City of Blackfoot
405 P.3d 22 (Idaho Supreme Court, 2017)
Douglas Visser v. Auto Alley, LLC
393 P.3d 1027 (Idaho Supreme Court, 2017)
Safaris Unlimited v. Mike Von Jones
353 P.3d 1080 (Idaho Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
86 P.3d 470, 139 Idaho 756, 2004 Ida. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinnacle-engineers-inc-v-heron-brook-llc-idaho-2004.