North Star Steel Texas, Inc. v. Entergy Gulf States, Inc.

33 F. Supp. 2d 557, 1998 U.S. Dist. LEXIS 18895, 1998 WL 839771
CourtDistrict Court, S.D. Texas
DecidedSeptember 29, 1998
DocketCIV. A. H-97-3994
StatusPublished
Cited by1 cases

This text of 33 F. Supp. 2d 557 (North Star Steel Texas, Inc. v. Entergy Gulf States, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Star Steel Texas, Inc. v. Entergy Gulf States, Inc., 33 F. Supp. 2d 557, 1998 U.S. Dist. LEXIS 18895, 1998 WL 839771 (S.D. Tex. 1998).

Opinion

MEMORANDUM OPINION AND ORDER

LAKE, District Judge.

Unhappy with the price it pays for electricity, the owner of a steel mill sued under the Sherman and Clayton Acts to force a regulated electric utility to acquire electrical power from a less expensive source and pass the savings on to the steel mill. The utility seeks immunity from the suit under the antitrust state-action doctrine. Pending before the court is defendants’ Motion to Dismiss Pursuant to Fed.R.Civ.P. 12(b)(6), or in the Alternative, Motion for Summary Judgment (Docket Entry No. 7). For the reasons stated below, the court will grant the motion.

I. BACKGROUND

North Star Steel Texas, Inc., (“North Star”), a company organized under Delaware corporate law, is a wholly owned subsidiary of Cargill, Inc., a privately held corporation based in Minneapolis, Minnesota. North Star produces steel wire rod of various sizes and qualities at a steel mill in Beaumont, Texas. Instead of manufacturing the steel from scratch, the company melts down scrap steel. It then refines the steel and shapes it into a finished product. The melting, refining, and shaping processes consume a substantial amount of electrical power. 1

Defendant, Entergy Corporation, is a public utility holding company providing electrical power through its subsidiaries to approximately 2.5 million customers in Arkansas, Louisiana, Mississippi, and Texas. Defendant, Entergy Gulf States, Inc., is one of those subsidiaries. (Entergy Corporation and Entergy Gulf States, Inc. will collectively be referred to as “Entergy.”) This subsid *559 iary generates and sells electrical power in Louisiana and southeast Texas to -approximately 600,000 customers, including North Star. North Star alleges (and Entergy does not dispute) that Entergy owns and operates the only power transmission lines capable of serving North Star’s steel mill in Beaumont. 2

On March 9, 1994, North Star entered an agreement with Gulf States Utilities Co. (predecessor in interest of Entergy Gulf States, Inc.) to provide electrical services to the Beaumont mill. 3 Dissatisfied with its electric power costs under this contract, North Star began looking for alternative energy suppliers. In an effort to reduce the price it paid for electricity, North Star submitted two alternative plans to Entergy for using a third-party supplier of electricity. First, North Star proposed “earmarked power.” Under such an arrangement Entergy would purchase power from a third party for specific distribution to North Star. North Star would then purchase this allocated power from Entergy at a negotiated price. Earmarked power was North Star’s preferred arrangement. In the alternative, North Star proposed “retail wheeling.” In this arrangement North Star would purchase power directly from a third party and pay Entergy to deliver it over Entergy’s power lines to North Star’s Beaumont mill. 4 Presumably, the third-party generator would charge less for generating the wheeled or earmarked power consumed by North Star than Enter-gy, thereby reducing North Star’s electricity bill. Under both arrangements, Entergy would no longer generate the electricity consumed by North Star, but Entergy would continue to deliver it. 5

On October 28, 1997, North Star sent En-tergy a letter requesting that the parties begin negotiations to purchase power generated by a third party. 6 Entergy responded on November 6, 1997, informing North Star that its mill was not eligible for either of the proposed arrangements. 7 North Star replied on November 12, 1997, declaring that it interpreted Entergy’s November 6 letter as a denial of its requests. 8

Ón December 8,1997, North Star filed this action against Entergy, alleging three claims under the Sherman and Clayton Acts, 15 U.S.C. §§ 1-7, 12-27 (1994):

(1) refusal to deal;
(2) monopolization of an essential facility; and
(3) unlawful tying.

While Entergy has not answered North Star’s complaint, it has filed a motion to dismiss or for summary judgment, asserting immunity from antitrust liability under the state action doctrine.

II. STANDARD OF REVIEW

Because the parties have submitted material outside the pleadings, Entergy’s motion '“shall be treated as one for summary judgment and disposed of as provided in Rule 56.” Fed.R.Civ.P. 12(b); see Young v. Biggers, 938 F.2d 565, 568 (5th Cir.1991); 5A Charles Alan Wright & Arthur R. Miller, *560 Federal Practice and Procedure § 1366, at 493-501 (2d ed.1990). Because both parties treated Entergy’s motion as one for summary judgment, the court concludes that both parties have received and used a “reasonable opportunity to present all material made pertinent” to Entergy’s motion. Fed.R.Civ.P. 12(b); see Maruho Co. v. Miles, Inc., 13 F.3d 6, 8 (1st Cir.1993). The court therefore does not need to delay its decision by providing additional time for the parties to present material relevant to Entergy’s motion. See Maruho Co., 13 F.3d at 8.

Summary judgment should be granted if the record, taken as a whole, “together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c); New York Life Ins. Co. v. Travelers Ins. Co., 92 F.3d 336, 338 (5th Cir.1996); Rogers v. International Marine Terminals, Inc., 87 F.3d 755, 758 (5th Cir.1996), The Supreme Court has interpreted the plain language of Rule 56(c) as mandating “the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Trade Commission v. Equitable Resources, Inc.
512 F. Supp. 2d 361 (W.D. Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
33 F. Supp. 2d 557, 1998 U.S. Dist. LEXIS 18895, 1998 WL 839771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-star-steel-texas-inc-v-entergy-gulf-states-inc-txsd-1998.