North Carolina Utilities Commission v. Federal Energy Regulatory Commission

653 F.2d 655, 209 U.S. App. D.C. 400
Court of Appeals for the D.C. Circuit·Decided May 20, 1981·No. No. 80-1219·Published·Cited by 2 cases

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

Petitioner North Carolina Utilities Commission (“NCUC”) seeks to vacate, or in the alternative to reverse and remand for further findings, an order of the Federal Energy Regulatory Commission (“FERC” or “the Commission”)1 affirming the Initial Decision of the Administrative Law Judge (“Initial Decision”)2 in the proceedings denominated as FERC Docket No. RP75-51. This order (hereinafter referred to as “RP75-51 Order”) terminated an investigation into the causes of, and possible solutions to, curtailments of natural gas deliveries suffered by customers of Transcontinental Gas Pipe Line Corporation (“Transco”) during the 1974-75 winter season, and approved several factual findings reached by the Administrative Law Judge (“AU”) after consideration of the testimony and exhibits presented to him. Because we find petitioner lacks standing to bring this suit and because the decision to terminate this investigation instituted pursuant to section 14 of the Natural Gas Act (“NGA” or “the Act”), 15 U.S.C. § 717m(a), is committed to agency discretion, we dismiss this case for lack of jurisdiction.

I. THE FACTS

Transco, a major interstate pipeline, purchases, transports and sells natural gas to distributors in 11 states, including North Carolina. At the time of the events which gave rise to this action, its principal sources of supply lay in the outer continental shelf, an area of small, fragmented reservoirs with relatively short productive lives. During the summer of 1974, it became obvious that Transco’s supplies from these sources would fall far short of its original estimates, necessitating curtailments in planned deliveries to its customers. Accordingly, Transco issued its first curtailment plan in September, 1974, projecting a shortfall of supply over contract demand of 28 percent. Transco continued to revise its estimates of available gas supplies downwards in the fall, and contemporaneously issued a series of revisions to its original curtailment projections, increasing projected non-delivery by 30 Bcf.,3 between October and December of 1974.

On January 8, 1975, the Federal Power Commission (“FPC”)4 invoked its discre[403] tionary authority under section 14 of the Act5 to investigate Transco’s supply shortage. In its Order Instituting Investigation and Order to Show Cause, Setting Hearing, and Establishing Procedures (“Investigatory Order I”),6 the FPC outlined five areas of inquiry: (1) “the circumstances for the increased curtailment,” (2) “a determination as to the current projections of curtailment for said system,” (3) “the adequacy of the gas reserves held or controlled by [Trans-co],” (4) “the change, if any, in the level of production from such reserves, [and] the effect on deliverability of gas from reserves affected by adverse weather” and (5) “the actions taken to fully reactivate the production from those reserves.” 7 Transco and its principal suppliers presented evidence on these matters at FPC hearings held between January and March, 1975, at which time the proceedings were suspended to allow the parties to obtain additional information.

In the spring of 1975, Transco again revised its deliverability projection, this time upward to include 18 Bcf. of gas which it had previously declared unavailable. On July 1, 1975, the FPC issued an Order Amending Prior Order and Broadening Scope of Investigation (“Investigatory Order II”)8 to enlarge the scope of the investigation. The additional areas to be explored were “all facts bearing upon the alleged need for any curtailment by Transco to its customers and also to Transco’s efforts to improve deliverability upon its system consistent with its obligations to provide adequate and reliable service to its customers,” as well as “all facts bearing upon (1) the enforcement of the provisions of the Natural Gas Act or any rule, regulation, or order thereunder; and (2) remedial measures to be directed by the Commission.”9 In the same order, the FPC' removed from the scope of the investigation two of Transco’s suppliers, Mitchell Energy and Development Corporation (“Mitchell”) and Cities Service Oil Corporation (“Cities Service”) pursuant to the request of a Congressional subcommittee conducting a related investigation.10 In its Order Amending Order and Requiring Report (“Investigatory Order IV”),11 the FPC limited the scope of its investigation to Transco’s 19 largest suppliers in the interest of efficiency “[s]ince the purpose of the investigation is to locate, if possible, additional supplies of gas that can [404] be brought on stream prior to the commencement of the coming heating season.” 12

After an extensive investigation in which seven people spent six weeks in the field, the FPC staff submitted a report concluding that:

in every case, the inability to satisfy the contract requirements was caused by a combination of mechanical and water problems and/or the inability of the wells to produce due to depletion. Thus, of the DCQ [daily contract rate] rate schedules/fields investigated, it is the conclusion of the technical staff that there were no companies that could not satisfactorily account for not making their respective DCQ....

FPC Report on Investigation and Audit of Transco Producer-Suppliers (“Staff Report”), FPC Docket No. RP75-51 at 5-6; R. 4695-96; II J.A. 5-6. The Staff Report further concluded that there was no evidence of any “shut-in reserves being ‘withheld from the market’ or that there are any wells capable of delivering in excess of current levels which can be legally or in some cases economically produced.” Staff Report at 6; R. 4696; II J.A. 6 (footnote omitted). This report served as the cornerstone of the hearings which reconvened before an ALJ in February, 1976.

Free access — add to your briefcase to read the full text and ask questions with AI

North Carolina Utilities Commission v. Federal Energy Regulatory Commission, 653 F.2d 655, 209 U.S. App. D.C. 400 (D.C. Cir. 1981).

653 F.2d 655 (North Carolina Utilities Commission v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related