North Anna Environmental Coalition v. United States Nuclear Regulatory Commission

533 F.2d 655, 174 U.S. App. D.C. 428, 8 ERC 1770
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 3, 1976
DocketNo. 75-1312
StatusPublished
Cited by8 cases

This text of 533 F.2d 655 (North Anna Environmental Coalition v. United States Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Anna Environmental Coalition v. United States Nuclear Regulatory Commission, 533 F.2d 655, 174 U.S. App. D.C. 428, 8 ERC 1770 (D.C. Cir. 1976).

Opinion

Opinion for the Court filed by Senior District Judge VAN PELT.

VAN PELT, Senior District Judge:

This case is before this court upon a petition for review of a decision of the Atomic Safety and Licensing Appeal Board which affirmed an Atomic Safety and Licensing Board decision granting a license for the construction of and holding that the location of a four unit nuclear power plant facility on the proposed North Anna, Virginia, site was consistent with public health and safety. Petitioner, North Anna Environmental Coalition, which was an intervenor before the Board, is a citizens and environmental organization. Respondent is the United States Nuclear Regulatory Commission, formerly called the Atomic Energy Commission. Both are referred to herein as the Commission. The Virginia Electric and Power Co. (VEPCO) and the State of Virginia were also intervenors before the Board and made an appearance in this court.

This litigation had its beginning in 1971 when the Commission issued two Construction Permits, CPPR-77 and CPPR-78, whereby VEPCO began construction of units one and two of what was to be a four unit nuclear power reactor generating station, to be known as North Anna Power Station. The site evaluations for units one and two had originally been made in 1968. The station is located on a 1075 acre tract in Louisa County, Virginia, and, as the name implies, it is in the area of the North Anna River. The North Anna site is located in the Appalachian Piedmont Geologic Province.

Construction began on units one and two and VEPCO then applied for construction permits for the two additional nuclear reactors at the same site. Hearings were had in May, 1973. Before the permits for units three and four were granted and during [431]*431excavation for units one and two a fault was discovered.1 The Commission2 then issued a show cause order to suspend all work pending an investigation and study. This show cause order and the hearing thereon resulted in the decisions now before the court.

The Commission held a hearing which lasted twelve days and which produced 2593 pages of testimony and 74 exhibits. All parties to this case above enumerated participated as did representatives of the U. S. Geological Survey (USGS), which was the Commission’s advisor on seismic and geologic matters. By stipulation of the parties, the hearing concentrated principally on the safety of the site and the adequacy of the reactor design in light of the discovery of the fault zone. The stipulated issues involved interpretation of Section 103(d) of the Atomic Energy Act of 1954, 42 U.S.C. § 2133(d) (1970) and of 10 C.P.R. Pt. 100, App. A, (1975).3

The Licensing Board determined and the Appeal Board affirmed that there was reasonable assurance that the fault under the North Anna site was not “capable” within the meaning of the regulations and the creation of a lake (Lake Anna) did not threaten to reactivate the fault. A finding of “incapability” was found to mean that the site was as stable as one without a fault and therefore it was determined that the presence of the fault did not require changes in design specifications for units one and two and also that the fault had no bearing on approval of the construction permits for units three and four.

The Board also determined that permits for construction of units three and four should be issued and that while the construction permits for units one and two were issued prior to full implementation of the National Environmental Policy Act by the Commission, the environmental values will be adequately protected by adding certain enumerated conditions.

The issues presented on this appeal, using petitioner’s language almost verbatim, are:

1. Whether the siting of a nuclear power plant directly astride a fault creates additional risks, above and beyond those normally associated with reactor siting, that are inimical to the health and safety of the public.

2. Whether the power plant, sited in the circumstances of this case, has earthquake design assumptions of sufficient conservatism to satisfy statutory and administrative standards.

3. Whether it is required that the absence of macroseismicity directly related to the fault be proven by instrumental determination.

4. Whether the Appeal Board erred in concluding that the fault at the site was proven not to be structurally related to a capable fault.

5. Whether the “reasonable assurance of safety” test, established by Commission regulations, requires the applicant to prove beyond a reasonable doubt that the North Anna fault is not capable.

This petition for review raises issues of first impression regarding the siting of a nuclear power reactor on a fault zone. In doing so it presents for review actions of an agency whose “regulatory scheme . is virtually unique in the degree to which [432]*432broad responsibility is reposed in the administrative agency, free of close prescription in its charter as to how it shall proceed in achieving the statutory objectives.” Siegel v. Atomic Energy Comm’n, 130 U.S.App. D.C. 307, 312, 400 F.2d 778, 783 (1968). As precondition to the issuance of a license for operation of a nuclear facility, the Atomic Energy Act of 1954, 42 U.S.C. § 2011 et seq. requires a finding by the agency that the proposed facility will provide “adequate protection to the health and safety of the public.” 42 U.S.C. § 2232(a) (1970). If issuance would be “inimical” to the health and safety of the public, a license must be denied. 42 U.S.C. § 2133(d) (1970). The demand for this type of protection has consistently been construed by the Commission as a demand for “reasonable assurance” that such protections are present, and this interpretation has been upheld by the Supreme Court. Power Reactor Dev. Co. v. International Union of Electrical, Radio and Machine Workers, 367 U.S. 396, 81 S.Ct. 1529, 6 L.Ed.2d 924 (1961); Nader v. Nuclear Regulatory Comm’n, 168 U.S.App.D.C. 255, 262, 513 F.2d 1045, 1052 (1975).

It follows that this is a first-time review of the agency’s interpretation of its own recently enacted regulations.

Guidelines for such review are already established. Nearly fifteen years ago the U. S. Supreme Court in Power Reactor Dev. Co. v. International Union of Electrical, Radio and Machine Workers, supra, 367 U.S., at 408, 81 S.Ct. at 1535, 6 L.Ed.2d at 932, stated:

“We see no reason why we should not accord to the Commission’s interpretation of its own regulation and governing statute that respect which is customarily given to a practical administrative construction of a disputed provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
533 F.2d 655, 174 U.S. App. D.C. 428, 8 ERC 1770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-anna-environmental-coalition-v-united-states-nuclear-regulatory-cadc-1976.