Nordyke & Marmon Co. v. Kehlor

56 S.W. 287, 155 Mo. 643, 1900 Mo. LEXIS 268
CourtSupreme Court of Missouri
DecidedMarch 30, 1900
StatusPublished
Cited by16 cases

This text of 56 S.W. 287 (Nordyke & Marmon Co. v. Kehlor) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nordyke & Marmon Co. v. Kehlor, 56 S.W. 287, 155 Mo. 643, 1900 Mo. LEXIS 268 (Mo. 1900).

Opinion

VALLIANT, T.

Plaintiff is a corporation engaged in manufacturing flouring mills and defendant is an owner and operator of such mills. Plaintiff sued for the price of certain rolls furnished to defendant, for his mills, • and defendant-answered with a counter-claim. The cause was by consent referred to Arba N. Crane, Esq., to try all tbe issues. Upon the trial before tbe referee, tbe plaintiff’s cause of action was confessed, but the controversy was over the counter-claim, which controversy is sufficiently stated in the report of the referee as follows:

“Shortly stated, 'the case is that by its contract plaintiff agreed to furnish -a flouring mill, of a specified description, to-he paid for when completed and proved capable of producing flour of a certain percentage. Before anything considerable was done towards performing the contract, the plaintiff abandoned it on -the expressed ground that the contract was [647]*647inoperative, because the basis furnished by it for said percentage test was impossible. Later on the defendant obtained from Allis & Co., of Milwaukee, a flouring mill, located on the same site.
“The contract in question was entered into and dated May 28, 1892, between the plaintiff, as party of the first part, and the defendant and one E. E. Pierson, parties of the second part. Pierson was a miller residing in Lawrence, Kansas, and operating a flouring mill in that State. Before this suit was begun he assigned his interest in the contract to defendant Kehlor, whom I will hereafter refer to as the contracting party.”

Then continuing the report sets out the contract in hciec verba, which, without here copying, it is sufficient to say is to the effect that plaintiff agreed to furnish, within a certain period, all materials, machinery, etc., and erect “in as proper order as is known to science in the art of milling at the present time, and to deliver to them a flouring mill with an easy capacity of manufacturing fifteen hundred barrels of flour of all grades as specified hereinafter, combined, in every day of twenty-four hours run” according to specifications, etc. The contract concludes as follows:

“The meaning and intent of the above agreement is as follows:
“The party of-the first part have agreed to build a flouring mill according to the specifications, etc., furnished by them, and which is guaranteed by them to be as complete and perfect a flouring mill, as far 'as construction, durability and easy working is concerned, as any in the United States, and to make aft least the lowest percentage of flour mentioned hereafter as conditions of payment.......
“And in consideration of the above, party of the second part agrees to pay for the same when the mill is completed and proved capable of producing not less than sixty per cent of Kansas hard wheat flour, fully equal in quality to the [648]*648best fifty-five per cent 'that Kelly & Lysle can make in their mill at Leavenworth, Kansas, as now constructed and operated from the same quality of wheat and the same yield which shall not exceed four and one-half bushels to the barrel of flour, the remaining forty per cent to be fully equal to Kelly & Lysle’s remaining forty-five per cent in proportion according to grades contained in Kelly & Lysle’s remaining forty-five per cent, sixty-five thousand dollars, as follows: $15,000 to be advanced when the machinery is ready for shipment, $17,000 to be advanced during the construction of the plant and as it progresses, $32,500 to be paid upon completion of the plant by the first party as provided above.” [Then follow promises to pay $75,000 if the mill produces seventy-five per cent equal to Kelly & Lysle’s best fifty-five per cent, and to pay $85,000, if it produces ninety per cent equal to Kelly & Lysle’s best fifty-five per cent of flour.]

Eurther the report says:

“In his counter-claim the defendant states his view of the terms of the contract, and says that his motive in making it was his obligation to others to build a flouring mill at Shawnee on land acquired for that purpose. He also alleges his own readiness always to perform his part of the contract and says that, on the 5th day of Inly, 1892, the plaintiff definitely refused to perform, and never has performed its part of the contract. He alleges that the market value of the mill constructed and completed as agreed and conforming to the contract and guarantee would have been $150,000; that after the plaintiff had refused to perform its' contract, defendant tried to get a mill constructed of 'the same description, but was unable to do so because the plaintiff alone was able to construct the mill on the plan called for by the contract. He lays his damages at $85,000. The reply of the plaintiff contains a general denial of all the allegations in the counter-claim except such as are specifically admitted by said reply........
“In justification of -the refusal of plaintiff to perform the [649]*649contract, it is in substance alleged in the reply that the contract was vitiated by a mistake in basing the flour percentage test on a fifty-five per cent of Kelly & Lysle’s manufacture, the fact being that Kelly & Lysle never made and could not make flour of that percentage without first making changes in their mill, which, when solicited to do by the parties to this contract, they refused. That this test was put in the contract by the defendant who wanted to make a better flour than Kelly & Lysle — that plaintiff had no knowledge as to the grades of the Kelly & Lysle flour, but was informed by defendant and by Pierson that it was 55 per cent brat grade. And this the plaintiff believed, or it would not have entered into the contract. "When the mistake was • discovered and it was found that Kelly & Lysle would not change their mill so as to run a fifty-five per cent grade, plaintiff asked the defendant to modify the contract in this particular of the percentage test, which defendant refused. Whereupon plaintiff declined to go on with the contract. The reply also states that defendant obtained a mill of the like kind, character and quality with .that which plaintiff contracted to build, and that said mill has been erected and is now in operation on the land mentioned in defendant’s answer, 'and is capable of producing not less than 1,500 barrels of flour in each twenty-four hours of continuous run........
“Proceeding now with the inquiry in hand there is no doubt that an error was made in designating in the contract the Kelly & Lysle product as a fifty-five per cent grade of flour, and it is proper to notice how this error happened to occur.”

Then follows, in the report, a summary of the evidence on that point, and the evidence to show that Kelly & Lysle had not made and declined to make that percentage of flour. Then the referee says:

“Under date of July 1, 1892, the plaintiff wrote to the defendant that inasmuch as Kelly & Lysle made no fifty-five [650]*650per cent flour the percentage test should be changed, and suggesting a seventy per cent grade of Kelly & Lysle’s manufacturing as the standard comparison.
“To this proposition defendant replied by letter to- plaintiff under date of July 2, 1892, declining to make any change in the percentages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.T. Switzer Co. v. Midwestern Construction Co.
670 S.W.2d 69 (Missouri Court of Appeals, 1984)
Caniglia v. Nigro Corp.
441 S.W.2d 703 (Supreme Court of Missouri, 1969)
Power Service Corporation v. Joslin
175 F.2d 698 (Ninth Circuit, 1949)
Brunner v. Stix, Baer & Fuller Co.
181 S.W.2d 643 (Supreme Court of Missouri, 1944)
Union Life & Accident Insurance v. American Surety Co.
203 N.W. 172 (Nebraska Supreme Court, 1925)
Buhler Mill & Elevator Co. v. Jolly
261 S.W. 353 (Missouri Court of Appeals, 1924)
Missouri Pacific Railroad v. Askew Saddlery Co.
256 S.W. 566 (Missouri Court of Appeals, 1923)
New York Life Insurance v. Gilbert
256 S.W. 148 (Missouri Court of Appeals, 1923)
Picotte v. Mills
203 S.W. 825 (Missouri Court of Appeals, 1918)
Eucalyptus Growers Ass'n v. Orange County Nursery & Land Co.
163 P. 45 (California Supreme Court, 1917)
Miller v. Thompson
160 P. 775 (Nevada Supreme Court, 1916)
Kinney v. Eckenberger
145 P. 665 (Oregon Supreme Court, 1915)
Coffman v. Saline Valley Railroad
167 S.W. 1053 (Missouri Court of Appeals, 1914)
Kelsey v. Mackay
117 P. 714 (Washington Supreme Court, 1911)
St. Louis Southwestern Railway Co. v. Johnston
125 S.W. 61 (Court of Appeals of Texas, 1910)
E. E. Souther Iron Co. v. Laclede Power Co.
84 S.W. 450 (Missouri Court of Appeals, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
56 S.W. 287, 155 Mo. 643, 1900 Mo. LEXIS 268, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nordyke-marmon-co-v-kehlor-mo-1900.