Noble Steel, Inc. v. Williams Bros. Concrete Construction Co.

2002 OK CIV APP 66, 49 P.3d 766, 73 O.B.A.J. 1905, 19 OSHC (BNA) 1958, 2002 Okla. Civ. App. LEXIS 46, 2002 WL 1285635
CourtCourt of Civil Appeals of Oklahoma
DecidedMarch 19, 2002
Docket95,706
StatusPublished
Cited by5 cases

This text of 2002 OK CIV APP 66 (Noble Steel, Inc. v. Williams Bros. Concrete Construction Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noble Steel, Inc. v. Williams Bros. Concrete Construction Co., 2002 OK CIV APP 66, 49 P.3d 766, 73 O.B.A.J. 1905, 19 OSHC (BNA) 1958, 2002 Okla. Civ. App. LEXIS 46, 2002 WL 1285635 (Okla. Ct. App. 2002).

Opinion

Opinion By

JOE C. TAYLOR, Presiding Judge.

11 In this action for inderonity, Plaintiff, Noble Steel, Inc., appeals a judgment entered in favor of Defendant, Williams Brothers Concrete Contractors, Inc. The issue on appeal is whether Plaintiff is entitled to either contractual or implied indemnity from Defendant for penalties and costs incurred due to violations of regulations of the Oceu-pational Safety and Health Administration (OSHA). Having reviewed the record and applicable law, we find that Noble Steel is entitled to non-contractual indemnity on one OSHA violation, and reverse and remand for further proceedings.

FACTS AND PROCEDURAL HISTORY

12 Williams Brothers was the primary contractor on a construction project at the Waste Water Treatment Plant in Clinton, Oklahoma. Williams Brothers solicited bids from subcontractors for the furnishing of labor to unload and install fabricated rebar at the Clinton project. Noble Steel submitted a bid offering to work based upon specified unit prices. Noble Steel's bid included certain conditions concerning scheduling, labor, payment, and other general items; a list of items that would be included in its price, such as hand tools, wire, supervision, torches, ete.; and a list of items that were excluded from the price, such as drinking water, toilets, certain equipment, ete. Of importance to this litigation is Noble Steel's exclusion of "[slafety caps on exposed vertical reinforcing steel." Although Williams Brothers accepted Noble Steel's bid, their agreement was never memorialized in a separate written agreement.

13 During the time that Noble Steel was installing the rebar on the project, an OSHA representative visited the construction site and cited both Williams Brothers and Noble Steel with OSHA violations, including a citation for failing to cover the vertical rebar during construction, as required by 29 C.F.R. § 1926.701(b). Additionally, Noble Steel received a citation for failing to provide stairways or ladders for access into and out of the area where its employees were working, as required by 29 C.F.R. § 1926.105l(a) 1 The total penalty for Noble Steel's violations was $2,250.

[4 Williams Brothers negotiated a settlement and paid the penalties on the citations. Noble Steel, on the other hand, unsuccessful *769 ly disputed the citations administratively in the OSHA Review Commission and judicially through the Tenth Cireuit Court of Appeals. During this ill-fated protest process, Noble Steel incurred costs and attorney fees in excess of $28,000. Noble Steel then filed this action seeking indemnification from Williams Brothers for the penalties, costs, and attorney fees.

T5 The case proceeded to a bifurcated non-jury trial. After the liability portion of the trial, the trial court granted judgment to Williams Brothers based on its finding that Williams Brothers "did not breach any obligation, contractual or otherwise, owed to [Noble Steel]." Noble Steel appealed the judgment, arguing the trial court erred in refusing Noble Steel's request for findings of fact and conclusions of law. The Court of Civil Appeals agreed and remanded the case to the trial court with directions to enter findings of fact and conclusions of law. Noble Steel, Inc. v. Williams Bros. Concrete Constr. Co., Appeal No. 91,548, July 27, 1999.

T6 On remand, after receiving proposed findings of fact and conclusions of law from both Williams Brothers and Noble Steel, the trial court filed its findings of fact and conclusions of law. The trial court concluded that (1) Williams Brothers had no obligation to provide plastic protective caps for the exposed vertical rebar; (2) Williams Brothers had no obligation to Noble Steel to provide ladders for Noble Steel's employees beyond those which were available; (8) Noble Steel had the option to quit the job if it believed Williams Brothers had breached its agreement to provide safety caps, ladders, or other equipment; (4) Williams Brothers had no contractual or other obligation to indemnify Noble Steel against penalties for violations of OSHA regulations or to pay any attorney fees incurred by Noble Steel in contesting OSHA citations; (5) Williams Brothers breached no obligation, contractual or otherwise, owed to Noble Steel; (6) Noble Steel was not entitled to damages from Williams Brothers; (7) neither party was entitled to attorney fees in this action; and (8) Williams Brothers was entitled to judgment exonerating it from all liability to Noble Steel.

17 Noble Steel again appeals the judgment entered in favor of Williams Brothers. Noble Steel implicitly makes two arguments regarding indemnity: (1) Williams Brothers contracted to indemnify Noble Steel for the OSHA violations; and (2) the contractual relationship between Williams Brothers and Noble Steel gives rise to an implied right of indemnification from Williams Brothers.

CONTRACTUAL INDEMNIFICATION

T8 The two OSHA regulations which Noble Steel violated are found among OSHA regulations regarding safety and health for construction projects, 29 C.F.R. Part 1926. Under these regulations, contractors and subcontractors are prohibited from requiring "any laborer or mechanic employed in the performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health or safety, as determined under construction safety and health standards promulgated by the Secretary [of Labor] by regulation." 29 C.F.R. $ 1926.10. Furthermore, although a prime contractor and its subcontractors "may make their own arrangements with respect to obligations which might be more appropriately treated on a jobsite basis rather than individually," the subcontractors are relieved "from the actual, but not any legal, responsibility." 29 C.ER. § 1926.16(a) (emphasis added). The regulations further provide as follows:

(c) To the extent that a subcontractor of any tier agrees to perform any part of the contract, he also assumes responsibility for complying with the standards in this part with respect to that part. Thus, the prime contractor assumes the entire responsibility under the contract and the subcontractor assumes responsibility with respect to his portion of the work. With respect to subcontracted work, the prime contractor and any subcontractor or subcontractors shall be deemed to have joint responsibility.
(d) Where joint responsibility exists, both the prime contractor and his subcontractor or subcontractors, regardless of *770 tier, shall be considered subject to the enforcement provisions of the Act.

29 C.F.R. § 1926.16(c), (d).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2002 OK CIV APP 66, 49 P.3d 766, 73 O.B.A.J. 1905, 19 OSHC (BNA) 1958, 2002 Okla. Civ. App. LEXIS 46, 2002 WL 1285635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noble-steel-inc-v-williams-bros-concrete-construction-co-oklacivapp-2002.