J-McDaniel Construction Co. v. Dale E. Peters Plumbing Ltd.

2014 Ark. 282, 436 S.W.3d 458, 2014 WL 2814947, 2014 Ark. LEXIS 370
CourtSupreme Court of Arkansas
DecidedJune 19, 2014
DocketCV-13-950
StatusPublished
Cited by10 cases

This text of 2014 Ark. 282 (J-McDaniel Construction Co. v. Dale E. Peters Plumbing Ltd.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J-McDaniel Construction Co. v. Dale E. Peters Plumbing Ltd., 2014 Ark. 282, 436 S.W.3d 458, 2014 WL 2814947, 2014 Ark. LEXIS 370 (Ark. 2014).

Opinion

CLIFF HOOFMAN, Justice.

1 Appellants, J-McDaniel Construction Company, Inc., John B. McDaniel, and Barbara G. McDaniel (collectively referred to as “McDaniel”), appeal from an order of the Pulaski County Circuit Court granting summary judgment in favor of appellees, Dale E. Peters Plumbing Ltd., d/b/a Dale Peters Plumbing and Irrigation (“Peters”); Robert Bostic Hauling and Excavating, Inc., d/b/a Bobby Bostic Hauling and Excavating, and Robert Bostic individually (“Bostic”); and Esquire Marble Company (“Esquire”). On appeal, McDaniel argues that the circuit court erred by dismissing its third-party claims against appellees. We have jurisdiction of this case pursuant to Ark. Sup.Ct. R. l-2(a)(7) (2013), as this is al2subsequent appeal to this court. We reverse and remand.

McDaniel began construction on a new home in Little Rock in late 2005 and hired Peters, Bostic, and Esquire as subcontractors to complete certain tasks necessary to build the home. Peters installed plumbing; Bostic performed excavation, fill, compaction, and site-preparation work; and Esquire installed a shower in the master bedroom. Susan and David Conrad (“the Conrads”) purchased the home from McDaniel on June 2, 2006. Shortly thereafter, the Conrads noticed several problems with the home, such as settlement cracks in the walls, misalignment of doors, and a foul odor in the master bathroom. The Conrads notified McDaniel, and some attempts were made by McDaniel and Peters to remedy the problems from fall 2006 through summer 2009.

After these attempts were unsuccessful, the Conrads filed a complaint in the Pulaski County Circuit Court against McDaniel on December 2, 2009, alleging negligence and breach of the implied warranties of habitability, sound workmanship, and proper construction. The Conrads later amended their complaint on November 16, 2010, to add claims of fraudulent transfer and to pierce the corporate veil of J-McDaniel Construction Company and hold Barbara and John McDaniel personally liable. The Conrads also alleged that due to an agreement with McDaniel, the statute of limitations had been tolled until December 2, 2009.

On December 23, 2009, McDaniel filed an answer and a third-party complaint against Peters and Bostic, asserting that any foundation problems with the Conrads’ home were caused by an improperly connected shower drain in the master bathroom and faulty ^excavation, fill, or site preparation. The complaint alleged breach of contract, negligence, and breach of the implied warranties of habitability, workmanlike performance, sound workmanship, and proper construction. McDaniel asked the court to enter judgment against Bostic and Peters for an amount equal to any and all liability that might be assessed against McDaniel as a result of the Conrads’ complaint. McDaniel filed an amended third-party complaint on March 1, 2011, and added Esquire as a third-party defendant, asserting that it had improperly installed a marble shower in the master bathroom of the home. McDaniel also added claims against all third-party defendants for contribution and indemnity pursuant to common law and Ark.Code Ann. § 16-61-201.

On December 10, 2010, Peters filed a cross-claim against Bostic, seeking contribution, indemnity, and apportionment of fault pursuant to Ark.Code Ann. § 16-55-201. Bostic then filed a counter cross-claim against Peters, also seeking contribution, indemnity, and the right to apportionment of fault. On December 21, 2010, Bostic filed a motion for summary judgment on Peters’s cross-claim, which the circuit court denied on March 9, 2011.

On April 20, 2011, Peters filed a motion for summary judgment, contending that it was entitled to judgment as a matter of law on the third-party complaint because the claims for negligence and for breach of contract were both barred by the statute of limitations, because McDaniel could not prove breach of a specific contractual term where the parties did not have a written contract, and because the implied warranties did not extend from McDaniel to Peters. On May 17, 2011, Bostic filed a motion for summary judgment on the third-party complaint and a motion for reconsideration of the denial of its motion for 14summary judgment on Peters’s cross-claim. Bostic argued that the claims for negligence, breach of contract, and breach of the implied warranties were time-barred; that McDaniel could not prove that Bostic had breached a specific term of the unwritten contract; that there is no implied warranty between a general contractor and a subcontractor; that equitable indemnity did not apply because this was an oral agreement without express terms; that Arkansas had abolished joint liability except in certain circumstances that were not applicable in this case; and that there is no general right to apportionment of fault. Bostic contended that because McDaniel had no valid claim against Bostic, it was also entitled to summary judgment on Peters’s cross-claim. Subsequently, Peters filed a supplemental motion for summary judgment, which incorporated Bostic’s arguments as to the third-party complaint.

On May 18, 2011, Esquire filed a motion for summary judgment, arguing that although McDaniel alleged a breach-of-contract claim against Esquire, any claim he had was for negligence; that the statute of limitations had run on any claim for negligence; that implied warranties of habitability, sound workmanship, and proper construction do not apply to the relationship between Esquire and McDaniel; that McDaniel was not entitled to indemnity where there was no express indemnity agreement; and that McDaniel was not entitled to contribution because the Civil Justice Reform Act of 2003 eliminated a claim for contribution, as a defendant is only required to pay its several share. On May 26, 2011, Peters filed a cross-claim against Bostic and Esquire, asserting that Peters was entitled to apportionment of fault, contribution, and indemnity. Both Bostic and Esquire answered the cross-claim and denied liability.

IfiA hearing was held on the motions on May 27, 2011, and on August 22, 2011, the circuit court entered an order granting Peters’s motion for summary judgment, Bostic’s motion for reconsideration of the denial of its motion for summary judgment on Peters’s cross-claim, and Esquire’s motion for summary judgment. Peters, Bostic, and Esquire were dismissed with prejudice. The court did not state its reasons for granting the third-party defendants’ respective motions. On December 19, 2011, the circuit court entered an order stating that the Conrads had settled their claims against McDaniel and that the matter was dismissed with prejudice. McDaniel filed a timely notice of appeal from the August 22 order. However, we dismissed the appeal for lack of a final, appealable order because there remained unresolved claims by McDaniel against Bostic, by Bostic against Peters, and by Peters against Esquire. See J-McDaniel Constr. Co. v. Dale E. Peters Plumbing Ltd., 2013 Ark. 177, 2013 WL 1776463.

After the appeal was dismissed, McDaniel filed a motion for reconsideration with the circuit court on June 14, 2013, arguing that the General Assembly’s enactment of Act 1116 of 2013, which amended the Uniform Contribution Among Tortfeasors Act, made it clear that a cause of action for contribution still exists subsequent to the modification of joint and several liability, contrary to the assertions of the third-party defendants in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crystal Reid v. Miller Ag Leveling, LLC
2025 Ark. App. 22 (Court of Appeals of Arkansas, 2025)
Wynne-Ark., Inc., D/B/A Kelley's Restaurant v. Richard Baughn Construction
2020 Ark. App. 140 (Court of Appeals of Arkansas, 2020)
James Tree & Crane Service, Inc. v. Fought
2016 Ark. App. 320 (Court of Appeals of Arkansas, 2016)
English v. Robbins
2014 Ark. 511 (Supreme Court of Arkansas, 2014)
Lookabaugh v. Hanna Oil & Gas Co.
2014 Ark. App. 445 (Court of Appeals of Arkansas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ark. 282, 436 S.W.3d 458, 2014 WL 2814947, 2014 Ark. LEXIS 370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-mcdaniel-construction-co-v-dale-e-peters-plumbing-ltd-ark-2014.