No East-West Highway Committee, Inc. v. John P. Chandler, as New Hampshire Highway Commissioner

767 F.2d 21, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20753, 1985 U.S. App. LEXIS 20879
CourtCourt of Appeals for the First Circuit
DecidedJuly 12, 1985
Docket85-1360
StatusPublished
Cited by29 cases

This text of 767 F.2d 21 (No East-West Highway Committee, Inc. v. John P. Chandler, as New Hampshire Highway Commissioner) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
No East-West Highway Committee, Inc. v. John P. Chandler, as New Hampshire Highway Commissioner, 767 F.2d 21, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20753, 1985 U.S. App. LEXIS 20879 (1st Cir. 1985).

Opinion

LEVIN H. CAMPBELL, Chief Judge.

This is an appeal by the No East-West Highway Committee, Inc. (“NEWHC”) from a decision by the United States District Court for the District of New Hampshire denying NEWHC’s motion for a preliminary injunction to restrain the appellee, John P. Chandler, the New Hampshire Highway Commissioner, from proceeding with the Marlborough Route 101/Main Street Highway Project (“the Project”) on the grounds that it is a “major Federal action” that cannot be undertaken without the prior preparation of an Environmental Impact Statement (“EIS”). Finding that the district court did not abuse its discretion in denying NEWHC preliminary relief, we affirm.

I.

The roots of the present controversy go back to 1960, when the New Hampshire Department of Public Works and Highways (“NHDPW & H”) commissioned the firm of Fay, Spofford, and Thorndike (“FST”) to prepare an engineering study and design report for the relocation and upgrading of an existing road, Route 101, as a limited-access highway running east-west across southern New Hampshire. In the 1970’s, two supplementary studies for east-west highways were prepared at NHDPW & H’s behest. NHDPW & H also adopted a plan to construct a bypass of the town of Milford, and conducted studies for a bypass of Dublin, both of which correspond to parts of the overall FST study.

Fearing that the two studies, among others, and improvements being made to segments of Route 101, were the outward signs of a concealed intention to construct a four-lane limited-access east-west highway across New Hampshire, NEWHC sued in the United States District Court for the District of New Hampshire to obtain a declaratory judgment and to enjoin NHDPW & H from planning or constructing such a highway without filing an EIS. In a comprehensive opinion, then District Judge Hugh Bownes found evidence of a drift towards building an east-west highway on a segmented basis, but concluded there was as yet no overall federal or state plan to do so and that study of the proposed highway was still too vague and preliminary to require an EIS. No East-West Highway Committee, Inc. v. Whitaker, 403 F.Supp. 260 (D.N.H.1975). The court said it would view any future construction comporting with any part of the FST study other than “betterments” of existing roads as a “major Federal action” requiring the preparation of an EIS under the National Environmental Protection Act, 42 U.S.C. § 4332 et seq. (“NEPA”). Judge Bownes used the term “betterments” in his opinion mainly in connection with improvements in existing roads, including flattening curves, widening of the pavement, or improvement of the shoulder, that did not involve acquisition of rights-of-way or the use of federal funds. See 403 F.Supp. at 269. The court denied NEWHC’s request for an injunction but retained jurisdiction.

In August 1978, F.T. Comstock, Jr., a Federal Highway Division Administrator, sent Judge Bownes a letter detailing, inter alia, a proposed improvement of the portion of Route 101 that coincides with Main Street in Marlborough. The letter describes the improvement as follows:

The proposed typical section consists of two 12’ lanes and two 10’ shoulders. It will involve several large trees, and possibly several buildings (residences and gas stations) within 60-foot right-of-way width. The estimated cost is $1.2 million for 0.9 mile of reconstruction.

After a hearing that all parties attended, Judge Bownes concluded that the use of federal funds for the Main Street improvement did “not violate either the terms or the spirit of [his] original order.” No East-West Highway Committee, Inc. v. Whitaker, No. 73-199 slip op. (D.N.H. Sept. 19, 1978).

*23 That same day, Judge Bownes requested the parties to submit briefs on the development of the facts and the law since 1975. After reviewing the post-1975 case law, Judge Bownes concluded that the Supreme Court had subsequently made clear that under the language of NEPA no agency could be required to prepare an EIS before it had made a “proposal” for a “major Federal action.” He thought that it was premature for him to exercise continuing jurisdiction over the alleged plan until NHDPW & H made a proposal. He therefore terminated his order of continuing jurisdiction and rescinded all subsequent orders made pursuant thereto. No East-West Highway Committee, Inc. v. Whitaker, No. 73-199 slip op. (D.N.H. Dec. 26, 1978).

In 1977, NHDPW & H commenced the preliminary design phases of the present Project, which it represented would correct the poor condition of Main Street in Marlborough and reconstruct its surface following the completion of the town’s proposed sewer project. The plan it eventually adopted closely follows that set out in the Comstock letter. It involves the modernization of Route 101/Main Street on its existing location by widening the present 45-foot right-of-way to one for the most part 60 feet wide to accommodate two twelve-foot lanes, two ten-foot shoulders, curbs, and sidewalks; at the Project’s western end, the shoulders narrow to six feet. The total length of Route 101/Main Street affected by the Project is 9/io mile. The widening of the right-of-way necessitates the taking of a number of strips of land along the sides of Main Street, as well as the acquisition of three parcels in their entirety. Also involved are the straightening of one substandard curve to improve safety, the installation of a new roadway drainage system, and the relocation of utility poles onto the State’s right-of-way. Under the terms of the plan, the speed limit on Route 101/Main Street would remain 30 miles-per-hour. A construction contract for the Project was awarded on February 22, 1985, and construction commenced on March 13, 1985.

On March 22, 1985, NEWHC filed the present action. A hearing was held on NEWHC’s motion for preliminary injunction on March 29, 1985. By then, the state had completed the 73 necessary right-of-way takings, including the three complete parcels, whose former owners had been relocated; moved utility poles and portions of the town’s new sewer system to the right-of-way; completed tree clearing; widened the north side of Main Street; and completed o.ne thousand feet of excavation and preparation of subbase for the new roadway.

At the hearing, defendant presented testimony by Highway Design Engineer Duncan S. Pearson that Route 101/Main Street was in very poor shape, had little foundation material, was severely susceptible to frost, and had a highly fractured surface. Pierson also testified that the installation of the town’s new sewer system required so many lateral excavations of the existing surface that repaving was a practical necessity. An Environmental Assessment submitted as plaintiff’s exhibit indicates that Route 101/Main Street may have represented a danger to travellers. Pierson pointed out that the Project deviated substantially from what the earlier FST study for an east-west highway had recommended for Marlborough (the study had called for a by-pass of the town).

The parties presented experts whose testimony conflicted sharply as to whether the new Route 101/Main Street could be converted to a four-lane road after completion of the Project simply by restriping.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Recovery, LLC v. Unlimited Rec-Rep
Court of Appeals of North Carolina, 2023
Brenda Jones v. Brent York
34 F.4th 550 (Seventh Circuit, 2022)
Weichel v. Town of Braintree
D. Massachusetts, 2021
Schand v. City of Springfield
D. Massachusetts, 2020
Reid v. Donelan
D. Massachusetts, 2019
Reid v. Donelan
390 F. Supp. 3d 201 (District of Columbia, 2019)
Cosenza v. City of Worcester
D. Massachusetts, 2019
Cosenza v. City of Worcester
355 F. Supp. 3d 81 (District of Columbia, 2019)
Builders Mut. Ins. Co. v. Bob Wire Elec., Inc.
817 S.E.2d 807 (Court of Appeals of South Carolina, 2018)
James Conant & a. v. Timothy O'Meara & a.
167 N.H. 644 (Supreme Court of New Hampshire, 2015)
Ag-Innovations, Inc. v. United States
82 Fed. Cl. 69 (Federal Claims, 2008)
Jackson v. Coalter
337 F.3d 74 (First Circuit, 2003)
Schwartz v. Chan
142 F. Supp. 2d 325 (E.D. New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
767 F.2d 21, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20753, 1985 U.S. App. LEXIS 20879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/no-east-west-highway-committee-inc-v-john-p-chandler-as-new-hampshire-ca1-1985.