NHC LLC v. Centaur Construction Company Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 15, 2023
Docket1:19-cv-06332
StatusUnknown

This text of NHC LLC v. Centaur Construction Company Inc. (NHC LLC v. Centaur Construction Company Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NHC LLC v. Centaur Construction Company Inc., (N.D. Ill. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

NHC, LLC, ) ) Plaintiff, ) ) vs. ) Case No. 19 C 6332 ) CENTAUR CONSTRUCTION CO., ) SPIRO TSAPARAS, and ) PETER ALEXOPOULOS, ) ) Defendants. )

MEMORANDUM OPINION AND ORDER MATTHEW F. KENNELLY, District Judge: NHC, LLC sued Centaur Construction Co., Spiro Tsaparas, and Peter Alexopoulos, alleging fraud and breach of a contract to build the Nobu Hotel in Chicago's West Loop. The Court granted summary judgment in favor of NHC on liability with regard to the breach of contract claim against Centaur and Tsaparas. NHC's claims went to trial in August 2022 regarding liability and damages on the fraud claim and damages on the breach of contract claim. The jury found in NHC's favor against all three defendants on the fraud claim. The jury awarded NHC compensatory damages, and it also assessed punitive damages against each of the defendants. Both parties have filed motions regarding the judgment. The defendants have moved under Federal Rule of Civil Procedure 50(b) for judgment as a matter of law on all claims. In the alternative, the defendants have moved under Rule 59(a) and (e) for a new trial or to alter the damages award on the fraud claim. NHC, for its part, has moved under Rule 59(e) to amend the judgment to include pre-judgment interest. For the reasons below, the Court (1) denies the defendants' motion for judgment as a matter of law; (2) denies the defendants' motion for a new trial and/or to alter the judgment; and (3) grants NHC's motion to alter the judgment to include pre-judgment interest.

Background The Court assumes familiarity with this case's factual and procedural background, which this Court has discussed in prior written opinions. See, e.g., NHC, LLC v. Centaur Constr. Co., No. 19 C 6332, 2022 WL 823878 (N.D. Ill. Mar. 18, 2022) ("Summary Judgment Decision"); NHC, LLC v. Centaur Constr. Co., No. 19 C 6332, 2020 WL 4052657 (N.D. Ill. July 19, 2020) ("Motion to Dismiss Decision"). The following background is relevant to the post-trial motions and largely is taken from the Court's summary judgment decision, see Summary Judgment Decision, 2022 WL 823878, at *1–2, and the trial record.

A. The contract NHC acquired the Chicago Nobu Hotel project from another developer in December 2017, and it entered into a written contract with Centaur regarding the project in April 2018. The contract specified that, among other obligations, Centaur was to "pay subcontractors within seven days, provide accurate monthly reports of completion progress, and submit payment applications for completed work." Summary Judgment Decision, 2022 WL 823878, at *1. It also stated that "the project would be subject to a guaranteed maximum price (GMP) of $48,257,000" and that "the 'contract sum' was to be identified in a 'Design Build Amendment.'" Id. Section 13.2.2 of the contract governed termination of the contract by NHC (as the Owner) for cause after the parties executed a Design Build Agreement, and it included a subsection stating as follows: §13.2.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work and other damages incurred by the Owner and not expressly waived, such excess shall be retained by the Owner. If such costs and damages exceed the unpaid balance, the Design-Builder shall pay the difference to the owner. The obligation for such payments shall survive termination of the Contract.

Third Am. Compl., Ex. 1, Standard Form of Agreement Between Owner and Design- Builder ("Master Agreement"), at 36. In contrast, Section 13.1 governs "Termination or Suspension Prior to Execution of the Design-Build Amendment" and does not address costs and damages if NHC were to terminate the contract for cause before executing a Design Build Amendment. Id. at 35. The parties never executed a Design Build Amendment. B. Trial testimony Because the Court granted summary judgment in favor of NHC on liability regarding the breach of contract claim, the trial concerned only liability on the fraud claim and damages on both claims. At trial, NHC's project lead Rodrigo Chapur testified that the $48.25 million guaranteed maximum price was the agreed-upon price rather than an estimate or projection. He also stated that NHC would not have contracted with Centaur if it believed Centaur could not complete the project for that price, and his father Roberto Chapur testified that Centaur never indicated to NHC that the price could exceed $48.25 million.1 Tsaparas similarly confirmed that the Chapurs expressed an unwillingness to spend more than the guaranteed maximum price. In addition,

1 To avoid confusion, the Court will refer to Rodrigo and Roberto Chapur by their first names. Tsaparas testified that although it was possible to build a twelve-story hotel for $49 million at the time of the contract, he believed that "under any circumstances" it would have been "absolutely impossible" to "build a hotel of the quality of the Nobu Hotel Chicago for $49 million." Defs.' Rule 59 Mot. for a New Trial, Ex. 1 ("Trial Tr."), Vol. 3-B,

at 15:21–16:4. The parties' witnesses also testified about the payment applications Centaur regularly submitted to NHC over the course of the project. It is undisputed that these payment applications did not accurately reflect "work actually performed prior to the date of the application" and that NHC paid Centaur the amounts indicated on each application. Summary Judgment Decision, 2022 WL 823878, at *2. Centaur contends that it "pegged each payment application amount to the February 2018 cashflow projection and did not bill based on work it had actually performed." Id. Rodrigo testified, however, that he received an email from Tsaparas that stated "[n]ext payment request will be on May 1st for work performed in April and payment will be due June 1st.

That will be the case for the duration of the project." Trial Tr., Vol. 1-B, at 69:3–5. Rodrigo stated that based on this email and similar oral statements by Tsaparas, he understood that the amounts in the applications were based on work performed and amounts used for project expenses like paying subcontractors. Alexopoulos testified that he signed the notarized payment applications, including a final application stating that "all amounts had been paid by the contractor for work" and that no subcontractor was owed any money. Id., Vol. 3-A, at 128:15–129:16. Alexopoulos stated that he knew those statements were factually inaccurate but said he "was led to believe that the information that [he] was to be providing to [NHC] is at [NHC]'s request." Id. at 129:19–30. NHC's accountant Manuel Nunez testified that in a December 2018 meeting, Tsaparas told him and Rodrigo that the expense reports were inaccurate because they did not reflect all of Centaur's spending on the project. In early May 2019, Tsaparas informed Rodrigo that the project was over budget

even though he had previously indicated otherwise. Rodrigo met with Tsaparas to discuss the project in August of that year. Rodrigo testified that during the meeting, Tsaparas explained that he had diverted "around 6 to 8 million dollars" from the funds NHC had sent Centaur "to other different things on projects and other items that he couldn't explain." Trial Tr., Vol. 1-B, at 110:1–6. Tsaparas claimed in that meeting that he did not know where he had transferred the money, but NHC's forensic accounting expert Dayna Anderson opined at trial that Centaur used more than $10 million of NHC's payments to pay expenses unrelated to the project. This included transferring $1.5 million and $400,000 to Tsaparas's and Alexopoulous's personal bank accounts, respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carlson v. Bukovic
621 F.3d 610 (Seventh Circuit, 2010)
Greenberger v. GEICO General Insurance
631 F.3d 392 (Seventh Circuit, 2011)
Duran v. TOWN OF CICERO, ILL.
653 F.3d 632 (Seventh Circuit, 2011)
William McNabola v. Chicago Transit Authority
10 F.3d 501 (Seventh Circuit, 1993)
United States v. Carlan D. Hodges
315 F.3d 794 (Seventh Circuit, 2003)
Whitehead v. Bond
680 F.3d 919 (Seventh Circuit, 2012)
Kimberly Passananti v. Cook County
689 F.3d 655 (Seventh Circuit, 2012)
Mahaffey v. Ramos
588 F.3d 1142 (Seventh Circuit, 2009)
Obriecht v. Raemisch
517 F.3d 489 (Seventh Circuit, 2008)
Deal v. Byford
537 N.E.2d 267 (Illinois Supreme Court, 1989)
Franz v. Calaco Development Corp.
818 N.E.2d 357 (Appellate Court of Illinois, 2004)
Kopley Group v. L.P. v. Sheridan Edgewater Properties, Ltd.
876 N.E.2d 218 (Appellate Court of Illinois, 2007)
In Re Estate of Savage
392 N.E.2d 263 (Appellate Court of Illinois, 1979)
Wilson v. DiCosola
815 N.E.2d 975 (Appellate Court of Illinois, 2004)
Gehrett v. Chrysler Corp.
882 N.E.2d 1102 (Appellate Court of Illinois, 2008)
Krause v. GE Capital Mortgage Service, Inc.
731 N.E.2d 302 (Appellate Court of Illinois, 2000)
Santa's Best Craft, L.L.C. v. Zurich American Insurance
941 N.E.2d 291 (Appellate Court of Illinois, 2010)
Jeremy Venson v. Lazaro Altamirano
749 F.3d 641 (Seventh Circuit, 2014)
Mathias v. Accor Economy Lodging, Inc.
347 F.3d 672 (Seventh Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
NHC LLC v. Centaur Construction Company Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nhc-llc-v-centaur-construction-company-inc-ilnd-2023.