NHC LLC v. Centaur Construction Company Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 18, 2022
Docket1:19-cv-06332
StatusUnknown

This text of NHC LLC v. Centaur Construction Company Inc. (NHC LLC v. Centaur Construction Company Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NHC LLC v. Centaur Construction Company Inc., (N.D. Ill. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

NHC, LLC, ) ) Plaintiff, ) ) vs. ) Case No. 19 C 6332 ) CENTAUR CONSTRUCTION CO., ) SPIRO TSAPARAS, and ) PETER ALEXOPOULOS, ) ) Defendants. )

MEMORANDUM OPINION AND ORDER MATTHEW F. KENNELLY, District Judge: NHC, LLC engaged Centaur Construction Co. to develop and build the Nobu Hotel in Chicago's West Loop in late 2017. Nearly two years later, NHC terminated its contract with Centaur after the project was over budget and behind schedule. NHC sued Centaur, as well as Spiro Tsaparas (Centaur's CEO) and Peter Alexopoulos (Centaur's President), for breach of contract and fraud. Both sides have moved for summary judgment. The Court addresses those motions in this decision. Background The following facts are undisputed except where otherwise noted. NHC purchased the Chicago Nobu Hotel project from another developer in December 2017. Centaur was already the general contractor for the project at that point, but upon taking over the project, NHC increased Centaur's role to that of design builder. The Nobu Hotel was the largest project that Centaur had ever undertaken. These parties entered into a written master agreement (the contract at issue) in April 2018, but the record shows that work started prior to that agreement. Rodrigo Chapur led the project for NHC. In an e-mail Tsaparas sent to Chapur on February 19, 2018, Tsaparas asked NHC to wire Centaur $4,555,000. This amount

was broken down into seven line items (e.g. Masonry - $300,000). The first line item specified $2.5 million for Centaur, which (in the same e-mail) Tsaparas explained would "be held in [his] company and [would] be used for positive cash-flow immediately to support the company in this effort." Pl.'s Resp. to Defs.' LR 56.1(D) Stat. of Facts, Ex. 15 (dkt. no. 138-15). The e-mail further specified that the "[n]ext payment request will be on May 1st for work performed in April and payment will be due June 1st. That will be the case for the duration of the project." Id.; see also Defs.' Resp. to Pl.'s L.R. 56.1 Stat. of Add'l Facts ¶ 16 (dkt. no. 144). On February 22, 2018, Chapur asked Tsaparas to send him a projected cashflow for the project based on a $48,687,000 budget. Tsaparas responded to this request

with a table listing sixteen dates and amounts, the sum of which fell within the budget. The first entry listed February 23, 2018, for $4,555,000, which matched the February 19 e-mail. The next 15 dates listed the first of each month from June 2018 through August 2019, and the corresponding amounts ranged from $1,900,000 to $4,000,000. These amounts consisted of whole numbers in the hundred-thousands (e.g. $2,700,000, $3,300,000, etc.). The figures in this e-mail are critical to the parties' dispute: NHC says it understood them to be simply projections and thus non-binding; the defendants say they understood the figures to reflect how much they would bill NHC throughout the duration of the project notwithstanding any future agreements. On April 16, 2018, NHC and Centaur entered into a written contract. Among other provisions, the contract specified that Centaur was to follow industry standards, seek approval for subcontractors, pay subcontractors within seven days, provide accurate monthly reports of completion progress, and submit payment applications for

completed work. See Defs.' Resp. to Pl.'s L.R. 56.1 Stat. of Add'l Facts ¶¶ 19–36 (dkt. no. 144). The contract also provided that Centaur would substantially complete construction of the project within 400 days after construction began and that the project would be subject to a guaranteed maximum price (GMP) of $48,257,000. Id. ¶¶ 24, 29. The contract further included a provision stating that the "contract sum" was to be identified in a "Design-Build Amendment," but no such amendment was ever executed. Pl.'s Resp. to Defs.' LR 56.1(D) Stat. of Facts ¶¶ 26–28 (dkt. no. 136). Lastly of note, the contract included an integration clause and a non-waiver provision. Defs.' Resp. to Pl.'s L.R. 56.1 Stat. of Add'l Facts ¶¶ 24, 36 (dkt. no. 144). The parties agree that throughout the hotel's construction, Centaur submitted

payment applications that did not reflect work actually performed prior to the date of the application. Centaur says it understood the payment applications to be "'file stuffers' intended only to satisfy a formality of needing an invoice prior to releasing payment." Pl.'s Resp. to Defs.' LR 56.1(D) Stat. of Facts ¶ 41 (dkt. no. 136). Accordingly, Centaur contends, it pegged each payment application amount to the February 2018 cashflow projection and did not bill based on work it had actually performed. NHC denies this understanding and contends that it expected Centaur to send payment applications that were based on actual construction progress, in other words work actually performed. The payment application requested amounts do not perfectly align with the February 2018 table, but they are close. Compare id. ¶ 39, with Defs.' Resp. to Pl.'s L.R. 56.1 Stat. of Add'l Facts ¶¶ 40, 47 (dkt. no. 144). Additionally, Alexopoulos signed each of the payment applications, which were also notarized. From the execution of the contract through April 2019, Tsaparas consistently

represented to Chapur that the project was within budget and on schedule. Then in early May 2019, Tsaparas informed Chapur that the project was $2 to $3 million over budget. Later that month, Tsaparas sent Chapur a spreadsheet indicating that NHC had paid $41,985,000 to date and that the total project cost would be at least $54.5 million. Centaur continued to submit payment applications to NHC through June 2019, though the parties contest whether and to what extent issues arose during that time over Centaur's payment of subcontractors. In August 2019, NHC hired a second construction company, Shawmut Construction and Design, to prepare a report assessing the state of the project and auditing the project's finances. NHC served a notice of claim on Centaur on September 5, 2019, for alleged

breaches of contract. NHC filed the present suit on September 23, 2019. In its third amended complaint, NHC has sued all three defendants for fraud and sues Centaur and Tsaparas for breach of contract, the latter under a piercing-the-corporate-veil theory. Both parties have now moved for partial summary judgment. Discussion To obtain summary judgment, a party must demonstrate that "there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). There is a genuine issue of material fact if "the evidence is such that a reasonable jury could return a verdict for the nonmoving party." Hanover Ins. Co. v. N. Bldg. Co., 751 F.3d 788, 791 (7th Cir. 2014) (citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)). When parties file cross-motions for summary judgment, courts "construe all inferences in favor of the party against whom the motion under consideration is made." Cremation Soc'y of Ill., Inc. v. Int'l Bhd. of Teamsters

Local 727, 869 F.3d 610, 616 (7th Cir. 2017) (citation omitted). A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Puffer v. Allstate Insurance
675 F.3d 709 (Seventh Circuit, 2012)
Fontana v. TLD Builders, Inc.
840 N.E.2d 767 (Appellate Court of Illinois, 2005)
Kelsay v. Motorola, Inc.
384 N.E.2d 353 (Illinois Supreme Court, 1978)
Lempera v. Karner
398 N.E.2d 224 (Appellate Court of Illinois, 1979)
Lane v. Fabert
533 N.E.2d 546 (Appellate Court of Illinois, 1989)
Long v. Kemper Life Insurance Co.
553 N.E.2d 439 (Appellate Court of Illinois, 1990)
In Re Nitz
739 N.E.2d 93 (Appellate Court of Illinois, 2000)
Connick v. Suzuki Motor Co., Ltd.
675 N.E.2d 584 (Illinois Supreme Court, 1996)
Wachovia Securities, LLC v. Banco Panamericano, Inc.
674 F.3d 743 (Seventh Circuit, 2012)
Hanover Insurance Company v. Northern Building Company
751 F.3d 788 (Seventh Circuit, 2014)
Joyce Whitaker v. Milwaukee County, Wisconsin
772 F.3d 802 (Seventh Circuit, 2014)
Jannotta v. Subway Sandwich Shops, Inc.
125 F.3d 503 (Seventh Circuit, 1997)
Parker v. Four Seasons Hotels, Ltd.
845 F.3d 807 (Seventh Circuit, 2017)
Coexist Foundation, Inc. v. Fehrenbacher
865 F.3d 901 (Seventh Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
NHC LLC v. Centaur Construction Company Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nhc-llc-v-centaur-construction-company-inc-ilnd-2022.