This text of 282 F.3d 257 (Nextel West Corp. v. Unity Township) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nextel West Corp. v. Unity Township, 282 F.3d 257, 2002 U.S. App. LEXIS 3444 (3d Cir. 2002).

Opinion

282 F.3d 257

NEXTEL WEST CORP., a Delaware Corporation d/b/a Nextel Communications,
v.
UNITY TOWNSHIP, Westmoreland County, Pennsylvania, a Political Subdivision of the Commonwealth of Pennsylvania; The Zoning Hearing Board of Unity Township.

No. 01-2030.

United States Court of Appeals, Third Circuit.

Argued October 18, 2001.

Filed March 5, 2002.

COPYRIGHT MATERIAL OMITTED Clifford B. Levine (Argued), Alice B. Mitinger, Thorp Reed & Armstrong, LLP, Pittsburgh, PA, for Appellant.

Joseph J. Bosick, Jeanette H. Ho (Argued), Pietragallo, Bosick & Gordon, Pittsburgh, PA, for Appellee.

Before: MANSMANN, ALITO, and BARRY, Circuit Judges.

OPINION OF THE COURT

ALITO, Circuit Judge.

Nextel West Corporation ("Nextel"), a wireless telecommunications company, has attempted to gain permission from the defendants, Unity Township ("Township") and its Zoning Hearing Board ("ZHB"), to build a 250 foot radio tower on private property in the Township, which is located southeast of Pittsburgh. On appeal to this Court, Nextel argues that the Township violated the federal Telecommunications Act of 1996 ("TCA"), see 47 U.S.C. § 332(c)(7) (2000), in two ways: (1) its zoning ordinance has the "effect of prohibiting" all wireless telecommunications towers in the Township, and (2) the Township's disparate treatment of Nextel and a competitor constituted "unreasonable discrimination" under the TCA. 47 U.S.C. § 332(c)(7)(B)(i). The District Court held that the case was mooted by an amendment of the original zoning ordinance and therefore granted the Township's motion for summary judgement on all claims. Because we hold that this case is not moot, we reverse and remand for adjudication of the merits of Nextel's two TCA claims.

I.

To create a wireless network that provides uninterrupted cell phone service for a given geographical region, a telecommunications company must stitch together a patchwork of transmission cells. An antenna is located in the approximate center of a cell and the antenna transmits wireless signals to and from cell phone users in that cell. Because an antenna transmits signals on a line-of-sight basis, it is typically mounted on a tower or other tall structure. The perimeter of each cell is shaped by the topography surrounding the antenna. Where the terrain is flat, a cell is circular and several miles in diameter. But the hilly terrain of western Pennsylvania distorts the shape and shrinks the size of a cell. The gaps these distortions create complicate the process of stitching together cells to blanket the targeted region.

Because each wireless company is licensed by the Federal Communications Commission ("FCC") to use a different radio frequency, and because different companies use different transmission technologies, each wireless provider must deploy its own network of antennae, spaced at intervals so that their cells interlock. Providers usually prefer to mount an antenna on a existing building or telecommunications tower. When no suitable buildings or towers are located in the area where an antennae is needed, a company must build a new tower to provide wireless service in that area. For a wireless provider, the absence of coverage over a high-use area (e.g., a population cluster or major road) creates legal and commercial problems. In order to retain its FCC license for a region, a licensee must achieve quality coverage (defined by the industry as the absence of "dropped" calls) for a certain percentage of the region's population within a certain number of years after the license was granted; if the licensee fails to do so, it will forfeit its entire license. See 47 C.F.R. § 90.685(d) (2002). In addition, the ability to provide uninterrupted coverage in high-use areas is considered essential for a wireless company to remain competitive in that region.

In this case, Nextel had a significant gap in service along a segment of U.S. Route 30, Unity's only major highway.1 In that area, there were no towers or other tall structures on which Nextel could co-locate a "viable" antenna, i.e., an antenna that would cover Nextel's gap along Route 30. Nextel therefore undertook a thorough search for a location where it could place a viable tower.

The Township's original ordinance permitted telecommunications towers, inaptly categorized as "utility substations," only in manufacturing zones, and it limited these towers to 75 feet in height, well below the industry average in that region.2 See App. at 1110. The parties agreed that no tower built in any of the manufacturing districts would be viable.3 Instead, Nextel identified a nearby 38-acre farm where a viable tower could be located. The farm site was in a residential zoning district, just beyond the edge of a manufacturing district. The site was near Route 30 and would adequately cover the gap. Moreover, it did not appear that this location would present any aviation problem.

Nextel applied to the ZHB for a variance to locate a tower on the farm site. In July 1998, the ZHB denied the variance. Nextel also filed an exclusionary challenge with the ZHB attacking the ordinance's validity under the TCA and state law. Nextel contended that the ordinance effectively prohibited wireless telecommunications facilities in the Township. When the ZHB failed to respond, Nextel's exclusionary challenge was deemed denied. In September 1998, days after Nextel's exclusionary challenge was denied, the Township settled a lawsuit filed by Sprint, a competitor of Nextel, after a state court reversed the ZHB's denial of Sprint's variance. See Sprint Spectrum v. Unity Township, 80 Westmoreland L.J. 53 (Pa. Ct. Common Pleas 1998). Sprint had sought to build a cell tower in a manufacturing district to cover a service gap in its network, but the proposed height of the tower (250 feet) far exceeded the ordinance's limit. In accordance with the settlement agreement, Sprint withdrew its exclusionary challenge against the ordinance, and the Township issued a variance that allowed Sprint to build its 250-foot tower.

Nextel timely filed two TCA actions based on these two denials from the ZHB, and the District Court consolidated the two actions. While this litigation was pending before the District Court, the Township amended its original ordinance in February 1999 in three ways. First, the amended ordinance allowed wireless telecommunications towers in two additional zoning districts (agricultural and conservation, but still not residential). Second, it permitted towers as a "special exception" if the site in question satisfied certain criteria. See App. at 1201-06. Third, it raised the maximum height of towers in manufacturing districts to 180 feet and in agricultural and conservation districts to 150 feet (plus 50 feet more if the setback was sufficient). Nextel argues, however, that the criteria to qualify a tower site for a special exception are so burdensome and the additional districts so remote from Route 30 that, in actuality, Nextel's ability to obtain approval for a viable tower was effectively unaltered by the amendment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DEFOGGI v. THOMPSON
D. New Jersey, 2025
T Mobile Northeast LLC v. City of Wilmington
913 F.3d 311 (Third Circuit, 2019)
Horvath Towers III, LLC v. Zoning Hearing Board of Butler Township
247 F. Supp. 3d 520 (M.D. Pennsylvania, 2017)
Global Tower, LLC v. Hamilton Township
897 F. Supp. 2d 237 (M.D. Pennsylvania, 2012)
Liberty Towers, LLC v. Zoning Hearing Board
748 F. Supp. 2d 437 (E.D. Pennsylvania, 2010)
Democracy Rising PA v. John Celluci
380 F. App'x 155 (Third Circuit, 2010)
Democracy Rising PA v. Celluci
380 F. App'x 155 (Third Circuit, 2010)
Coastal Outdoor Advertising Group, LLC v. Township of Union
676 F. Supp. 2d 337 (D. New Jersey, 2009)
Omnipoint Holdings, Inc. v. City of Cranston
586 F.3d 38 (First Circuit, 2009)
T-MOBILE USA, INC. v. City of Anacortes
572 F.3d 987 (Ninth Circuit, 2009)
Democracy Rising PA v. Celluci
603 F. Supp. 2d 780 (M.D. Pennsylvania, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
282 F.3d 257, 2002 U.S. App. LEXIS 3444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nextel-west-corp-v-unity-township-ca3-2002.