Nextel Partners, Inc. v. Clarks Summit Borough

958 A.2d 587, 2008 Pa. Commw. LEXIS 501, 2008 WL 4527454
CourtCommonwealth Court of Pennsylvania
DecidedOctober 10, 2008
Docket1375 C.D. 2007, 1376 C.D. 2007
StatusPublished
Cited by14 cases

This text of 958 A.2d 587 (Nextel Partners, Inc. v. Clarks Summit Borough) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nextel Partners, Inc. v. Clarks Summit Borough, 958 A.2d 587, 2008 Pa. Commw. LEXIS 501, 2008 WL 4527454 (Pa. Ct. App. 2008).

Opinion

OPINION BY

Judge SIMPSON.

In these consolidated land use appeals, Clarks Summit Borough/Borough Council (Borough Council) and Stephen J. Evers (Objector) ask whether the Court of Common Pleas of Lackawanna County (trial court) erred in determining Nextel Partners, Inc. (Applicant) was entitled to a deemed approval of its conditional use application seeking to construct a cellular communications tower. Borough Council denied the application on the grounds it did not satisfy several requirements in the Clarks Summit Borough Zoning Ordinance (Ordinance). On appeal, the trial court reversed, concluding Applicant was entitled to a deemed approval because Borough Council did not hold a timely hearing on Applicant’s application. Objector and Borough Council argue the trial court erred in determining Applicant was entitled to a deemed approval and in failing to make its own findings as to the merits of Applicant’s application. Discerning no merit in these assertions, we affirm.

On June 23, 2005, Applicant, by and through its agent, Launch Wireless, submitted a conditional use application seeking to construct a 150-foot wireless communications tower on a parcel located in the Borough’s Highway Commercial (HC) Zoning District. Applicant claimed its proposed use was permitted as a conditional use under Section 809 of the Ordinance.

Shortly thereafter, Borough Council requested its engineer review Applicant’s *589 conditional use application. The engineer issued a letter to Borough Council on July 13, 2005, indicating the proposed conditional use did not comply with several requirements in Section 809 of the Ordinance.

Thereafter, on July 20, 2005, the Borough Planning Commission met to discuss Applicant’s conditional use request. Among others, a representative for Applicant and the Borough Planner attended this meeting. Notably, the minutes of the meeting indicate:

[The Borough Planner] suggested a meeting with [the Borough Engineer], [Applicant’s representative] and himself to work out some of the details. [Borough] Council is required to hold a hearing within 60 days. If all the details don’t work out, [the Borough Planner] said he was sure that [Applicant would be willing to grant an extension. [Applicant’s representative] said okay, great.

Reproduced Record (R.R.) at 7a.

On September 13, 2005, Borough Council held a hearing on Applicant’s application. At the hearing, Applicant asserted it was entitled to a deemed approval because Borough Council did not hold a hearing on its application within 60 days of when Applicant filed its application. Borough Council rejected this assertion. In addition, after the hearing, Borough Council issued an opinion in which it denied Applicant’s application because it did not comply with several Ordinance requirements. Borough Council also determined Applicant did not prove it was necessary for the proposed tower to be 150 feet in height. Further, Applicant conceded it could not meet the setback requirement necessary to establish that a collapse of the tower would not affect adjoining properties. Borough Council also determined Applicant did not provide evidence of a written contract with wireless service providers, which was necessary to establish feasibility of the facilities. Applicant appealed to the trial court. 1

Without taking additional evidence, the trial court reversed. The trial court determined Applicant was entitled to a deemed approval of its application because Borough Council did not hold a hearing within 60 days of when it received the application on June 23, 2005. In its order, the trial court directed the parties to post the property as “deemed approved” in order to “trigger” the appeal period pursuant to this Court’s decision in Magyar v. Zoning Hearing Board of Lewis Township, 885 A.2d 123 (Pa.Cmwlth.2005). Borough Council and Objector appealed to this Court; this Court consolidated the appeals.

On appeal, 2 Borough Council argues the trial court erred in concluding Applicant’s conditional use application was deemed approved based on Borough Council’s failure to hold a hearing within 60 days of June 23, 2005. It contends Applicant’s initial submission was incomplete, and Applicant’s representatives did not complete the application process until August 31, 2005. Borough Council points out it conducted a hearing on the completed application on September 13, 2005. Borough Council argues after Applicant’s initial submission on June 23, 2005, it promptly reviewed the incomplete submission and engaged in continuous communication with Applicant’s *590 representatives to assist them in completing the application process. Borough Council maintains the Borough’s engineer and the planning commission reviewed Applicant’s incomplete submission in July and August 2005 and informed Applicant of the materials needed. Borough Council argues Applicant did not submit all required materials until August 31, 2005, at which time a hearing before Borough Council was scheduled.

Borough Council also maintains the minutes of the July 2005 Planning Commission meeting indicate Applicant’s representative acknowledged the application was incomplete, and Applicant agreed to an extension for Borough Council to conduct a hearing.

Alternatively, Borough Council asserts, if a deemed approval occurred the trial court erred in failing to make findings on the merits of Applicant’s conditional use application. Gryshuk, v. Kolb, 685 A.2d 629 (Pa.Cmwlth.1996). Thus, Borough Council asks us to remand to the trial court for findings on whether Applicant’s proposal complies with the Ordinance.

Similarly, Objector argues the trial court erred in determining Applicant was entitled to a deemed approval where: the application was incomplete when filed under the terms of the Ordinance; Applicant tacitly agreed to an extension of the 60-day period for a hearing; and, Applicant’s delay in submitting documents it knew were necessary amounted to an attempt to manipulate the process in the Ordinance and frustrate the purpose of Section 908(9) of the Pennsylvania Municipalities Planning Code (MPC). 3 See Philomeno & Salamone v. Bd. of Supervisors of U. Merion Twp., 882 A.2d 1044 (Pa.Cmwlth.2005), appeal granted, 588 Pa. 790, 906 A.2d 1197 (2006) (recognizing the failure of a municipality to rule on an application within the requisite time period can be the result of confusion and protracted proceedings caused by the applicant).

Objector also asserts the trial court failed to recognize that Borough Council properly denied the application because it did not comply with general lot size and setback requirements, and it did not provide sufficient documentation to justify a waiver of the Ordinance’s setback requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plum Creek MHC, LLC v. The ZHB of The Borough of Plum
Commonwealth Court of Pennsylvania, 2025
D. Folk & J. Folk v. Mifflin Twp. ZHB
Commonwealth Court of Pennsylvania, 2024
Brookview Solar I, LLC v. Mount Joy Twp. Bd. of Supers.
Commonwealth Court of Pennsylvania, 2023
Heisler's Egg Farm, Inc. v. Walker Twp. ZHB
Commonwealth Court of Pennsylvania, 2020
All State Signz Company v. Burgettstown Borough
154 A.3d 416 (Commonwealth Court of Pennsylvania, 2017)
Gaughen LLC v. Borough Council of the Borough of Mechanicsburg
128 A.3d 355 (Commonwealth Court of Pennsylvania, 2015)
Gibraltar Rock, Inc. v. New Hanover Township Zoning Hearing Board
68 A.3d 1012 (Commonwealth Court of Pennsylvania, 2013)
DeSantis v. Zoning Hearing Board
53 A.3d 959 (Commonwealth Court of Pennsylvania, 2012)
Ulsh v. Zoning Hearing Board of Lower Paxton Township
22 A.3d 244 (Commonwealth Court of Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
958 A.2d 587, 2008 Pa. Commw. LEXIS 501, 2008 WL 4527454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nextel-partners-inc-v-clarks-summit-borough-pacommwct-2008.