Abarbanel v. Solebury Township

572 A.2d 862, 132 Pa. Commw. 326, 1990 Pa. Commw. LEXIS 219
CourtCommonwealth Court of Pennsylvania
DecidedApril 5, 1990
Docket1998 C.D. 1989
StatusPublished
Cited by14 cases

This text of 572 A.2d 862 (Abarbanel v. Solebury Township) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abarbanel v. Solebury Township, 572 A.2d 862, 132 Pa. Commw. 326, 1990 Pa. Commw. LEXIS 219 (Pa. Ct. App. 1990).

Opinion

*328 CRAIG, Judge.

Ian A. Abarbanel (developer) appeals an order of Judge Biester of the Court of Common Pleas of Bucks County which affirmed the Solebury Township Board of Supervisors’ denial of the developer’s application for approval of a preliminary subdivision plan. The issue is whether the township acted in bad faith in denying the application after allowing one additional time period to bring the plan into compliance with the township’s ordinances.

The record indicates that on October 13, 1987, the developer submitted his preliminary subdivision plan for the board’s approval. The plan sought to subdivide a 58-acre tract into 37 parcels for single-family homes. The board directed the plan to the township’s planning commission, which first reviewed it on November 9, 1987. The commission then deferred the matter to its December 1987 meeting because the township engineer had not completed his report on the developer’s plan.

On December 10, 1987, the township engineer submitted his report. The report detailed approximately 40 objections to the developer’s plan. 1 On the same day, the commission reviewed both the developer’s plan and the township engineer’s report, and deferred further action on the plan.

The developer took no additional formal action with the township until January 7, 1988, when the developer’s engineer contacted the township and requested a 30-day extension to address the township engineer’s objections. During this 30-day extension, the developer did not file a revised plan. Then, by letter of February 10, 1988, the developer requested an additional 60-day extension, and stated that any revisions submitted to the board would be considered as *329 a supplement to the original plan, and not a submission of a new plan.

However, as stated in the board’s findings, the board considered the developer’s request for an second extension as an attempt to keep his 1987 application alive and thus to avoid being subject to land use legislation enacted by the township in 1988. On January 7, 1988, the township had adopted an environmental impact assessment ordinance requiring developers to submit reports on the environmental impact of their development relating to certain environmental issues. 2

Therefore, because the developer had failed to submit a revised plan after the 30-day extension, and because the developer gave no indication that his revised plans would be promptly submitted, the board denied the developer’s application on February 16, 1988. The developer received notice of the board’s decision on March 2, 1988.

On March 21, 1988, the developer appealed the board’s decision to the trial court, which remanded the matter to the board for determination of whether the board acted in good faith. On remand, the board held public hearings on the matter, and after reviewing the evidence, the board concluded that they acted in good faith in denying the application. The board then issued findings of fact, which the trial court reviewed in affirming the board’s determination. This appeal followed. 3

On appeal, the developer contends that the board failed to act in good faith in reviewing his subdivision plan.

*330 We note that section 508 of the Pennsylvania Municipalities Planning Code (Code), Act of July 31, 1968, P.L. 805, as amended, 53 P.S. § 10508, requires a municipality to act on a subdivision plan within a period of time fixed by municipal ordinance. However, regardless of the time set by their own ordinances, a municipality must render a decision on a plan within 90 days or the plan is deemed approved. See Morris v. Northampton County Hanover Township Board of Supervisors, 39 Pa.Commonwealth Ct. 466, 395 A.2d 697 (1978). If a municipality allows a developer to submit a revised plan because of the original plan’s deficiencies, a municipality has an additional 90-day period from the date of filing of the revised plan to render a decision. DePaul Realty Co. v. Borough of Quakertown, 15 Pa.Commonwealth Ct. 16, 324 A.2d 832 (1974).

In the present case, the developer cites Raum v. Board of Supervisors of Tredyffrin Township, 29 Pa.Commonwealth Ct. 9, 370 A.2d 777 (1977) and Township of Plymouth v. County of Montgomery, 121 Pa.Commonwealth Ct. 303, 550 A.2d 1033 (1988) to support his contention.

In Raum, the developer submitted a revised plan which cured defects noted by the township’s planning commission. However, because the developer submitted the revised plan at the board’s deadline, the board refused to consider the plan. In reversing the board’s decision on bad faith grounds, this court stated that:

A municipality has a legal obligation to proceed in good faith in reviewing and processing development plans. The duty of good faith includes discussing matters involving technical requirement or ordinance interpretation with the applicant, and providing an applicant a reasonable opportunity to respond to objections or to modify plans where there has been a misunderstanding or difference of opinion.

Raum, 29 Pa.Commonwealth Ct. at 48, 370 A.2d at 798.

In Township of Plymouth, the township rejected the county’s plan to construct a trash-to-steam plant. The. county then submitted a revised plan which cured most of *331 the township’s objections. However, the township refused to consider the revised plan, and this court concluded that the township acted in bad faith in failing to consider the county’s revised plan, stating that:

The matter which is significant, and with which the trial judge was concerned, was whether the township gave fair consideration to the application following the previous disposition of this case by this court, or was unlawfully obstructive in the manner condemned by this court in Raum....

Township of Plymouth, 121 Pa.Commonwealth Ct. at 315, 550 A.2d at 1038.

A significant difference between Raum and Township of Plymouth and this case is that, in the cited cases, the developers submitted their revised plans to the boards, which the boards then refused to consider. In this case, the developer failed to submit a revised plan in a timely manner for the board’s determination under § 508. As the trial judge stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. Haring v. Newberry Twp.
Commonwealth Court of Pennsylvania, 2024
Hummelstown Swim Club v. Borough of Hummelstown
Commonwealth Court of Pennsylvania, 2017
Delchester Developers, L.P. v. London Grove Township Board of Supervisors
161 A.3d 1106 (Commonwealth Court of Pennsylvania, 2017)
Highway Materials, Inc. v. Board of Supervisors of Whitemarsh Township
974 A.2d 539 (Commonwealth Court of Pennsylvania, 2009)
Philomeno & Salamone v. Board of Supervisors
966 A.2d 1109 (Supreme Court of Pennsylvania, 2009)
Nextel Partners, Inc. v. Clarks Summit Borough
958 A.2d 587 (Commonwealth Court of Pennsylvania, 2008)
Kassouf v. Township of Scott
883 A.2d 463 (Supreme Court of Pennsylvania, 2005)
Advantage Development, Inc. v. Board of Supervisors
688 A.2d 759 (Commonwealth Court of Pennsylvania, 1997)
Overlook Associates v. Borough Council
10 Pa. D. & C.4th 121 (York County Court of Common Pleas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
572 A.2d 862, 132 Pa. Commw. 326, 1990 Pa. Commw. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abarbanel-v-solebury-township-pacommwct-1990.