Nextel Communications of the Mid-Atlantic, Inc. v. City of Margate

305 F.3d 188, 2002 WL 31111830
Court of Appeals for the Third Circuit·Decided September 24, 2002·No. 00-4282·Published·Cited by 5 cases

Opinion

OPINION OF THE COURT

JOHN R. GIBSON, Circuit Judge.

Nextel Communications of the Mid-Atlantic, Inc., appeals from the denial of its *190 motion for preliminary injunction against the City of Margate, New Jersey, the Zoning Board of Adjustment for -the City of Margate, and A. Ralph Perone. The essence of Nextel’s argument is that it is entitled to relief under the Federal Telecommunications Act of 1996, see 47 U.S.C. § 332(c)(7) (Supp. V 1999), as a result of the Defendants’ efforts to reopen hearings on Nextel’s construction of a previously approved telecommunications facility. Because Nextel’s claims are not yet ripe, we vacate the district court’s order and remand with directions to dismiss without prejudice.

On October 4, 1999, Nextel entered into a lease agreement with Margate Towers Condominium Association, Inc. The agreement gave Nextel permission to place twelve communication antennas and an eight-foot by fourteen-foot equipment cabinet on the roof of Margate Towers, an eleven-story building containing condominium units. In anticipation of the lease agreement, Nextel submitted a Staff Committee Review Application to the Land Use Administrator for the City of Margate. Nextel also submitted an Application for Action by the Zoning Board, requesting a “D Variance” to allow construction of the twelve antennas and equipment cabinet. Both applications referred to an eight-foot by fourteen-foot equipment cabinet.

A hearing before the Zoning Board was scheduled and interested property owners were given public notice. Again, both the notice and hearing agenda stated the planned equipment cabinet measured eight feet by fourteen feet. At the hearing, however, Kevin Wolfe, a land surveyor testifying on behalf of Nextel, stated the equipment cabinet would measure five and one-half feet by fourteen feet. This testimony was in accordance with plans submitted to the Zoning Board (and placed on file with the City of Margate) by Nextel.

Following the hearing, the Zoning Board unanimously approved Nextel’s application, specifically referring to the equipment Cabinet as eight feet by fourteen feet in its Resolution and stating that “[t]he proposed installation will be virtually invisible to any neighbors or passer-by of this site.” A Notice of Decision was issued by the Zoning Board indicating issuance of the Resolution and approval of the eight-foot by fourteen-foot equipment cabinet. The forty-five day period for appealing the Zoning Board’s Resolution passed without any party bringing an action seeking review, see N.J. Ct. R. 4:69-6, and Nextel was issued a building permit on February 8, 2000.

While construction was underway, Pe-rone, a former municipal court judge in Margate who occupied the top-floor condominium immediately under the equipment cabinet, and who owned other units, brought an action in New Jersey state court seeking preliminary injunctive relief precluding Nextel from going forward with the project. . He complained that: (1) Nextel’s work had already damaged the roofs protective membrane, resulting in water damage to one of his units, and that further damage was likely; (2) the “equipment shack,” which Nextel refused to relocate, would constitute an eyesore interfering with his use and enjoyment of his units and reducing their market value; (3) the noise from the telecommunications facility would shatter his serenity and peace, interfere with his use and enjoyment of his units, and reduce their market value; and (4) potential health hazards would exist as a result of the electromagnetic field created by the antennas. The state court denied the application for a preliminary injunction on May 8, 2000, and construction was completed May 30, 2000.

*191 On July 13, 2000, Nextel was issued a Notice of Violation and Order to Terminate by a construction official for the City of Margate. The Notice asserted that Nextel had failed “to install the roof top structure in accordance with prior approvals and the construction documents submitted.” Specifically, the equipment cabinet was said to be “approximately 3 ft 6 inches higher and 4 ft wider than approved.” The Notice also stated that no Certificate of Approval would be issued until the violations were corrected, and that a penalty of five hundred dollars per week would be imposed for every week after August 4, 2000, that the violation remained outstanding. Nextel states that it thereafter provided the construction official with a copy of the Resolution, with which the equipment cabinet was in compliance, but the Notice and Order were not rescinded. Nextel also filed revised “as built” plans showing the equipment cabinet as eight feet by fourteen feet, but the Zoning Board refused to approve them. Nextel then filed an appeal with the Atlantic County Board of Appeals. Around the same time, the City of Margate also served Nextel with two complaints for violating Land Use Ordinances by failing to build in accordance with Zoning Board approval. 1

The Zoning Board sought a rehearing to address the situation. Nextel believed the Zoning Board had no authority to hold a second hearing, and apparently contacted John C. Matthews, the Zoning Board’s attorney, to make that point. On September 19, 2000, Matthews replied with a letter to Nextel’s attorney, asserting that it was “clear that the zoning board has the ability to address this situation,” and that Nextel should reappear before the Zoning Board to “address the inconsistencies in [Nex-tel’s] application and the ultimate size of the cabinet that was installed.” Perone was also involved in this correspondence. On September 22, 2000, his attorney sent a letter to Matthews petitioning the Zoning Board to reconsider the Nextel application. In that letter, Perone’s attorney stated that he was aware that: (1) “the City of Margate Subcode Official issued to Nextel a Notice of Violation and Order to Terminate”; and (2) that Nextel’s attorney had written to Matthews arguing that it was unnecessary “for an applicant to return to the Board to be relieved of a condition of approval.” Perone’s attorney went on to state that “[s]hould Nextel fail to appear back before the Board when ordered to do so, the case law is clear that the Board has the authority to rescind the approval previously granted based upon the misrepresentation, whether intentional or inadvertent, made during the initial proceeding.”

On September 26, 2000, Perone’s attorney sent another letter to Matthews. That letter mentioned a September 22 letter sent by Nextel’s attorney challenging Pe-rone’s right to petition the Zoning Board for rehearing and reiterated Perone’s position on the matter. Finally, also on September 26, Matthews sent a second letter to Nextel’s attorney, informing her that the Zoning Board had reviewed his letter of September 19, agreed with the contents of that letter, and was expecting Nextel “to come back before the Board on October 19, 2000 at 7:30 P.M. in order to have the Board reconsider this matter.” The letter went on to state that “[t]here was clearly a mistake involving this application,” because both the plans submitted by Nextel and the testimony of Nextel’s witness at the hearing, referred to an equipment cabinet measuring five feet by four *192

Free access — add to your briefcase to read the full text and ask questions with AI

Nextel Communications of the Mid-Atlantic, Inc. v. City of Margate, 305 F.3d 188, 2002 WL 31111830 (3d Cir. 2002).

305 F.3d 188 (Nextel Communications of the Mid-Atlantic, Inc. v. City of Margate) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related