Newton Housing Authority v. Cumberland Construction Co.

358 N.E.2d 474, 5 Mass. App. Ct. 1, 1977 Mass. App. LEXIS 597
CourtMassachusetts Appeals Court
DecidedJanuary 3, 1977
StatusPublished
Cited by11 cases

This text of 358 N.E.2d 474 (Newton Housing Authority v. Cumberland Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newton Housing Authority v. Cumberland Construction Co., 358 N.E.2d 474, 5 Mass. App. Ct. 1, 1977 Mass. App. LEXIS 597 (Mass. Ct. App. 1977).

Opinion

Goodman, J.

This litigation involves a number of claims which have been tried together and sought damages resulting from alleged breaches of various contracts involved in the construction of a housing project in Newton — including the general contract awarded by the Authority to Cumberland for the construction of the project, a subcontract for the performance of the roofing and sheet-metal work in the project, and two contracts through which certain doors were supplied to Cumberland for use in the project. The case was referred to a master and later recommitted to him. Thereafter Cumberland filed a number of objections to the master’s report and moved to have the report recommitted again. The trial judge denied the motion to recommit and filed a “Memorandum and Order for Judgment” in which he sustained some and overruled the remainder of Cumberland’s objections, ordered that the report as modified be confirmed, and ordered the entry of judgment as to all the claims. Cumberland appealed from the judgment so entered.

1. Cumberland attacks that portion of the judgment entered as to the counterclaim brought against it by the Authority which alleged various defects in Cumberland’s performance of the general contract. We summarize the subsidiary findings of the master which give a background for Cumberland’s contentions.

Construction of the project began on August 4, 1969. *3 Cumberland’s subcontractor for the installation of roofing and sheetmetal was Richard E. Moore Co., Inc. (Moore). The subcontract provided that Moore was to line the gutters of the buildings with sheets of a metal alloy composed of titanium, copper, and zinc and that it should install these sheets in accordance with the manufacturer’s recommended practices. The manufacturer of the sheets of alloy, which Moore used for the job, recommended that the sheets be joined by “3/4 inch locked soldered seam[s]” and that provision be made for expansion and contraction by the installation of expansion joints. Moore failed to join the sheets by the recommended seams and installed no expansion joints. Moore’s performance of its subcontract was defective in a number of other respects as well.

The general contract between the Authority and Cumberland contained a “general guaranty” which provided that Cumberland “shall remedy any defects due to faulty materials or workmanship and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of final payment, or from the date of the Local Authority’s use or occupancy of the project as a whole, whichever is earlier.” The general guaranty also provided that the Authority “will give notice of observed defects with reasonable promptness.” The full text of the general guaranty is set out in the margin. 2

*4 On August 17,1970, the Authority, after its final inspection of the housing project, issued to Cumberland a memorandum of acceptance of the project, effective that day, for use and occupancy of all the buildings. Simultaneously the Authority compiled and gave to Cumberland a “punch list” of work still to be completed or corrected. On September 16, 1970, the Authority gave Cumberland another such list. Each list contained a request that Cumberland correct specified defects in Moore’s roofing work. Thus the first list contained a request that “metal edging and ends of gutters... be corrected,” and the second a request that “metal edging on roof... be nailed. Gutter work completed.” Cumberland apparently repaired the listed items. Neither list specifically mentioned Moore’s failure to use proper seams and install expansion joints in the gutter lining system.

In December, 1970, or January, 1971, the Authority complained to Moore that the roofs of the buildings leaked. Moore sent some employees to the project, and they attempted to repair those seams between the sheets of metal alloy which they found had separated. The repairs were only temporarily successful. On May 21, 1971, the Authority again gave Cumberland a punch list of work to be corrected containing requests that Cumberland repair various specified leaks in the roofs of the buildings* * 3 but not mentioning Moore’s failure to use the correct seams and install expansion joints. Again Cumberland apparently repaired the items.

In spite of the repairs made by both Cumberland and Moore the roofs of the buildings continued to leak, par *5 ticularly during succeeding winters. This leakage resulted from Moore’s failure to install the gutter lining system in accordance with the practice recommended by the manufacturer of the sheets of metal alloy and from certain other defects in Moore’s work. The leakage damaged the first floor apartments and the central common hallways of the buildings. The master, in his general findings, concluded that Cumberland had breached the general contract and awarded damages both for the cost of replacing the gutter lining system and the cost of repairing the damage done by the roof leakage. Cumberland’s attack on the master’s report is based on two different, although related, grounds.

Its first contention, in substance, is that the general guaranty (see fn. 2) supplanted the Authority’s common law right to recover from Cumberland contract damages for defective work (see Ficara v. Belleau, 331 Mass. 80, 81 [1954]; Restatement: Contracts, §346 [1932]) and barred recovery unless the Authority had, under the general guaranty, given Cumberland notice of and requested that it remedy Moore’s failure to install the gutter lining system and unless Cumberland had thereupon refused to remedy the defects in the system. The trial judge, in his “Memorandum and Order for Judgment” rejected this contention stating that a request by the Authority under the general guaranty that Cumberland remedy defects was not a condition precedent to a recovery by the Authority of damages arising from those defects in an action for breach of contract.

We agree with the trial judge. An English text writer, discussing construction contract clauses similar to the general guaranty, has stated: “In the absence of express provision the remedies under these clauses are in addition to and not in substitution for the common law rights, and even where the defects have appeared within the [guaranty] period the employer may sue for damages rather than call on the contractor to do the work____” Hudson, Building and Engineering Contracts, pp. 396-397 (1970). See Hancock v. Brazier, [1966] 2 All E.R. 901, 904 (C.A. *6 1966). The general contract between the Authority and Cumberland contains no express provision stating that the guaranty clause is to supplant the Authority’s common law right to bring an action for breach of contract against Cumberland. Indeed, the general guaranty begins with the broad provision: — “Neither... any provision in the Contract nor partial or entire use or occupancy of the premises by the Local Authority shall constitute an acceptance of work not done in accordance with the Contract or relieve the Contractor of...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Ahmed Shabazz.
Massachusetts Appeals Court, 2025
Doe v. Gonpo
Massachusetts Appeals Court, 2023
Aggregate Industries Northeast Region, Inc. v. Mass Paving, Inc.
20 Mass. L. Rptr. 477 (Massachusetts Superior Court, 2006)
Fraley v. Minger
829 N.E.2d 476 (Indiana Supreme Court, 2005)
Lake States Insurance v. Consumer Insurance Services of America
13 Mass. L. Rptr. 104 (Massachusetts Superior Court, 2001)
McNamara & Goodman v. Pink
696 A.2d 1328 (Connecticut Superior Court, 1997)
Phelps Steel, Inc. v. Von Deak
511 N.E.2d 42 (Massachusetts Appeals Court, 1987)
Albee Industries, Inc. v. Inspector of Buildings
407 N.E.2d 1307 (Massachusetts Appeals Court, 1980)
Nychis v. Fields
389 N.E.2d 1037 (Massachusetts Appeals Court, 1979)
Pearce, Mayer, & Greer, Inc. v. Attoyac Properties, Inc.
374 N.E.2d 349 (Massachusetts Appeals Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
358 N.E.2d 474, 5 Mass. App. Ct. 1, 1977 Mass. App. LEXIS 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newton-housing-authority-v-cumberland-construction-co-massappct-1977.