New York State Electric & Gas Corp. v. City of Plattsburg

168 Misc. 597, 6 N.Y.S.2d 419, 1938 N.Y. Misc. LEXIS 1861
CourtNew York Supreme Court
DecidedAugust 15, 1938
StatusPublished
Cited by4 cases

This text of 168 Misc. 597 (New York State Electric & Gas Corp. v. City of Plattsburg) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York State Electric & Gas Corp. v. City of Plattsburg, 168 Misc. 597, 6 N.Y.S.2d 419, 1938 N.Y. Misc. LEXIS 1861 (N.Y. Super. Ct. 1938).

Opinion

Lawrence, J.

This is a taxpayer’s action in equity to restrain the city of Plattsburg and its officials from proceeding with the construction of a municipal electric light and power plant under a grant and loan from the Federal government.

An injunction pendente lite was granted and, on appeal, was affirmed, with a statement by the appellate court that the issues should be determined without delay, as they were serious and involved the constitutionality of statutes. At the next Trial Term in Clinton county the presiding justice, because of his relationship to one of the parties, felt that he should not determine the issues, and by stipulation of the attorneys the case was heard by the undersigned.

At the opening of the trial defendants made a motion to dismiss the complaint on the ground that it did not state facts sufficient to constitute a cause of action. The sufficiency of the complaint was before the court on an application for temporary injunction. It was before the Appellate Division on appeal from the order granting the temporary injunction. (254 App. Div. 628.) The case was sent back for trial upon the complaint and the answer to be interposed. The motion was and is denied.

[599]*599Various other objections were and are made to the complaint. It is urged that there is a defect of parties defendant. It is stated that the action of the city in employing engineers to determine the cost of the project, and the payment to them by the city for services, make them necessary parties to the action because the complaint alleges that their actions were without authority and that under such circumstances an action would he against them to recover the sums paid to them. It seems to me that such allegation should be deemed to state steps in the prosecution of a plan, which, in its entirety, is claimed to be a violation of the constitutional debt limit. Under those circumstances I cannot see how the engineers are necessary parties here.

Another objection urged by the defendants is that the Federal Administrator of Public Works should be brought into the action .because, under the National Industrial Recovery Act, he had authority to accept and act upon an application for Federal aid and that, ¡having acted on the program for proposed construction, his rights ¡were prejudiced by the action to restrain its continuance, and that he ¡should be heard. Primarily this action is to restrain the defend-I ants from entering upon a plan of construction the expense of which ¡will exceed the constitutional debt limit, and I fail to see how the presence in this action of the Federal Administrator is necessary or important. Moreover, the statute provides who are necessary parties.

j Another objection by the defendants is that section 51 of the General Municipal Law does not apply here as its operation is suspended by reason of the enactment of the so-called Mandelbaum ¡Act (Laws of 1933, chap. 782). That act states, in substance, that where it is inconsistent with other acts it shall control. It does not seem to me that it was thereby intended to deprive an interested party from estabhshing a violation of the Constitution. ¡Such an intention and the granting of such power to municipal ¡authorities would make it possible for cities to disregard the prohibition against incurring obligations beyond the constitutional i limit. It would also remove the limitation placed on cities by section 20 of the General City Law. Defendants claim that no right to restrain cities existed under the common law and that, as the Mandelbaum Act suspends section 51 of the General Municipal Law, no present right exists to restrain cities from incurring unlimited indebtedness. With this I cannot agree.

Another objection by the defendants is that the plaintiff seeks to have the court vitiate and set aside the discretionary acts of city officials in deciding the amount which may be expended for the proposed system and, in effect, asks the court to substitute its [600]*600judgment for the judgment of the city officials. Courts do not concern themselves with acts which are administrative and discretionary. Whether a municipality shall engage in vast expenditures and establish various municipal activities which may destroy existing enterprises and deprive itself of tax revenue may be for them to decide. The question of the wisdom of a proposed construction is not for the court, but whether, under the law as limited by the Constitution, they have the power to carry out a proposed plan does become the concern of the court.

The question may not be raised that the city, under existing law, has no power to build an electric fighting and power plant and system, and if its acts are kept within constitutional limitations, no one can question its decisions. Here it is claimed that the constitutional limit has been exceeded and, taking the evidence as most favorable to the defendants, they have exceeded the constitutional debt limit by upwards of $14,000, and this is substantially conceded. The present assessed valuation of the city is $5,419,572. The existing debt limitation of ten per cent is, therefore, $541,957.20. The outstanding bonds, exclusive of the sewer bonds, are $299,000. Provision is made in the present budget for retiring $29,000. This leaves outstanding bonds of $270,000. Under the minimum estimate of cost of the construction of the proposed system, it will be necessary to issue additional bonds in the sum of $286,000. Subtract the margin of $271,957.20 and we have $14,042.80 as the amount over and above the limit allowed by the Constitution, taking the testimony in the most favorable construction possible for the defendants. The answer of the defendants regarding this situation is that it is not expected that the whole amount of bonds authorized will be issued, but that they will only be issued as funds are needed for carrying forward the plan, and that in the meantime further bonds will be paid so that the bonded limit will at no time be exceeded. It seems to me that we are dealing with present conditions and must determine the question of legality upon the present conditions. Under the circumstances here the least defendants would spend on the proposed construction is more than allowed by the Constitution.

Plaintiff claims, however, that a larger bond issue was authorized ($360,000 instead of $286,000) and that the cost of construction would far exceed the minimum estimate. Plaintiff’s contention is that the cost of construction would be $687,540. Plaintiff submits evidence to that effect, which was received over objection. This cost would necessitate the issuance of bonds in excess of the debt limit by about $145,000, not taking into account the minimum amount of the sewer revenue bonds of $187,000, which plaintiff [601]*601claims should also be considered in determining the constitutional debt limit. Under those circumstances, in my judgment, that would spell out a waste of funds, and it almost becomes a matter of common knowledge and experience that the cost of construction would far exceed the ■minimum estimate. It seems to me that it is conclusively established that, until arrangements are made so that defendants can proceed with construction within the debt limit by raising assessments or lowering the cost of construction, they should be restrained from entering upon a plan or scheme which would amount to a violation of fundamental law. Their plan is definite and they contemplate going forward with it according to plans adopted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Telephone Co. v. City of New York
111 Misc. 2d 727 (New York Supreme Court, 1981)
Wein v. City of New York
80 Misc. 2d 894 (New York Supreme Court, 1975)
Bloom v. Mayor
35 A.D.2d 92 (Appellate Division of the Supreme Court of New York, 1970)
New York State Electric & Gas Corp. v. City of Plattsburgh
257 A.D. 1022 (Appellate Division of the Supreme Court of New York, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
168 Misc. 597, 6 N.Y.S.2d 419, 1938 N.Y. Misc. LEXIS 1861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-state-electric-gas-corp-v-city-of-plattsburg-nysupct-1938.