New York Skyline, Inc. v. Empire State Building Co.

542 B.R. 321, 2015 U.S. Dist. LEXIS 142538, 2015 WL 6161243
CourtDistrict Court, S.D. New York
DecidedOctober 20, 2015
DocketNo. 13-cv-7686 (SAS)
StatusPublished
Cited by1 cases

This text of 542 B.R. 321 (New York Skyline, Inc. v. Empire State Building Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York Skyline, Inc. v. Empire State Building Co., 542 B.R. 321, 2015 U.S. Dist. LEXIS 142538, 2015 WL 6161243 (S.D.N.Y. 2015).

Opinion

OPINION AND ORDER

SHIRA A. SCHEINDLIN, District Judge.

I. INTRODUCTION

This adversary proceeding between former debtor New York Skyline Inc. (“Skyline”), the operator of a helicopter simulator on the second floor of the Empire State Building (the “Building”), and its landlord and related entities (together, “ESB”) originally came before me as an appeal by Skyline from a Judgment entered by Bankruptcy Judge Stewart M. Bernstein. On appeal, Skyline argued that the Bankruptcy Court lacked authority to enter the Judgment, and in any event had committed reversible errors on the merits. Skyline argued that the Bankruptcy Court erred by awarding injunctive relief to ESB on its counterclaim that Skyline had breached a provision of a 2005 lease amendment (the “May 2005 Agreement”) which prohibited Skyline from paying commissions or sales incentives to Skyline employees or representatives working in “any area of or near the Building” (the “Protocol Provision”). And Skyline argued that the Bankruptcy Court erred by not holding that Article 42 of the lease (the “Electricity Provision”), requires ESB to bill Skyline based on a survey that estimates Skyline’s actual consumption, not its estimated overall capacity to consume electricity.1

Without reaching the merits, I vacated the Judgement after determining that the Bankruptcy Court lacked authority to en[324]*324ter a final judgment over non-core matters to which the parties had not consented pursuant to section 157 of title 28 of the United States Code.2 In addition, I remanded for consideration of whether the Bankruptcy Court had authority to issue proposed findings of fact and conclusions of law under the circumstances of this proceeding. Over a year later, the Bankruptcy Court issued a decision on remand.

Pursuant to this District’s Amended Standing Order of Reference, “[t]he district court may treat any order of the bankruptcy court as proposed findings of fact and conclusions of law in the event the district court concludes that the bankruptcy judge could not have entered a final order or judgment consistent with Article III of the United States Constitution.”3 Although it is troubling that an Article I judge would continue to preside over purely state-law contract claims long after their actual relevance to a bankruptcy case has terminated,4 I am unaware of any case, controlling or otherwise, that has held that a bankruptcy court lacks authority under section 157 to issue proposed findings of fact and conclusions of law when jurisdiction is otherwise proper. Accordingly, I will treat the Bankruptcy Court’s Electricity Decision, Protocol Decision, and Stay Decision — as defined below — as proposed findings of fact and conclusions of law, and will treat the parties’ appellate briefs as the objection, response, and reply, respectively, to the proposed findings of fact and conclusions of law.

For the following reasons, I accept the Bankruptcy Court’s proposed findings of fact and conclusions of law with respect to the Electricity Provision and reject the Bankruptcy Court’s interpretation of “near the Building,” a term found in the Protocol Provision.

II. BACKGROUND

A. The Electricity Provision

Skyline’s Twelfth Claim in its Third Amended Complaint alleged that ESB overcharged it for electricity in breach of the lease.5 Skyline sought declaratory and [325]*325monetary relief. A trial was held before the Bankruptcy Judge on September 24 and October 24, 2012. Following trial, ESB moved for judgment on partial findings pursuant to Federal Rule of Civil Procedure 52(c).

On February 22, 2013, the Bankruptcy Court issued the Electricity Decision, which granted ESB’s motion and dismissed Skyline’s claim. As an initial matter, the Bankruptcy Court determined that Skyline failed to comply with the lease’s contractual dispute resolution procedure and thus was precluded from disputing the methodology used by ESB in estimating Skyline’s consumption of energy.6 Notably, Skyline has not objected to this determination.

The Bankruptcy Court found that Skyline did not prove that ESB’s electrical consultant “failed to compute the connected load in accordance with the Lease or that ESB failed to correctly compute the electricity charges....”7 The Bankruptcy Court determined that the Electricity Provision — and in particular the phrase “connected electrical load” — was not ambiguous and did not support Skyline’s contention that the Electricity Rent Inclusion Factor was to be calculated based on Skyline’s actual consumption of electricity.8

B. The Protocol Provision

ESB asserted a counterclaim based on Skyline’s alleged violation of the Protocol Provision. That provision states that “[a]ll [Skyline] employees and representatives who work in the NYSR Premises or in any area of or near the Building (including without limitation the [Second Floor Observatory] Visitor Center) in the course of performing NYSR-related duties [m]ust be salaried employees and not working on commission or other sales incentive.” A trial on the counterclaim was held before the Bankruptcy Judge on May 6 and 7, 2013.9

Both sides agreed that the Protocol Provision was intended to stem aggressive sales tactics by Skyline agents selling tickets to Skyline’s helicopter simulator attraction at or near the Building. They disagreed over whether Skyline can consider an employee’s sales performance in fixing his salary and whether “any area of or near the Building” includes the sidewalks directly across the street from the Building and west of the Building footprint but east of Sixth Avenue on 33rd and 34th Streets.

The Bankruptcy Court issued a decision (the “Protocol Decision”) in ESB’s favor and granted an injunction barring Skyline from paying commissions to Skyline representatives working in what was termed the “ESB Zone.”10 In denying Skyline’s request for a stay of the injunction pending appeal (the “Stay Decision”), the Bankruptcy Court provided additional analysis of its interpretation of the Protocol Provision.11

III. LEGAL STANDARD

The district court conducts a de novo review of those findings of fact and conclusions of law to which written objections [326]*326have been made.12 “The district judge may accept, reject, or modify the proposed findings of fact or conclusions of law, receive further evidence, or recommit the matter to the bankruptcy judge with instructions.” 13

IV. APPLICABLE LAW

Under New York law, “[t]he court’s function in interpreting a contract is to apply the meaning intended by the parties, as derived from the language of the contract in question.”14 “[T]he best evidence of what parties to a written agreement intend is what they say in their writing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barbara Wortley v. Michael R. Bakst
844 F.3d 1313 (Eleventh Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
542 B.R. 321, 2015 U.S. Dist. LEXIS 142538, 2015 WL 6161243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-skyline-inc-v-empire-state-building-co-nysd-2015.