New York Indemnity Co. v. Hurst

66 S.W.2d 8, 252 Ky. 59, 94 A.L.R. 864, 1933 Ky. LEXIS 989
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedDecember 15, 1933
StatusPublished
Cited by8 cases

This text of 66 S.W.2d 8 (New York Indemnity Co. v. Hurst) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York Indemnity Co. v. Hurst, 66 S.W.2d 8, 252 Ky. 59, 94 A.L.R. 864, 1933 Ky. LEXIS 989 (Ky. 1933).

Opinion

OPINION OF THE COURT BY

JUDGE PERRY

Affirming.

This appeal had its origin in litigation growing ont of the construction of the Hurst Hotel and hospital building, iii Hazard, Ky. It appears that when this property was acquired by Dr. Hurst it consisted of two lots upon one of which stood a three-story hotel building, while upon his adjoining lot there remained standing only the walls of a structure previously burned. Plans and specifications for the improvement of the property were prepared by A. L. Ware, architect, for the erection of a five-story building on the vacant lot and the remodeling of the adjoining building by extending a fourth story thereto. The new building was to be used as an office building and hospital in connection with the added fourth floor of the old building as a part of the hospital. After these plans had been worked out by the architect, Dr. Hurst entered into a contract with K. W. Owens, doing business under the trade name of the Hazard Plumbing & Supply Company, on July 13, 1929, to install a heating plant and plumbing fixtures in the proposed new building, and also on August 6, 1929, entered into a contract with E. C. & T. S. Todd, a partnership of Richmond, Ky., doing business as Todd Bros. Construction Company, for the erection of the' proposed new Taylor Hurst building. It further appears, however, that at the time of Dr. Hurst’s *62 contract with, the Hazard Plumbing & Supply Company (operated by R. W. Owens), that the latter executed an indemnifying bond to him in the penal sum of $8,753.42-with the appellant, the New York Indemnity Company, as his surety, for the faithful performance of his contract; also, that Todd Bros., upon entering into their written contract with Dr. Hurst for the hospital building’s construction, did, as thereby required, execute an indemnifying bond to him with the same, New York Indemnity Company, as its surety, in the penal sum of $20,000 for the faithful performance of its building contract. The work was then begun and continued until practically completed along about the middle of February, 1930, when possession thereof was taken by Dr. Hurst, and when also it developed that certain material-men’s accounts were then outstanding and owing by both contractors, Todd Bros, and R. W. Owens, for materials sold to and used by them in the construction and plumbing work of this building. These material-men’s liens were asserted and perfected by filing proper statements of their claims under the Mechanic and Material Men’s Lien Law, section 2463, Kentucky Statutes. Payment of these lien claims having been by these creditors demanded and refused, one of the lien creditors, Ben F. Hurst, doing business as B. F. Hurst & Co., filed his petition in equity against Dr. Hurst and the contractor, R. W. Owens, on May 26, 1930, to whom he had sold certain plumbing material, seeking judgment upon his lien claim against Owens and also its enforcement against the property of Dr. Hurst upon which used. Further, by amended petition, certain other named lien holding creditors were made defendants together with the appellant New York Indemnity Company, in which judgment was sought against it, under the bond it had signed for the Hazard Plumbing & Supply Company, operated by R. W. Owens. All the lien holding creditors and contractors, both Todd Bros, and Owens, having by the pleadings been made defendants, filed appropriate responsive pleadings, and enforcement of personal judgments against the contractors, Todd Bros, or Owens, to whom they had sold the materials going into the building’s construction and also against the appellant the New York Indemnity Company, as surety upon their indemnifying bonds, and for enforcement of their materialmen’s lien claims against the property of the appellee Dr. Hurst. On September 20, *63 1930, the appellee Dr. Hurst filed answer to plaintiff’s petition, and cross-petitions of defendant lienholders, and also a cross-petition against his contractors, R. W. Owens, doing’ business as the Hazard Plumbing & Supply Company and against E. C. and T. S. Todd, doing business as Todd Bros. Construction Company, and the New York Indemnity Company, surety, upon their bonds executed him, wherein he prayed that the action be referred to a special commissioner for hearing proof and ascertaining the correctness and amount of the several lien claims thus sued upon by those who had supplied materials going into the building, and alleging the appellants’ breach of contract and bond through their failure to, pay these lien claims. The lien creditor, George L. Mesker & Co. (appellee), asserted, no materialman’s lien but came into the action by filing: an intervening petition, asking judgment against Dr. Hurst, Todd Bros., and the New York Indemnity Company under the bond, for materials sold and furnished by it to Todd Bros. The appellants New York Indemnity Company and Todd Bros, alike filed answer wherein were set out in full the building contract, made between Todd Bros, and Dr. Hurst on August 6, 1929, and. also the bond, executed by them for the faithful performance of the contracts with Dr. Hurst upon which, the New York Indemnity Company became surety; and further it pleaded as to the Todd Bros.’ bond that it: became the firm’s indemnitor only, for the performance of the contract, and that, as such, when the bond so-given was construed with the parties’ contract, expressly made a part thereof, that it was not bound under the. bond for any labor or materials that went into the construction of the building described in the contract, inasmuch as it thereby secured the performance only of a, percentage contract, based upon the estimated cost of the building’s construction and not for labor or material purchased therefor, and that, if Todd Bros, purchased any materials going into said building, it did so only as agent for Dr. Hurst and not as his contractor or did so merely for accommodation; also it. pleaded that Todd Bros, completed the building in February, 1930, when saíne was accepted for Dr. Hurst by A. L. Ware, his architect, and possession taken thereof by him. Amended answers were filed by Dr. Hurst, alleging the making of the contract and the execution *64 of the bond by Todd Bros, and the New York Indemnity Company, as surety, for the faithful performance of the contract, upon the conditions named in the bond that Todd Bros, should satisfy all claims and demands incurred in performing same; and to indemnify Dr. Hurst, its indemnitee, from all cost and damage he might suffer by reason of its failure so to do, and that it should pay all persons having contracts directly with the principal for labor and materials. Further he pleaded that from the date of the execution* of ’the bond and during the entire progress of the work on the building, that the contract was so construed and mutually understood by the parties, as providing and imposing on Todd Bros, the obligation to purchase materials, according to schedule prepared by the defendant Dr. Hurst therefor and to pay all persons having contracts directly with the said Todd Bros, for labor and materials. Further pleadings were filed, forming the issues, both as to what we will here call the Todd Bros.’ branch of the case and also that involving the Hazard Plumbing & Supply Company’s branch of it, hereinafter considered. The special commissioner to whom the case was referred and proof taken, filed report of his findings of fact to the effect that the parties’ contract was one by which Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferguson Contracting Co. v. Charles E. Story Construction Co.
417 S.W.2d 228 (Court of Appeals of Kentucky (pre-1976), 1967)
La Salle Iron Works, Inc. v. Largen
410 S.W.2d 87 (Supreme Court of Missouri, 1966)
Gibbs v. Trinity Universal Insurance Company
1958 OK 147 (Supreme Court of Oklahoma, 1958)
Standard Accident Ins. Co. v. Knox, Recr.
184 S.W.2d 612 (Texas Supreme Court, 1944)
Associated Indemnity Corp. v. Del Guzzo
81 P.2d 516 (Washington Supreme Court, 1938)
Dorman, Banking Com'r v. Carnes
96 S.W.2d 869 (Court of Appeals of Kentucky (pre-1976), 1936)

Cite This Page — Counsel Stack

Bluebook (online)
66 S.W.2d 8, 252 Ky. 59, 94 A.L.R. 864, 1933 Ky. LEXIS 989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-indemnity-co-v-hurst-kyctapphigh-1933.