National Surety Co. v. Daviess County Planing Mill Co.

281 S.W. 791, 213 Ky. 670, 1926 Ky. LEXIS 592
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedMarch 23, 1926
StatusPublished
Cited by9 cases

This text of 281 S.W. 791 (National Surety Co. v. Daviess County Planing Mill Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Daviess County Planing Mill Co., 281 S.W. 791, 213 Ky. 670, 1926 Ky. LEXIS 592 (Ky. 1926).

Opinion

Opinion of the Court by

Commissioner Hobson

Affirming.

In September, 1922, the board of education of the city of Owensboro let to I. D. Smith & Son the contract for the construction of a large school building. Smith & Son contracted with the Daviess County Planing Mill Company for the mill work to be used in the building at a total price of $15,850.00. The contractors executed with the National Surety Company, as their surety, a bond to the board of education in the sum of $105,500.00, by which they undertook that the contractors would faithfully perform the contract with the board of education. The bond contained this clause:

“Whereas, the principal has by means of a written agreement, dated August 25, entered into a contract with the owner for general work, Owensboro high school, a copy of which agreement is by reference made a part hereof;
“Now, therefore, the condition of this obligation is such that if the principal shall faithfully perform the contract on his part and satisfy all claims and demands, incurred for the same, and shall fully indemnify and save harmless the owner from all cost and damage, which he may suffer by reason of failure so to do, and shall fully reimburse and repay the owner all outlay and expense which the owner may *672 incur in making good such default, and shall pay all persons who have contracts- directly with the principal for labor or materials, then this obligation shall be null and void; otherwise it shall remain in full force and effect.”

Smith & Sons did not pay the Daviess County Planing Mill Company and it brought this suit against the surety company on the bond. The circuit court gave judgment in favor of the plaintiff. The defendant appeals.

The chief ground for reversal is that the bond is an obligation to the board of education and that no suit can be maintained on it by the planing mill company. But it will be observed that the condition of the bond is that if the principal shall pay all persons who have contracts directly with the principal for labor or materials, then this obligation shall be null and void, otherwise it -shall remain in full force and effect. It will thus be seen that the bond remains-in full force and effect unless the principal shall pay all persons who have contracts directly with the principal for labor or materials. The planing mill -company had a -contract directly with the principal for material, and was not paid. In 13 C. J. 707-709, the rule is thus stated:

‘ ‘ The doctrine that a third person may maintain an action on a -contract made for his benefit has been applied to an agreement by which one of the parties promises, on the receipt of property or other consideration, to pay a debt due from the other to a third person or . . . to a bond executed by a contractor for the erection of a building or for public work, to the owner or municipality, conditioned to pay for labor and materials.”

A number of cases are -cited sustaining the text. In Federal Union Surety Co. v. Commonwealth of Kentucky, 139 Ky. 92, the court followed this rule. In so holding it only applied the rule announced in its former decisions, under which a property owner was held entitled to sue on a -contract made between the water company and the city where he had suffered a loss by a breach of the contract, and a bastard child was allowed to recover on a contract made by the father with the mother by which the father agreed to provide for the child and other like cases.' Kenton Water Co. v. Glenn, 141 Ky. *673 531; Morrison v. Peyton, 31 R. 994; Albin Co. v. Commonwealth of Ky., 128 Ky. 301; Tobin v. Frankfort Water Co., 158 Ky. 352; Louisville Gas Co. v. City of Louisville, 191 Ky. 796; and eases cited. Owens v. Georgia Life Insurance Co., 165 Ky. 507 rests upon tbe ground that tbe liability sued for was not witbin tbe terms of tbe bond.

It is also complained that tbe court erred in entering a judgment on tbe debt with interest from February 7, 1924, and not from tbe filing of tbe petition on May 24, 1924. But the subcontractor was entitled to bis money from the contractor on February 7th. The bond bound tbe surety for tbe payment of tbe money. In such a case if interest is not allowed tbe creditor will lose a part of bis debt. It is a suit upon a written contract to pay and interest may be allowed from tbe time tbe money was due and not paid. Henderson Cotton Mfg. Co. v. Lowell Machine Works, 86 Ky. 668; City of Louisville v. Henderson, 11 R. 796; Citizens Trust Co. v. Peebles, 174 Ky. 439; Whitehead v. Brothers Lodge, 34 R. 1633.

Tbe allegations of tbe plaintiff’s petition setting out its debt are in these words:

“Plaintiff states that on or about August 18, 1923, tbe representative of tbe defendant, National Surety Company, bad taken charge of tbe work of completing said high school building and ordered plaintiff to deliver tbe necessary material for the completion of said building. Plaintiff states that it relied upon tbe statements and representations of tbe defendant, National Surety Company, and that it did deliver said material and that on and after August 20,1923, it delivered to tbe defendants, I. D. Smith & Son and National Surety Company, materials and merchandise, as shown on tbe itemized statement attached hereto, of tbe aggregate value of $5,159.20, for which tbe defendants, I. D. Smith & Son and National Surety Company, promised to pay.
“Plaintiff states that in addition to tbe contract price for mill work, that there were numerous extras included in tbe material ordered by said defendants, I. D. Smith & Son and National Surety Company, for tbe completion of said building and said extras are set out in tbe itemized statement attached hereto, and it states that on February 7, 1924, tbe said de *674 fendants, I. D. Smith & Son and National Surety Company, were indebted to plaintiff in the sum of $3,242.51, that being the balance due on their contract price and extras, and that no part of said sum has ever been paid and plaintiff is entitled to recover interest thereon, from February 7,1924, until paid.”

It will be observed that it is averred that on and after August 20, 1923, the plaintiff delivered to the defendants, I. D. Smith & 'Son and National Surety Company, materials and merchandise, as shown on the itemized statement attached to the petition, of the aggregate value of $5,159.20, for which the defendants promised to pay. But it is not averred how much of this sum has been paid or how much is unpaid. It will also be observed that it is averred that in addition to the contract price for the mill work, there were numerous extras included in the materials ordered by the defendants for the completion of the building and it is averred that on February 17, 1924, the defendants were indebted to the plaintiffs in the sum of $3,242.51, that being the balance due on their contract price and extras, and no part of this sum has been paid. But there is no averment how much the extras amounted to or that the"priees charged therefor were reasonable or that the extras were furnished under any agreement as to price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ill-Mo Contractors, Inc. v. Aalcan Demolition & Contracting Co.
431 S.W.2d 165 (Supreme Court of Missouri, 1968)
Byington v. Baughman
137 S.W.2d 1101 (Court of Appeals of Kentucky (pre-1976), 1940)
Century Indemnity Co. v. Shunk Manufacturing Co.
68 S.W.2d 772 (Court of Appeals of Kentucky (pre-1976), 1934)
New York Indemnity Co. v. Hurst
66 S.W.2d 8 (Court of Appeals of Kentucky (pre-1976), 1933)
J. T. Jackson Lumber Co. v. Union Transfer & Storage Co.
55 S.W.2d 670 (Court of Appeals of Kentucky (pre-1976), 1932)
Aetna Casualty & Surety Co. v. United States Gypsum Co.
39 S.W.2d 234 (Court of Appeals of Kentucky (pre-1976), 1931)
Standard Oil Co. of N.J. v. National Surety Co.
29 S.W.2d 29 (Court of Appeals of Kentucky (pre-1976), 1930)
Chesapeake & Ohio Railway Co. v. Wadsworth Electric Manufacturing Co.
28 S.W.2d 650 (Court of Appeals of Kentucky (pre-1976), 1930)
Mid-Continent Petroleum Corp. v. Southern Surety Co.
9 S.W.2d 229 (Court of Appeals of Kentucky (pre-1976), 1928)