J. T. Jackson Lumber Co. v. Union Transfer & Storage Co.

55 S.W.2d 670, 246 Ky. 653, 1932 Ky. LEXIS 819
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 7, 1932
StatusPublished
Cited by9 cases

This text of 55 S.W.2d 670 (J. T. Jackson Lumber Co. v. Union Transfer & Storage Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. T. Jackson Lumber Co. v. Union Transfer & Storage Co., 55 S.W.2d 670, 246 Ky. 653, 1932 Ky. LEXIS 819 (Ky. 1932).

Opinion

Opinion op the Court by

Stanley, Commissioner

—Affirming.

The appellant, J. T. Jackson Lumber Company, a partnership, had a contract with the board of education of Lexington to construct the Henry Clay High School building. Under subcontract the Huntington Iron .Works Company undertook the steel and iron work, and the Union Transfer & Storage Company transported material under contract -with the iron works company. This suit wgs instituted by the lumber company against the school board to recover $1,745.44, balance due under its contract. The board. admitted that it owed that sum, but pleaded that certain claims had been asserted against it- on account of unpaid material and labor charges and asked that those claimants be made parties to the suit. Thereupon the appellee Union Transfer & Storage Company and others came into the case. The appellee claimed the benefit , of the commitments of the appellants to the school board, particularly the obligation contained in this part of the contract:

“Unless otherwise stipulated, the contractor shall provide and pay for all materials, labor, water,, tools, equipment, light and power necessary for the execution of the work.”

Another provision required.the contractor to indemnify and save harmless the board of education from all suits- and actions against it and should guarantee the. prompt, payment of all persons furnishing material or labor to-the contractor in the prosecution of the work. It was. further provided that the final payment of the retained percentage would not be made until the contractor-should deliver to the board a complete release of all liens arising out of the contract, or receipts in full in lieu thereof, and, if required, submit an affidavit that the releases and receipts included all the labor and material for which a lien might be filed. It was claimed by the appellee that the money in the hands of the school board constituted a trust fund for the satisfaction of its claim and other similar ones.

The court construed the contract favorable to appellee’s contentions, and rendered judgment upon the pleadings in its favor against the appellants for $801.56, the amount of its claim, and adjudged that it had a lien *655 upon the money due by the school board, which had been paid into the court pending the litigation. Appellants claim the judgment 'to be erroneous since the appellee was not a party to the contract between the school board and themselves, and that the contract was of a kind that should not be construed as being for its benefit.

That a contract between two parties may inure to the benefit of another, who may maintain an action on it, is an established doctrine in this and most jurisdictions in this country. The right is dependent upon whether the third person is a party to the consideration or the contract was entered into for his benefit or he has some legal or equitable interest in its performance. 13 C. J. 705-709; Matheny v. Chester, 141 Ky. 790, 133 S. W. 754; Morrison v. Payton, 104 S. W. 685, 31 Ky. Law Rep. 992; National Surety Co. v. Daviess County Planing Mill Co., 213 Ky. 670, 281 S. W. 791; Mid-Continent Petroleum Corporation v. Southern Surety Co., 225 Ky. 501, 9 S. W. (2d) 229; Standard Oil Co. v. National Surety Co., 234 Ky. 764, 29 S. W. (2d) 29; Chesapeake & O. Ry. Co. v. Wadworth Electric Mfg. Co., 234 Ky. 645, 29 S. W. (2d) 650.

This court has had recently several cases involving the rights of materialmen under a bond executed by ■a building contractor to the owner whereby the surety agreed to save the owner harmless from loss by reason of the nonpayment of such claims. As pointed out in Standard Oil Co. v. National Surety Co., supra, we have two distinct lines of decisions in cases of this character. As sho„wn, the dissimilarity arises from the differences in the terms of the particular contracts. It is only a question into which classification the contract before us is to be placed.

In some of the recent eases the obligation sought to be fixed upon the contractor to satisfy materialmen was in the indemnifying bond given the owner. The bond usually is to be regarded as a part of the general ■contract, and, when the two documents are to be read together, if either contains a provision committing the ■contractor to the payment of the material or compensation of the laborers, it is construed to have been made for their benefit, and they are given a cause of action thereunder. Here the bond guarantees to the owner that the contractor “shall pay all persons who have *656 contracts directly with, the principal (appellant) for labor or materials.” But the contract itself contains-a provision that the appellants shall pay for all material and labor. We cannot follow appellant’s argument that this case is to be distinguished from others, because it is not rested on the bond and the subcontractor was between' them and the claimant. Cf. National Surety Co. v. Daviess County Planing Mill Co., supra. It is only a question whether under either or' both documents the contractor is liable to those furnishing material. Where liability is measured by_ the-bond, the surety is held only because he is a joint, obligor. His liability is once removed from that of his-principal.

One who hauls for the contractor material which enters into the construction of a building comes within the purview of the mechanic’s and materialmen’s lien law (section 2463, Kentucky Statutes), and is as much entitled to the benefits of that law as is one who furnishes the material or labors on the building. Fowler & Guy v. Pompelly, 76 S. W. 173, 25 Ky. Law Rep. 615. By a parity of reasoning, if the contract between the' owner and the contractor covers claims of materialmen or the wages of workmen actually engaged in the- construction and it was made for their benefit, it must be-construed as including the appellee who hauled the-material to the building.

In Mid-Continent Petroleum Corporation v. Southern Surety Co., supra, the surety on the contractor’s, bond had to assume its contract and complete the construction of a sewer for the city of Louisville. The' claim asserted was for gasoline furnished to the contractor and used in the operation of machinery. The-contract between the commissioners of sewerage and the contractor provided that the latter should do all work and furnish all material necessary or proper to complete the job and that he would “indemnify and save harmless the city and commission from all claims-relating to labor and materials furnished for the work.”' Btit the terms of the bond went further than the contract and provided that the contractor “shall also pay for all labor performed and furnished and for all material used in the carrying out of said contract.” The-provision in the contract between the Lexington board of education and its general contractor, as is quoted above, was similar to the provisions of this bond, in that. *657 the contractor obligated himself to pay for all materials, labor, etc., necessary for the execution of the work. The provisions in the sewer construction contract and bond were regarded as a protection against loss to the city, and the bond provision was held to be for the benefit of the laborers and materialmen, and the bonding company liable to them upon default of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles E. Cannell Co. v. D. & D. Millwork Co.
156 S.W.2d 170 (Court of Appeals of Kentucky (pre-1976), 1941)
Daves' Administrator v. Daves
110 S.W.2d 1073 (Court of Appeals of Kentucky (pre-1976), 1937)
Massachusetts Bonding & Insurance v. United States Radiator Corp.
97 S.W.2d 586 (Court of Appeals of Kentucky (pre-1976), 1936)
Lincoln Nat. Life Ins. Co. v. Means
95 S.W.2d 264 (Court of Appeals of Kentucky (pre-1976), 1936)
Royal Indemnity Co. v. International Time Recording Co.
75 S.W.2d 527 (Court of Appeals of Kentucky (pre-1976), 1934)
Consolidated Realty Co. v. Richmond Hotel & Building Co.
69 S.W.2d 985 (Court of Appeals of Kentucky (pre-1976), 1934)
Century Indemnity Co. v. Shunk Manufacturing Co.
68 S.W.2d 772 (Court of Appeals of Kentucky (pre-1976), 1934)
Blair & Franse Construction Co. v. Allen
65 S.W.2d 78 (Court of Appeals of Kentucky (pre-1976), 1933)
Mason Construction Co. v. Kosmos Portland Cement Co.
59 S.W.2d 1016 (Court of Appeals of Kentucky (pre-1976), 1933)

Cite This Page — Counsel Stack

Bluebook (online)
55 S.W.2d 670, 246 Ky. 653, 1932 Ky. LEXIS 819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-t-jackson-lumber-co-v-union-transfer-storage-co-kyctapphigh-1932.