PER CURIAM:
The principal issue presented by these consolidated appeals is whether the district court erred in granting appellee’s motion for summary judgment by applying the wrong tolling doctrine to appellant New Port Largo, Inc.’s (NPL) temporary regulatory takings claims, thereby holding [1490]*1490the claims barred by the applicable statute of limitations. NPL sold the subject property two years after the enactment of the allegedly infringing regulation. The district court, observing that the regulation could cause NPL no injury thereafter, held that the applicable statute of limitations ran from the date NPL sold the property. NPL contends that the statute of limitations was tolled until the state court, in passing on the validity of the regulation, declared the regulation invalid. Based on Corn v. City of Lauderdale Lakes, 904 F.2d 585 (11th Cir.1990) (Com III),1 we conclude that the district court erred. Accordingly, we vacate the district court’s judgment and remand the case for further proceedings.2
I.
A.
In August 1968, the State of Florida sold a parcel of submerged land located on Key Largo’s Atlantic coast to a private trust.3 In December 1972, after the private trust filled in and prepared the land for residential construction, the Monroe County Planning and Zoning Department (the Zoning Department) zoned the property for residential duplex use (RU-2).
In September 1979, NPL purchased the property from the private trust. In November 1979, appellee Monroe County (the County) filed an application with the Zoning Department to rezone the property from RU-2 to private airport use (PA). On January 24, 1980, the Zoning Department held a hearing on the proposed rezoning and subsequently approved the County’s application. NPL appealed the Zoning Department’s decision to the Monroe County Board of Commissioners (the Commission). On September 11, 1980, the Commission affirmed the Zoning Department’s decision.
On October 10, 1980, NPL filed a petition for a writ of certiorari in state circuit court alleging that the rezoning violated Florida law. NPL claimed that the County had not complied with the procedural requirements of its Major Development Project Ordinance, an ordinance that applies to rezon-ings which, as here, concern parcels of land greater than five acres. On September 9, 1982, during the pendency of its certiorari petition, NPL sold the property in question, conveying one-half undivided interests in fee simple both to TFW, Inc., a Florida corporation, and to a land trust administered by the First National Bank of South Miami. Neither of these purchasers intervened in the certiorari proceeding brought by NPL. In August 1985, NPL amended [1491]*1491its petition to include a claim that the County had deprived NPL of its property “without offering compensation ... in violation of the constitutions and laws of the United States and of the State of Florida.” NPL also claimed that the rezoning did not comply with the dimensional requirements and safety regulations for a private airport. NPL asked the court to declare the rezoning invalid, to return the property to its RU-2 zone classification, and to provide any further relief the court deemed appropriate.
On January 2, 1986, the state court granted NPL’s petition to invalidate the rezoning ordinance. The court found that the County’s rezoning of the property to PA violated the dimensional requirements of a private airport zone, the County had not complied with the procedures of its Major Development Project Ordinance, and the rezoning “would deprive [NPL] of any reasonable use” of its property. Accordingly, the court declared invalid and quashed the County’s rezoning of the subject property. Because the court found that the County had acted in good faith in pursuing the rezoning, however, it did not award damages to NPL.4 Neither party sought appellate review of the court’s decision.
B.
On July 7, 1987, NPL brought this action in the United States District Court for the Southern District of Florida, seeking, among other forms of relief, just compensation for the alleged temporary regulatory “taking” of its property5 both under 42 U.S.C. § 1983 (1988), and directly under the Fifth Amendment as made applicable to the states by the Fourteenth Amendment.6 NPL alleged that the taking occurred when the County rezoned the property to a PA zone classification. The County filed a motion to dismiss all counts of the complaint asserting that NPL’s takings claims were barred by res judicata and by the statute of limitations. See New Port Largo, Inc. v. Monroe County, 706 F.Supp. 1507, 1511 (S.D.Fla.1988).
On November 21, 1988, the district court found that the state court had not rendered [1492]*1492a final adjudication on NPL’s takings claims, and therefore rejected the County’s res judicata defense. Id. at 1512-13 & n. 3; see Corn III, 904 F.2d at 587 (res judicata defense based on state petition attacking the validity of ordinances did not preclude later claim for just compensation). In considering the County’s statute of limitations argument, the district court reasoned that all just compensation claims should be treated similarly, regardless of whether the claims allege a complete taking or a temporary regulatory taking. New Port Largo, 706 F.Supp. at 1516-17. The court opined that in all actions to rectify the government’s taking of private property, the applicable “statute of limitations runs from the time of [the government’s] appropriation.” Id. at 1516. The court suggested that the statute of limitations can be tolled only if the government continues to violate the law by new acts of appropriation.7 Id. at 1517.
Utilizing this “continuing wrong” tolling doctrine, the court initially held that the last act of appropriation by the County occurred on April 9, 1985, when the state district court of appeal finally quieted title to the subject property in NPL.8 Id. at 1518. After holding that the applicable statute of limitations in takings actions runs for four years,9 here until April 9, 1989, the district court found that NPL’s filing of its takings claims on July 7, 1987, fell well within the statutory period. Id.
On July 17, 1989, the County filed a motion for summary judgment seeking reconsideration of the court’s determination that the last act of appropriation occurred on April 9, 1985, and arguing anew that NPL’s regulatory takings claims were barred by the statute of limitations. Utilizing the district court’s tolling doctrine, the County contended that NPL’s sale of the subject property on September 9, 1982, precluded any tolling of the statute of limitations beyond that date by additional wrong[1493]*1493ful acts of appropriation by the County. As viewed by the County, NPL’s action accrued on September 9, 1982, and the appropriate statute of limitations for NPL’s action ran out four years later, on September 9,1986, almost a year prior to the filing of NPL’s claims in district court on July 7, 1987. The county concluded that NPL’s claims were time-barred.
Free access — add to your briefcase to read the full text and ask questions with AI
PER CURIAM:
The principal issue presented by these consolidated appeals is whether the district court erred in granting appellee’s motion for summary judgment by applying the wrong tolling doctrine to appellant New Port Largo, Inc.’s (NPL) temporary regulatory takings claims, thereby holding [1490]*1490the claims barred by the applicable statute of limitations. NPL sold the subject property two years after the enactment of the allegedly infringing regulation. The district court, observing that the regulation could cause NPL no injury thereafter, held that the applicable statute of limitations ran from the date NPL sold the property. NPL contends that the statute of limitations was tolled until the state court, in passing on the validity of the regulation, declared the regulation invalid. Based on Corn v. City of Lauderdale Lakes, 904 F.2d 585 (11th Cir.1990) (Com III),1 we conclude that the district court erred. Accordingly, we vacate the district court’s judgment and remand the case for further proceedings.2
I.
A.
In August 1968, the State of Florida sold a parcel of submerged land located on Key Largo’s Atlantic coast to a private trust.3 In December 1972, after the private trust filled in and prepared the land for residential construction, the Monroe County Planning and Zoning Department (the Zoning Department) zoned the property for residential duplex use (RU-2).
In September 1979, NPL purchased the property from the private trust. In November 1979, appellee Monroe County (the County) filed an application with the Zoning Department to rezone the property from RU-2 to private airport use (PA). On January 24, 1980, the Zoning Department held a hearing on the proposed rezoning and subsequently approved the County’s application. NPL appealed the Zoning Department’s decision to the Monroe County Board of Commissioners (the Commission). On September 11, 1980, the Commission affirmed the Zoning Department’s decision.
On October 10, 1980, NPL filed a petition for a writ of certiorari in state circuit court alleging that the rezoning violated Florida law. NPL claimed that the County had not complied with the procedural requirements of its Major Development Project Ordinance, an ordinance that applies to rezon-ings which, as here, concern parcels of land greater than five acres. On September 9, 1982, during the pendency of its certiorari petition, NPL sold the property in question, conveying one-half undivided interests in fee simple both to TFW, Inc., a Florida corporation, and to a land trust administered by the First National Bank of South Miami. Neither of these purchasers intervened in the certiorari proceeding brought by NPL. In August 1985, NPL amended [1491]*1491its petition to include a claim that the County had deprived NPL of its property “without offering compensation ... in violation of the constitutions and laws of the United States and of the State of Florida.” NPL also claimed that the rezoning did not comply with the dimensional requirements and safety regulations for a private airport. NPL asked the court to declare the rezoning invalid, to return the property to its RU-2 zone classification, and to provide any further relief the court deemed appropriate.
On January 2, 1986, the state court granted NPL’s petition to invalidate the rezoning ordinance. The court found that the County’s rezoning of the property to PA violated the dimensional requirements of a private airport zone, the County had not complied with the procedures of its Major Development Project Ordinance, and the rezoning “would deprive [NPL] of any reasonable use” of its property. Accordingly, the court declared invalid and quashed the County’s rezoning of the subject property. Because the court found that the County had acted in good faith in pursuing the rezoning, however, it did not award damages to NPL.4 Neither party sought appellate review of the court’s decision.
B.
On July 7, 1987, NPL brought this action in the United States District Court for the Southern District of Florida, seeking, among other forms of relief, just compensation for the alleged temporary regulatory “taking” of its property5 both under 42 U.S.C. § 1983 (1988), and directly under the Fifth Amendment as made applicable to the states by the Fourteenth Amendment.6 NPL alleged that the taking occurred when the County rezoned the property to a PA zone classification. The County filed a motion to dismiss all counts of the complaint asserting that NPL’s takings claims were barred by res judicata and by the statute of limitations. See New Port Largo, Inc. v. Monroe County, 706 F.Supp. 1507, 1511 (S.D.Fla.1988).
On November 21, 1988, the district court found that the state court had not rendered [1492]*1492a final adjudication on NPL’s takings claims, and therefore rejected the County’s res judicata defense. Id. at 1512-13 & n. 3; see Corn III, 904 F.2d at 587 (res judicata defense based on state petition attacking the validity of ordinances did not preclude later claim for just compensation). In considering the County’s statute of limitations argument, the district court reasoned that all just compensation claims should be treated similarly, regardless of whether the claims allege a complete taking or a temporary regulatory taking. New Port Largo, 706 F.Supp. at 1516-17. The court opined that in all actions to rectify the government’s taking of private property, the applicable “statute of limitations runs from the time of [the government’s] appropriation.” Id. at 1516. The court suggested that the statute of limitations can be tolled only if the government continues to violate the law by new acts of appropriation.7 Id. at 1517.
Utilizing this “continuing wrong” tolling doctrine, the court initially held that the last act of appropriation by the County occurred on April 9, 1985, when the state district court of appeal finally quieted title to the subject property in NPL.8 Id. at 1518. After holding that the applicable statute of limitations in takings actions runs for four years,9 here until April 9, 1989, the district court found that NPL’s filing of its takings claims on July 7, 1987, fell well within the statutory period. Id.
On July 17, 1989, the County filed a motion for summary judgment seeking reconsideration of the court’s determination that the last act of appropriation occurred on April 9, 1985, and arguing anew that NPL’s regulatory takings claims were barred by the statute of limitations. Utilizing the district court’s tolling doctrine, the County contended that NPL’s sale of the subject property on September 9, 1982, precluded any tolling of the statute of limitations beyond that date by additional wrong[1493]*1493ful acts of appropriation by the County. As viewed by the County, NPL’s action accrued on September 9, 1982, and the appropriate statute of limitations for NPL’s action ran out four years later, on September 9,1986, almost a year prior to the filing of NPL’s claims in district court on July 7, 1987. The county concluded that NPL’s claims were time-barred. The district court, adopting the County’s argument, granted the County’s motion for summary judgment on December 22, 1989.10 NPL appealed, No. 90-5091, and the County cross-appealed the district court’s denial of attorneys’ fees, No. 90-5327.
II.
Our review of the applicable statute of limitations doctrine is a question of law subject to de novo review. Atlantic Land & Improvement Co. v. United States, 790 F.2d 853, 857 (11th Cir.1986). The determination of the accrual date of a federal regulatory takings claim depends on the occurrence of two events. First, state judicial authorities must make a final determination on the status of the subject property affected by the zoning ordinance. Corn III, 904 F.2d at 588 (holding that a regulatory takings claim is not mature until a state appellate court affirmed issuance of mandamus invalidating zoning ordinance); Norco Constr., Inc. v. King County, 801 F.2d 1143, 1145 (9th Cir.1986) (finding that a just compensation claim matures only after “planning authorities and state review entities make a final determination on the status of the property”). But cf. Williamson County Regional Planning Comm’n v. Hamilton Bank, 473 U.S. 172, 192-93, 105 S.Ct. 3108, 3119-20, 87 L.Ed.2d 126 (1985) (holding that a takings claim ripens after final determination by the initial decisionmaker). Second, the property owner must be denied an adequate postde-privation remedy. Williamson, 473 U.S. at 195, 105 S.Ct. at 3121. For statute of limitations purposes, both events are necessary for the accrual of a property owner’s takings claim.
First, if NPL had remained the owner of the subject property, then its takings claims could not have accrued for purposes of the statute of limitations until the state judicial authorities had made a final determination on the status of the property. See Corn III, 904 F.2d at 588. In the instant case, the state circuit court entered a final judgment on January 2, 1986, invalidating the County’s rezoning of the property. The parties did not appeal. The state circuit court’s judgment, therefore, was the state’s final determination on the status of the subject property. See id.
Second, NPL must show that the state denied it adequate procedures through which NPL could seek compensation for the alleged taking. “[T]he State’s action is not ‘complete’ in the sense of causing a constitutional injury ‘unless or until the State fails to provide an adequate postde-privation remedy for the property loss.’ ” Williamson, 473 U.S. at 195, 105 S.Ct. at 3121 (quoting Hudson v. Palmer, 468 U.S. 517, 532 n. 12, 104 S.Ct. 3194, 3203 n. 12, 82 L.Ed.2d 393 (1984)). At the time of the state circuit court’s final judgment,11 Florida courts did not recognize damages claims arising from regulatory takings. See Dade County v. National Bulk Carriers, Inc., 450 So.2d 213, 216 (Fla.1984).12 Florida [1494]*1494law, therefore, provided no postdeprivation remedy for NPL’s claimed deprivations.
Assuming NPL’s continuous and uninterrupted ownership of the land, NPL’s claims would have accrued on January 2, 1986, the date of the final judgment. At that time, both events required by Williamson to establish accrual of the takings claims had occurred. Applying Corn III, no matter which statute of limitations period urged by the parties governs the claims, NPL timely filed its takings claims in district court on July 7, 1987.13
The unique feature of this case is, however, that NPL sold its property three and one-half years before the state circuit court reached a final determination on the status of the subject property. The district court reasoned that this sale ended the toll on NPL’s otherwise properly tolled claims because no new appropriation of the property could befall NPL after the date of sale. The district court’s analysis therefore assumes, for purposes of the statute of limitations, that the date of sale determined the accrual date of NPL’s claims.14
Corn III’s approach to tolling the statute of limitations in regulatory takings cases, however, compels the opposite conclusion. First, the state court allowed NPL’s state claims to proceed to a final judgment. This necessarily implies that NPL demonstrated sufficient injury-in-fact to litigate the scope and legality of the County’s rezoning of the subject property.
Second, under Corn III, takings claims can accrue, if ever, only after the state judiciary’s final determination on the status of the subject property. Corn III, 904 F.2d at 588. NPL’s injury may have ended when it sold the property, but, under Corn III, NPL’s claims did not accrue until the state proceedings had concluded.
We do not hold that the sale of the property in this case has no relevance to NPL’s takings claims. The sale may prove relevant to a determination of the amount of compensation that would be “just” if NPL does establish that it is entitled to compensation for the taking of its property. Rather, we hold today that the state’s invalidation of the zoning ordinance, not NPL’s sale of the property, determines of the accrual date of NPL’s action.
[1495]*1495III.
For the foregoing reasons, we find that NPL’s temporary regulatory takings claims were tolled until January 2, 1986, when the state circuit court invalidated the County’s rezoning of the subject property. NPL’s claims are not time-barred. Accordingly, we vacate the district court’s judgment and remand this case for further proceedings.
VACATED and REMANDED.