New England Utilities v. Hydro-Quebec

10 F. Supp. 2d 53, 1998 U.S. Dist. LEXIS 9066, 1998 WL 327906
CourtDistrict Court, D. Massachusetts
DecidedJune 15, 1998
DocketCivil Action 97-12545-PBS
StatusPublished
Cited by10 cases

This text of 10 F. Supp. 2d 53 (New England Utilities v. Hydro-Quebec) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Utilities v. Hydro-Quebec, 10 F. Supp. 2d 53, 1998 U.S. Dist. LEXIS 9066, 1998 WL 327906 (D. Mass. 1998).

Opinion

MEMORANDUM AND ORDER

SARIS, District Judge.

INTRODUCTION

This case concerns an arbitration of a pricing dispute between New England Utilities (“NEU”), which is a group of American power companies, and Hydro-Quebec, a Canadian power company from which NEU purchases power. The parties disagree over whether two different “costs” should be included in the complex pricing formula in their long-term so-called Firm Energy Contract (the “Contract”). The dispute was aired at a three-week arbitration hearing in Boston before George A. Avery of the American Arbitration Association (“AAA”), who on October 10, 1997 adopted NEU’s interpretation of its payment requirements to Hydro-Quebec.

Within days of the arbitrator’s decision, NEU filed an action in Massachusetts Superior Court seeking to confirm the award under the Massachusetts Uniform Arbitration Act. Mass.G.L. c. 251, § 11. Hydro-Quebec filed a timely, notice of removal to federal court based on diversity jurisdiction. 28 U.S.C. §§ 1332, 1441(a) & 1446(b). Hydro-Quebec then moved to vacate the Arbitrator’s decision based on two “errors of law,” which, Hydro-Quebec argues, are reviewable by this Court pursuant to the arbitration clause of the Contract. NEU responds (1) that Hydro-Quebec’s motion to vacate was untimely under Massachusetts arbitration law; (2) that the Court’s review should be limited to state or federal statutory standards less rigorous than “error of law”; and (3) that, in any event, the Arbitrator committed no legal error.

After hearing, the Court concludes that the motion to vacate is timely and that judicial review for arbitral errors' of law is appropriate under the parties’ agreement, but that the Arbitrator did not commit legal error in *56 excluding the two costs. Therefore, the Court ALLOWS NEU’s Motion to Confirm and DENIES Hydro-Quebec’s Motion to Vacate the Decision of the Arbitrator.

BACKGROUND

The factual background recited here is based exclusively on the factual findings of the Arbitrator in his October 10, 1997 decision and on the Contract between the parties, dated October 14,1985.

NEU is an unincorporated group of public and private utilities, each member of which is a participant in the New England Power Pool (“NEPOOL”), a common physically interconnected electric generation and transmission system for the New England region. 1 (Arb’r Dec. at 1.) Twenty companies and plants are listed in the Contract as members of NEU, including large regional companies, such as New England Power Company and The Connecticut Light and Power Company, and others which are far smaller. (Contract Supp. III.) A NEPOOL Management Committee, made up of executives of some of the participating utility companies, acts on behalf of all member companies of NEU.

Hydro-Quebec, a Crown corporation of Quebec, Canada, is headquartered in Montreal,

A. The Firm Energy Contract

The contractual arrangement that is the centerpiece of this dispute arose out of the recognition by some of the NEPOOL Participants in the 1970s that they were relying too heavily for their energy needs on fossil fuel, principally oil and coal, at a time when the future supply of fossil fuel was potentially unreliable and expensive. Across the northern border was Hydro-Quebec, a “major vertically integrated utility” with vast power generation capabilities relying not on fossil fuel but rather, as the name suggests, on hydro-electric power from sources in the northern part of the province of Quebec. (Arb’r Dee. at 18.) Sensing a compatible relationship, NEU and Hydro-Quebec agreed to physically interconnect their systems and arrange the delivery of power from Quebec to New England. (Id. at 18-19.)

The parties initially entered into an “Energy Contract” (not implicated in this case) which “provided for [Hydro-Quebec] energy sales to NEPOOL on an as-available basis.” (Id. at 20.) The subsequent “Firm Energy Contract,” the Contract under which this dispute arises, was signed on October 14, 1985 and is effective through August 31, 2004, at the latest. (Contract Art. 21.0.) NEU agreed to pay for a fixed annual quantity of energy from 1985 until August 31, 2000, and Hydro-Quebec agreed to make that fixed amount available across an agreed-upon “Interconnection” on the international border. (Contract Art. 2.1.) The fixed annual quantity is seven terawatt-hours of energy, or seven million megawatt-hours (MWh). (Id.)

The Contract’s pricing structure is complicated. The price is a rate, measured in United States Dollars per megawatt-hour of energy ($/MWh). The rate is based on a “reference price,” which was initially set by the Contract at $32.25/MWh. 2 The “price applicable for each megawatthour of Contract Energy delivered” is calculated by multiplying the reference price times the ratio of (i) certain of NEPOOL’s current fossil fuel costs to (ii) the same fossil fuel costs as they were in 1983. The historical 1983 “cost,” the denominator of the ratio, was fixed by the Contract at the rate of $40.33/MWh. In other words, any variation in the rate paid by NEU to Hydro-Quebec depends exclusively on the costs NEU incurs each year for its traditional source of electricity, fossil fuel.

The use of NEU’s fossil fuel costs, seemingly unrelated to the deal, as a price gauge *57 was mutually beneficial to the parties. As the Arbitrator found, “[u]se of this approach met NEPOOL’s goal of reducing the output of its fossil-fired plants and [Hydro-Que-bee’s] goal of creating an attractive market for its hydro-generated surplus based, not on the low production cost of hydro-generation, but on the higher production cost of the fossil-fired facilities it would supplant.” (Arb’r Dec. at 19.) Said another way, for every nickel NEU saved on costs devoted to fossil fuel, it received a marginally lower rate on energy purchased from Hydro-Quebec. Hydro-Quebec, on the other hand, would presumably see an increase in volume sold to NEU of its hydro-electric power as NEU attempted to reduce its fossil fuel reliance.

The variable current fossil fuel cost figure in the Contract Energy price ratio is at the heart of this controversy between the parties. The cost figure, referred to in the Contract as the Annual Weighted NEPOOL Fossil Energy Cost (“AWNFEC”), is derived from another formula found in Supplement I of the Contract. (A copy of Supplement I is attached to this opinion as Appendix A.) The AWNFEC is “based on the actual experience of the NEPOOL Participants during the twelve-month period starting September 1st and ending August 31st.” (Contract Supp. I.) It is a ratio of absolute cost (in U.S. Dollars) to energy (in MWh). Specifically, the AWNFEC

shall be the quotient obtained from dividing
1) the total cost of the Fossil Fuel burned, by NEPOOL Participants for the production of electrical energy during such twelve-month period, by

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman J. Martinez v. Ring-Central, Inc.
District Court of Appeal of Florida, 2024
A Better Way Wholesale Autos, Inc. v. Saint Paul
Connecticut Appellate Court, 2019
Nationwide Mutual Ins. v. Liberty Mutual Ins.
57 F. Supp. 3d 112 (D. Massachusetts, 2014)
Cable Connection, Inc. v. DirecTV, Inc.
190 P.3d 586 (California Supreme Court, 2008)
Del Piano v. Merrill Lynch
859 A.2d 742 (New Jersey Superior Court App Division, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
10 F. Supp. 2d 53, 1998 U.S. Dist. LEXIS 9066, 1998 WL 327906, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-utilities-v-hydro-quebec-mad-1998.