New England Power Co. v. Federal Energy Regulatory Commission

533 F.3d 55, 2008 U.S. App. LEXIS 15114, 2008 WL 2747038
CourtCourt of Appeals for the First Circuit
DecidedJuly 16, 2008
Docket07-2418
StatusPublished
Cited by1 cases

This text of 533 F.3d 55 (New England Power Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Power Co. v. Federal Energy Regulatory Commission, 533 F.3d 55, 2008 U.S. App. LEXIS 15114, 2008 WL 2747038 (1st Cir. 2008).

Opinions

LIPEZ, Circuit Judge.

New England Power Company (“NEP”) seeks review of orders of the Federal Energy Regulatory Commission (“FERC” or the “Commission”).1 In the orders, FERC found the 18 percent per year late payment charge that NEP had applied to the Town of Norwood’s overdue contract termination payments to be unjust and unrea[57]*57sonable. FERC ordered that NEP substitute a prime rate-based interest rate as set forth in 18 C.F.R. § 35.19a (the “Revised Interest Rate”). NEP does not appeal this ruling. Instead, NEP challenges only FERC’s determination that the lower Revised Interest Rate must be applied to bills rendered before June 30, 2006, arguing that the earlier application constitutes impermissible retroactive rate-making. Because FERC failed to address NEP’s retroactivity arguments and instead based its decision to apply the Revised Interest Rate to the earlier bills solely on an erroneous reading of our opinion in Town of Norwood v. FERC, 476 F.3d 18, 29 (1st Cir.), cert. denied, — U.S.-, 128 S.Ct. 432, 169 L.Ed.2d 258 (2007) (“Norwood IV”), we vacate that portion of the orders and remand for full consideration by the Commission of the appropriate effective date for the Revised Interest Rate.

I.

The background of this protracted dispute is set forth in detail in Town of Norwood v. FERC, 202 F.3d 392, 397-98 (1st Cir.), cert. denied, 531 U.S. 818, 121 S.Ct. 57, 148 L.Ed.2d 24 (2000) (“Norwood I ”), Town of Norwood v. FERC, 202 F.3d 408, 412-14 (1st Cir.), cert. denied, 531 U.S. 818, 121 S.Ct. 57, 148 L.Ed.2d 24 (2000) (“Norwood II ”), Town of Norwood v. FERC, 217 F.3d 24, 25-27 (1st Cir.), cert. denied, 532 U.S. 993, 121 S.Ct. 1653, 149 L.Ed.2d 636 (2001) (“Norwood III”), and Norwood IV, 476 F.3d at 20-24. For our purposes, only a brief outline is required.

The case arises from the Town of Nor-wood’s 1998 decision to terminate its full requirements electric service contract with NEP prior to its scheduled expiration in 2008 so that Norwood could change power suppliers. Pursuant to a FERC-approved tariff, Norwood was permitted to terminate the contract early upon payment of a contract termination charge (the “CTC”). The CTC was calculated using a formula that would enable NEP to recover the revenues that it would have collected if a terminating customer had continued to pay the tariff rate then in effect through the end of the contract term. In a series of lawsuits, Norwood mounted unsuccessful challenges to the reasonableness of the CTC formula, as well as the values used in calculating the amount of the CTC under the formula.

In Norwood IV, we disposed of the last of Norwood’s substantive challenges to the CTC formula, concluding that Norwood’s remaining objections were either without merit or barred by res judicata. We then turned to a series of arguments raised by Norwood regarding late payment charges applicable to the monthly bills for CTC installments. NEP had begun sending these bills to Norwood in May 1998. In June 1998, it had begun including late payment charges of 18 percent per year (1.5 percent per month) as set forth in schedule I, section J of its tariff.2 We affirmed FERC’s conclusion that the sec[58]*58tion J rate was the governing provision for the late payment charge, but concluded that FERC’s June 30, 2006 order had not adequately addressed Norwood’s contention that the 18 percent rate constituted an unreasonable penalty. Norwood had argued that the rate was unreasonable because it was in excess of NEP’s cost of money and was inconsistent with Connecticut Light & Power Co., 59 F.P.C. 811 (1977), in which FERC itself had rejected a proposed 18 percent late fee on the ground that it was “not supported by cost data.” Id. at 821. We rejected FERC’s decision to distinguish Connecticut Light & Power based solely on Norwood’s failure to introduce cost evidence to show that the provision was not cost related, noting that “NEP[ ] does not seriously suggest that 18 percent represents its cost of money.” Norwood IV, 476 F.3d at 28. Accordingly, we remanded the issue to the Commission with instructions to “squarely and adequately resolve” the issue of the reasonableness of the 18 percent rate. Id. at 29.

We then addressed “one other loose end as to interest,” concerning Norwood’s argument that “even if the 18 percent rate is applicable to CTC late payments, the rate should not be applied to payments due prior to FERC’s order of February 22, 2006, since before that point the CTC amount had not been determined.”3 Id. We rejected this argument by relying on the language of the tariff itself, which anticipated that the amount billed may be in dispute and provided that interest nevertheless would accrue during the pendency of the dispute:

[Election J makes it quite clear that, when a customer disputes an amount billed by a carrier, the carrier is entitled to prescribed interest that accrues “from ... the rendering of said bill” on “the amount finally determined to be due and payable.”

Id. We then concluded our discussion with a paraphrase of the tariff language: “Nor-wood has challenged the amount of interest prescribed; but whatever the figure FERC finds justified, the tariff provides that Norwood owes that amount from the time the bill was rendered.” Id. In summarizing our holdings at the end of the opinion, we restated that Norwood was responsible for “interest payments based on at least the prime rate — the figure Nor-wood itself seeks — and remand[ed] only as to whether more was properly due.” Id.

On remand, FERC concluded that the 18 percent interest rate for late payments was unjust and unreasonable and directed NEP to “file a report with the Commission reflecting the amount of the CTCs owed, plus the applicable interest rate(s) and interest amount(s), calculated pursuant to section 35.19a of the Commission’s regulations.” NEP filed a motion for clarification and an alternative request for rehearing as to the effective date of the Revised Interest Rate. NEP argued that the Commission is generally only empowered, under § 206 of the Federal Power Act, 16 U.S.C. § 824e, to order prospective relief when rates within a tariff are determined to be unreasonable. NEP asserted that the only applicable exception to this rule provides that when an appellate court has reversed a Commission order upholding an existing rate, the Commission may make the relief effective as of the date of the overturned order. See Natural Gas Clearinghouse v. FERC, 965 F.2d 1066, 1073 (D.C.Cir.1992) (per curiam) (holding that FERC may make a new rate effective as of the date of an overturned order by [59]*59applying the “general principle of agency authority to implement judicial reversals”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
533 F.3d 55, 2008 U.S. App. LEXIS 15114, 2008 WL 2747038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-power-co-v-federal-energy-regulatory-commission-ca1-2008.