Neuhoff v. Marvin Lumber & Cedar Co.

370 F.3d 197, 53 U.C.C. Rep. Serv. 2d (West) 711, 2004 U.S. App. LEXIS 11092, 2004 WL 1242333
CourtCourt of Appeals for the First Circuit
DecidedJune 7, 2004
Docket03-2111
StatusPublished
Cited by54 cases

This text of 370 F.3d 197 (Neuhoff v. Marvin Lumber & Cedar Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neuhoff v. Marvin Lumber & Cedar Co., 370 F.3d 197, 53 U.C.C. Rep. Serv. 2d (West) 711, 2004 U.S. App. LEXIS 11092, 2004 WL 1242333 (1st Cir. 2004).

Opinion

TORRUELLA, Circuit Judge.

Plaintiffs-appellants, Roger and Louise Neuhoff (hereinafter jointly referred to as “the Neuhoffs”) brought a diversity action against defendants-appellees Marvin Lumber & Cedar Company and Marvin Windows of Tennessee, Inc. (hereinafter jointly referred to as “Marvin”) for breach of an oral contract, breach of implied warranty, violation of Mass. Gen. Laws ch. 93A, and promissory estoppel. The district court granted Marvin’s motion for summary judgment on all four claims. We conclude that the district court appropriately granted summary judgment on the first three claims, but inappropriately granted summary judgment on the promissory estoppel claim. We, therefore, affirm in part and reverse in part.

I. Background

In 1991, the Neuhoffs purchased and installed sixty windows manufactured by Marvin. In 1994, the Neuhoffs noticed that many of the windows were decaying and notified Simon Hickman, the contractor who installed the windows, of the decay.

The parties disagree as to when Marvin was notified of the decay. The Neuhoffs contend that Marvin was notified in 1994 or early 1995 when Marvin’s area distributor came to examine the windows. Marvin contends that it did not learn of the decay until late 1997 when the area distributor contacted Marvin regarding the decay.

In 1998, Marvin sent Roy Holthusen to inspect the windows. The inspection showed that 56 windows had either “obvious decay” or “incipient decay.” In March 1998, Marvin sent the Neuhoffs a letter promising to replace 33 windows for free. Several weeks later, after inquiring about the remaining windows, the Neuhoffs claim that Marvin’s agent, Greg Muirhead, orally informed them that the remaining windows would be replaced for free, but that Marvin could not replace them yet due to production problems. In 1999, Marvin replaced 33 of the windows that were in the most advanced state of decay.

In June 2000, the Neuhoffs contacted Marvin again because the windows that had not been replaced had reached an advanced state of decay. Marvin sent another inspector to the Neuhoffs’ home. This inspector concluded that 21 windows, including four of the newly installed windows, had obvious decay. In January 2001, Marvin informed the Neuhoffs that their windows would not be replaced for free, but that the Neuhoffs could purchase replacement windows at a 32% discount. The Neuhoffs filed suit in July 2001.

II. Standard of Review

We review summary judgment decisions de novo, viewing the facts in the light most favorable to the nonmoving party. GTE Wireless, Inc. v. Cellexis Int’l, Inc., 341 F.3d 1, 4 (1st Cir.2003). Summary judgment is inappropriate if there is a genuine issue as to any material fact. Id. It is undisputed that Massachusetts substantive law controls.

III. Analysis

A. Breach of oral contract

The Neuhoffs allege that Marvin breached an oral contract to provide replacement *201 windows for free. The oral contract was allegedly made in March 1998 when Greg Muirhead informed the Neuhoffs that their decaying windows would be replaced once Marvin’s production problems were fixed and the windows reached a more advanced stage of decay.

The district court held that there was not a breach of an oral contract because the promise to replace the defective windows constituted a remedy, not a new contract. See Neuhoff v. Marvin Lumber & Cedar Co., 2003 WL 21672831, at *1-2, 2008 U.S. Dist. LEXIS 12278, at *4 (D.Mass. Jul. 16, 2003) (citing New England Power Co. v. Riley Stoker Corp., 20 Mass.App.Ct. 25, 477 N.E.2d 1054, 1058 (App.Ct.1985)). As a result, the district court granted Marvin’s summary judgment motion on this claim. Although we disagree with the district court’s reasoning, we do not disagree with the result.

The district court’s reliance on New England Power and the cases cited therein was mistaken for several reasons. First, in New England Power, the promises to repair were viewed as remedies “rather than as an independent or separate warranty” because the warranty and the promise to repair were included in the same contract. New England Power, 477 N.E.2d at 1058. The logic behind New England Power is that a promise to repair does not create a contract independent from the warranty because if it did, then “limitations periods could be extended for virtually infinite time.” Id. In this case, however, the initial contract was executed in 1991. The promise to repair did not allegedly occur until 1998 and was not a part of the original contract or warranty in effect. Marvin went to great lengths to emphasize that the original contract warranty had expired and the ten year warranty was inapplicable. Thus, the promise to repair was independent of the warranties and could, therefore, be breached.

Second, by applying New England Power, the district court confuses a “promise to repair warranty” from a promise to repair that is made after a product’s defects are known. A “promise to repair warranty” refers to a type of warranty that stipulates the remedy to be invoked if the product purchased becomes faulty. See Standard Alliance Indus., Inc. v. Black Clawson Co., 587 F.2d 813, 818 n. 10 (6th Cir.1978). If the promisor does not abide by the promise to repair, then the promisee has a cause of action for the underlying breach of warranty for the defective product. New England Power, 477 N.E.2d at 1058. In this case, the promise to repair made by Marvin was not the type of promise that stipulates the remedy to be invoked in case of a defect, rather it was an independent promise addressing a known defect.

Nonetheless, the Neuhoffs’ breach of contract claim fails because Marvin’s alleged promise to repair lacked consideration. See Geffon v. Micrion Corp., 249 F.3d 29, 35 (1st Cir.2001) (court of appeals may affirm a grant of summary judgment on any ground supported by the record). A contract must have consideration to be enforceable and “[i]n order for a contract to have valid consideration, the contract must be a bargained-for exchange in which there is a legal detriment of the promisee or a corresponding benefit to the promisor.” See Hinchey v. NYNEX Corp., 144 F.3d 134, 142 (1st Cir.1998) (quotations and citations omitted).

The Neuhoffs allege three types of consideration: (1) forbearance of their legal claims, (2) the time and labor expended assisting Marvin in connection with Marvin’s promise to replace the defective windows, and (3) the benefit Marvin received *202 to their reputation by agreeing to replace the windows.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
370 F.3d 197, 53 U.C.C. Rep. Serv. 2d (West) 711, 2004 U.S. App. LEXIS 11092, 2004 WL 1242333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neuhoff-v-marvin-lumber-cedar-co-ca1-2004.