George P. Johnson Hong Kong Ltd. v. L.E.K. Consulting LLC

CourtDistrict Court, D. Massachusetts
DecidedDecember 18, 2020
Docket1:20-cv-11269
StatusUnknown

This text of George P. Johnson Hong Kong Ltd. v. L.E.K. Consulting LLC (George P. Johnson Hong Kong Ltd. v. L.E.K. Consulting LLC) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George P. Johnson Hong Kong Ltd. v. L.E.K. Consulting LLC, (D. Mass. 2020).

Opinion

United States District Court District of Massachusetts

) George P. Johnson Hong Kong Ltd., ) ) Plaintiff, ) ) v. ) ) Civil Action No. L.E.K. Consulting LLC ) 20-11269-NMG ) Defendant. ) ) ) )

MEMORANDUM & ORDER

GORTON, J.

Plaintiff George P. Johnson Company Hong Kong Ltd. (“GPJ” or “plaintiff”) brings suit against L.E.K. Consulting LLC (“L.E.K.” or “defendant”) for breach of contract and breach of the implied covenant of good faith and fair dealing. Pending before the Court is defendant’s motion to dismiss for failure to state a claim. For the reasons that follow, that motion will be denied. I. Background

GPJ is a Hong Kong-based, event-planning firm and L.E.K. is a global consulting company with its principal place of business in Boston, Massachusetts. In early 2019, L.E.K. contacted GPJ for assistance in planning and conducting a global management conference (“the Conference”) to be hosted by L.E.K in Hong Kong in March, 2020. GPJ alleges that the parties ultimately executed a contract memorializing GPJ’s role as the Conference planner. The negotiations with respect to and the terms of the

purported contract are summarized below. GPJ avers that, in March, 2019, a manager of L.E.K. contacted GPJ to assist L.E.K. in securing a venue and amenities for the Conference. GPJ contends that it subsequently negotiated a proposal with a hotel in Hong Kong (“the Hotel”) for the Conference which L.E.K. approved. GPJ asserts that, in April, 2019, it obtained a quote from the Hotel covering hotel rooms, meeting rooms and dinners. After reviewing that quote, according to GPJ, an L.E.K. representative stated, “let’s go to contract”, in response to which GPJ sent to L.E.K. two iterations of a document entitled “Event Cost Estimate and Variance Report”. The complaint

contends that the final version of that document dated May 22, 2019 (Exhibit D) is a binding contract (“the purported contract”) and reflects a negotiated total price of $1.6 million for accommodations and conference management services of GPJ. The purported contract provides that 50% of the quoted price would be payable six months prior to the event (in September, 2019) and imposes the following cancellation fee provisions “if the event is cancelled by the Client”: - as of agreement confirmation date, 30% of total cost; - after July 31, 2019, 60% of total cost; - after October 30, 2019, 90% of total cost; and - after January 31, 2020, 100% of total cost.

According to GPJ, a representative from L.E.K. subsequently reviewed that document and, on May 29, 2019, delivered a signed copy of it to GPJ (the signed copy is attached to the complaint as Exhibit D). Approximately two months later, GPJ purportedly sent an invoice to L.E.K. for 50% of the quoted price but L.E.K. did not then and has not since made any payment. Instead, in September, 2019, L.E.K. sent an email to GPJ expressing concern about the Conference because of the violent protests then occurring in Hong Kong.1 It also requested and was granted by GPJ a two-week extension of the October, 2019, cancellation deadline. GPJ submits that, on November 14, 2019, L.E.K. sent to it a formal notice of cancellation, thus invoking the 60% cancellation fee due under the purported contract. According to the complaint, however, L.E.K. has refused to make any payments to GPJ. Accordingly, in June, 2020, GPJ filed this civil action against L.E.K. in a Massachusetts Superior Court, alleging breach of contract (Count I) and breach of the implied covenant of good faith and fair dealing (Count II). L.E.K. subsequently

1 Pursuant to Fed. R. Evid. 201, the Court will take judicial notice of the extreme political unrest which has occurred in Hong Kong beginning in or about June, 2019. removed the case to this Court on diversity jurisdiction grounds and now moves to dismiss the complaint for its failure to plead an enforceable contract. II. Discussion

A. Legal Standard

To survive a motion under Fed. R. Civ. P. 12(b)(6), the subject pleading must contain sufficient factual matter to state a claim for relief that is actionable as a matter of law and “plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). A claim is facially plausible if, after accepting as true all non-conclusory factual allegations, the court can draw the reasonable inference that the defendant is liable for the misconduct alleged. Ocasio-Hernandez v. Fortuno-Burset, 640 F.3d 1, 12 (1st Cir. 2011). When rendering that determination, a court may not look beyond the facts alleged in the complaint, documents incorporated by reference therein and facts susceptible to judicial notice. Haley v. City of Boston, 657 F.3d 39, 46 (1st Cir. 2011). A court also may not disregard properly pled factual allegations even if actual proof of those facts is improbable. Ocasio-Hernandez, 640 F.3d at 12. Rather, the relevant inquiry focuses on the reasonableness of the inference of liability that the plaintiff is asking the court to draw. Id. at 13. B. Application 1. Breach of Contract

To state a claim for breach of contract under Massachusetts law, the plaintiff must allege that 1) a valid contract exists between the parties, 2) the defendant failed to perform its obligations under that contract and 3) such failure caused the plaintiff damage. See Shaulis v. Nordstrom, Inc., 120 F. Supp. 3d 40, 54 (D. Mass. 2015) (quoting Guckenberger v. Bos. Univ., 957 F. Supp. 306, 316 (D. Mass. 1997)). A valid contract exists if, at the time of execution, the parties 1) agreed on all of the material terms, 2) had the present intention to be bound by that agreement and 3) supported it with sufficient consideration. See Neuhoff v. Marvin Lumber &

Cedar Co., 370 F.3d 197, 201 (1st Cir. 2004); Situation Mgmt. Sys., Inc. v. Malouf, Inc., 724 N.E.2d 699, 703 (Mass. 2000). The manifestation of such an agreement “generally consists of an offer by one and the acceptance of it by the other.” I & R Mech., Inc. v. Hazelton Mfg. Co., 817 N.E.2d 799, 802 (Mass. App. Ct. 2004). Here, the Court concludes that the complaint states a claim for breach of contract. First, the factual allegations permit the reasonable inference that a valid contract exists. The complaint states specifically that, 1) after L.E.K. contacted GPJ seeking assistance in planning and conducting the Conference in Hong Kong, GPJ secured a venue, 2) the parties negotiated the

cost of the hotel rooms, meeting rooms, dinner and other amenities at the Hotel and GPJ’s services, 3) L.E.K. informed GPJ that they were ready to contract, 4) GPJ subsequently sent L.E.K. a finalized price quotation (the purported contract) and 5) a representative of L.E.K. signed and delivered that document to GPJ. Second, the complaint plausibly alleges that L.E.K. failed to perform its obligations under that contract because the purported contract required L.E.K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Neuhoff v. Marvin Lumber & Cedar Co.
370 F.3d 197 (First Circuit, 2004)
FAMM Steel, Inc. v. Sovereign Bank
571 F.3d 93 (First Circuit, 2009)
Ocasio-Hernandez v. Fortuno-Burset
640 F.3d 1 (First Circuit, 2011)
Haley v. City of Boston
657 F.3d 39 (First Circuit, 2011)
Young v. Wells Fargo Bank, N.A.
717 F.3d 224 (First Circuit, 2013)
Guckenberger v. Boston University
957 F. Supp. 306 (D. Massachusetts, 1997)
APB Realty, Inc. v. Georgia-Pacific LLC
889 F.3d 26 (First Circuit, 2018)
Situation Management Systems, Inc. v. Malouf, Inc.
724 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2000)
I & R Mechanical, Inc. v. Hazelton Manufacturing Co.
817 N.E.2d 799 (Massachusetts Appeals Court, 2004)
Shaulis v. Nordstrom Inc.
120 F. Supp. 3d 40 (D. Massachusetts, 2015)
Cocchi v. Morais Concrete Service, Inc.
2015 Mass. App. Div. 49 (Mass. Dist. Ct., App. Div., 2015)

Cite This Page — Counsel Stack

Bluebook (online)
George P. Johnson Hong Kong Ltd. v. L.E.K. Consulting LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-p-johnson-hong-kong-ltd-v-lek-consulting-llc-mad-2020.