Nesbitt, Inc. v. Massachusetts Bonding & Insurance

49 N.E.2d 765, 38 Ohio Law. Abs. 299, 1942 Ohio App. LEXIS 762
CourtOhio Court of Appeals
DecidedDecember 28, 1942
DocketNo. 18881
StatusPublished
Cited by4 cases

This text of 49 N.E.2d 765 (Nesbitt, Inc. v. Massachusetts Bonding & Insurance) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nesbitt, Inc. v. Massachusetts Bonding & Insurance, 49 N.E.2d 765, 38 Ohio Law. Abs. 299, 1942 Ohio App. LEXIS 762 (Ohio Ct. App. 1942).

Opinion

OPINION

By MORGAN, J.

In 1933 the Board of Education of the School District of Norwalk, Ohio, decided to erect a new high school building. On application, the Public Works Administration of the United States granted the Board $126,000.00 which was substantially 457> of the cost of the building. The voters of Norwalk, Ohio, approved a bond issue of $148,500.00, sufficient to meet the remainder of the cost of the building. Bids were called for and E. M. Withers, d.b.a., The Withers Company, was awarded the “plumbing, heating and ventilating.” The .plaintiff was a sub-contractor who agreed to furnish to Withers, the contractor, certain materials known as “Thermovents” at an agreed price. It is not denied that these materials were actually installed in the building by the plaintiff and that Withers owes him $821.00 therefor.

As provided by §2365-1 et al, GC E. M. Withers, as principal, and defendant, The Massachusetts Bonding & Insurance Company of Boston, as surety, executed the required contractor’s bond.

Section 2365-3 GC provides that any person to whom any money shall be due on account of having performed any labor or furnished any materials in the construction of a building such as the Norwalk High School, shall furnish the surety “a statement of the amount due to such person, Arm or corporation” but such statement must be furnished to the surety “not later than ninety days after the acceptance of such building, work or improvements by the duly authorized Board or Officer.”

The plaintiff on September 6, 1940, to comply with §2365-3 GC, furnished to the defendant bonding company, an itemized statement of labor and materials furnished by plaintiff on -its subcontract. The defendant in its answer alleges that “the Board of Education of Norwalk, Ohio, accepted the contract of E. M'. Withers Company on May 24, 1940” which was more than ninety days before the plaintiff furnished it with the said statement. At the be[301]*301ginning of the trial the parties stipulated that “the sole issue to be determined in this law suit is, therefore, whether or not the Board of Education of the City of Norwalk School District met and accepted the public improvement installed by the defendant, Ernest M. Withers, as contemplated by §2365-3 GC, on the 24th day of May, 1940.”

The case was submitted to a jury which found for the defendants.

Only one witness, called by the plaintiff and the defendants, testified in the case, namely, Arthur C. Elmer, the Clerk of the Board who was also a member. Bus evidence, together with the exhibits and the court’s charge to the jury constitutes the entire record in the case.

The facts of the case as testified to by Mr. Elmer are as follows :

On May 24, 1940, the general contractor, The L. M. Leonard •Company, had completed its contract. There were ten other contractors. Two of them, The Withers Company having the contract' for the plumbing, heating and ventilating, and The E. C. Reitz. Company having the contract for the electrical work, had not completed their contracts. The general contractor was anxious to get his money and on May 24, 1940, he met with the architect of the building and the resident engineer of the P. W. A. at the high school building under construction. All of the members of the Board of Education were called by telephone and they and the said three persons met at the building.

In order that the general contractor should be paid promptly, it was necessary to secure from P. W. A. the balance of its grant amounting to $26,000.00. A form of certificate prepared by P. W. A. was submitted to the members of the Board by the resident engineer of P. W. A. with the statement that it would be necessary under P. W. A. regulations to have such a certificate signed before the P. W. A. would proceed to make an audit of the Project and pay the balance of $26,000.00. "

Mr. Elmer, the Clerk of the Board, further testified that on May 24, 1940, “we went through the building and the building was substantially completed at that time, except for work the Withers Company and the Reitz Company were doing at that time.” -

The form of acceptance submitted by the resident P. W. A. was altered before it was signed by the members of the Board. The certificate as signed which is defendant’s exhibit 1, contains a proviso not included in the form of acceptance submitted by the representative of P. W. A. The acceptance as signed by the five members of the Board is as follows:

[302]*302“THIS IS TO CERTIFY that in compliance with the approved plans and specifications, and other contract documents for the construction of a schooi building, P. W. A. Docket No. OH-1808 F, in the City of Norwalk, County of Huron and State of Ohio, co-partnerships, corporations or individuals as follows:

(then follow the names of the 11 contractors including the Withers Company.)

Said co-partnerships, corporations or individuals being hereinafter designated as ‘contractors’ have furnished materials and constructed said school building which, on the part of said contractors, was to be furnished and constructed, under their contracts with the Board of Education of the City of Norwalk, Ohio, and that all of said work is accepted, provided, however, that the issuance of this certificate shall not be taken or construed as relieving said contractors of their agreements expressed in their said contracts to remedy such defects, if any, m material or workmanship, as may appear within the periods stated in said contracts, or as relieving said contractors of any other responsibility or contractual’'obligations which, in accordance with the true intent and meaning of said contracts, should remain in force and effect after the issuance of the certificate of completion and acceptance.

THIS IS TO FURTHER CERTIFY that all of the work contemplated by said Project P. W. A. Docket No. OH-1808 F, has been completed and is accepted.

Dated this 24th day of May, 1940, at Norwalk, Huron County, Ohio.

Norman B. Furlong, President

Mildred M. Laning, Vice-President

Arthur C. Elmer, Clerk, Mem.

Ray Gandolf, Member of Board

Tracy M. Patrick,'Member of Board.”

Mr. Elmer further testified that the words in the said certificate, beginning with “provided however, * * *” and to the end of the paragraph, were not found in the original certificate submitted by P. W: A;', and were added at the request and insistance of the members of the Board.

■ ■ A- quéstion directed to the Clerk by the attorney for the plaintiff, as to-the reason’s for the Board insisting, on the additional provision was held incompetent, by the trial' judge as violating the parol evidence rule. We have no .fault to find with this ruling. An exainination, however, of the clause added by the Board discloses' the reasons for its inclusion.

■ - • The evidence is uncontradicte.d that neither the Withers Com-, pany nor the Reitz Company had completed their contracts on [303]*303May 24, 1940. The Withers Company kept five men on the job until J June 20th and even then, the record discloses that Withers had notf completed his contract according to its terms and the plans and. specifications. The Board, while wishing to secure promptly the; balance due from P. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph J. Hock, Inc. v. Baltimore Contractors, Inc.
249 A.2d 135 (Court of Appeals of Maryland, 1969)
United States Fidelity & Guaranty Co. v. Hamilton & Spiegel, Inc.
215 A.2d 735 (Court of Appeals of Maryland, 1966)
Baltimore County Department of Education v. Henry A. Knott, Inc.
199 A.2d 369 (Court of Appeals of Maryland, 1964)
Johnson Service Co. v. American Casualty Co.
148 N.E.2d 112 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
49 N.E.2d 765, 38 Ohio Law. Abs. 299, 1942 Ohio App. LEXIS 762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nesbitt-inc-v-massachusetts-bonding-insurance-ohioctapp-1942.