Johnson Service Co. v. American Casualty Co.

148 N.E.2d 112, 77 Ohio Law. Abs. 508, 6 Ohio Op. 2d 290, 1957 Ohio Misc. LEXIS 350
CourtCourt of Common Pleas of Ohio, Franklin County, Civil Division
DecidedJanuary 3, 1957
DocketNo. 190192
StatusPublished

This text of 148 N.E.2d 112 (Johnson Service Co. v. American Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Common Pleas of Ohio, Franklin County, Civil Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Service Co. v. American Casualty Co., 148 N.E.2d 112, 77 Ohio Law. Abs. 508, 6 Ohio Op. 2d 290, 1957 Ohio Misc. LEXIS 350 (Ohio Super. Ct. 1957).

Opinion

OPINION

By LEACH, J.

This action was instituted by plaintiff against the defendant Bonding Company to recover the sum of $3050.00 on a performance bond in the form required by §153.57 R. C., and executed by J. Frank Bowen Co. Inc., contractor, as principal and the Bonding Company as Surety in connection with a contract with the Board of Education of the City School District of Columbus, Ohio, for the heating, ventilating and plumbing work on the addition and modernization of a school building. This case was submitted to the Court, the jury having been waived. '

In carrying out that contract, Bowen entered into a contract with the plaintiff for the furnishing of certain labor and materials. The contract price agreed upon between Bowen and the plaintiff was $4,550.00, of which $1500.00 was paid, leaving a balance of $3050.00.

Sec. 153.56 R. C., reads as follows:

[509]*509“Any person, firm or corporation to whom any money is due on account of having performed any labor or furnished any material in the construction, erection, alteration, or repair of any public building or other public work or improvement as provided in §153.54 R. C., at any time after* performing such labor or furnishing such material, but not later than ninety days after the acceptance of such building, work, or improvement by the duly authorized board or officer, shall furnish the sureties on said bond, a statement of the amount due to any such person, firm, or corporation.

“No suit shall be brought against said sureties on said bond until after sixty days after the furnishing of said statement. If said indebtedness is not paid in full at the -expiration of said sixty days, said person, firm, or corporation may bring an action in its own name upon such bond, as provided in §§2307.06 and 2307.07 R. C., said action to be commenced not later than one year from the date of acceptance of said building, work, or improvement.” (Emphasis added.)

The sole issue presented in this case is whether plaintiff furnished the Bonding Company a statement of the amount due “not later than ninety days after the acceptance” and whether this action was commenced “not later than one year from the date of acceptance.”

It is undisputed that plaintiff furnished the Bonding Company such a statement on January 21, 1954, and this suit was commenced on June 17, 1954.

Basically, it is the contention of the plaintiff that the work in question never has been accepted by the Board of Education within the purview of §153.56 R. C. On the contrary, it is the contention of the defendant that §153.56 R. C., authorizes acceptance by an officer as well as by a duly authorized Board and that the work in question was accepted by W. V. Drake, Clerk-Treasurer of the Board, on May 1, 1953.

On April 17, 1951, the Board adopted a resolution approving the recommendation of the Superintendent of Schools that Freshwater and Harrison, architects, be employed in connection with the remodeling of an addition to the Second Avenue School. On May 3, 1951, a written agreement was entered into between the Board of Education and Freshwater and Harrison, the agreement being signed on behalf of the Board by its Vice-president and Mr. Drake as Clerk-Treasurer. By resolution of January 7, 1952, the Board awarded a contract to J. Frank Bowen, Inc. in the amount of $44,350.00 for the addition and modernization of such school. On January 10, 1952, the Board, acting by its President and Clerk-Treasurer, entered into a contract with Bowen for such work and in connection with this contract, the Bonding Company executed its statutory bond. The contract between the Board and Bowen provided for certain monthly payments and further provided “on substantial completion of the entire work, a sum sufficient to increase the total payment of 90% of the Contract price, and thirty days thereafter, provided the work be fully completed and the Contract fully performed, the balance due under the Contract.”

The agreement between the Board and the architects provided that the architects should furnish complete supervision throughout the period of construction. On April 29, 1953, the architects certified to the Board [510]*510that final payment was due to Bowen under the terms of the Contract between Bowen and the Board, dated January 10, 1952. On April 30, 1953, Edward Kromer, employed as a Structural Engineer for the Board of Education as a full-time employee supervising the construction and improvement of school buildings, and sometimes designated by the Board of Education as its architect, certified to the Board that such final payment was due to Bowen. On May 1, 1953, the Clerk-Treasurer, Mr. W. V. Drake, certified such payment as being correct, such was approved by' the President of the Board, and payment made at that time.

Mr. H. C. Kuhnle, the present Clerk-Treasurer, testified that the procedure followed in handling this contract with Bowen, was the same as the procedure followed by the Board in all of the Board’s contracts for improvements, additions or reconstructions. It appears that the Board did not at any time formally adopt a resolution stating specifically that they did hereby accept the improvement in question. It further appears that the Board has never followed this procedure of adopting such a formal resolution but instead, has always followed the procedure as in the instant case.

It appears from the work sheets of the plaintiff as to this particular job that the last work done by it at the Second Avenue School was on April 5, 1953. The contract between the Board and Bowen provided that the contract should be substantially completed on or before September 1, 1952, and the Second Avenue School was actually opened as a remodeled building on September 2, 1952. The work sheets of the employer indicate that most of the hours of work of their employees on the Second Avenue School took place prior to September 16, 1952, although, as heretofore indicated, we find isolated hours of work running until April 5, 1953.

As heretofore stated, it is the contention of the plaintiff that the work in question never has been accepted by the Board of Education in view of the fact that it has never adopted a formal resolution, stating in effect: “We hereby accept the work on the Second Avenue School.” In support of this contention plaintiff makes reference to certain language in the opinion of Vickery, J. of the 8th District Court of Appeals in the case of Royal Indemnity Company v. Buckeye Brick Company, 7 Abs 501, wherein he stated that “The statute of Ohio undoubtedly had in mind a resolution as to the improvement so that it would be definite and determined when those who claimed liens against it could determine the time when they must file their claims or be forever barred.” This same judge, however, in Royal Indemnity Company v. American Slide and Supply Company, 8 Abs 282, held as to a school contract that the work had been accepted “by Director Hogan” and that the statute authorized acceptance either by the Board or by an officer. We are in agreement with the opinion expressed by Judge Vickery that the statute permits acceptance by an officer as well as by a Board and conclude that there was acceptance within the purview of §153.56 R. C., on May 1, 1953. We conclude that the actions of the President of the Board of Education and the Clerk-Treasurer on that date did constitute an acceptance.

[511]*511Judge Vickery also stated in the first case that the allowing of a final estimate does not necessarily constitute acceptance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Illinois Surety Co. v. United States Ex Rel. Peeler
240 U.S. 214 (Supreme Court, 1916)
Royal Indemnity Co. v. Buckeye Brick Co.
7 Ohio Law. Abs. 501 (Ohio Court of Appeals, 1929)
Royal Indemnity Co. v. American Slag & Supply Co.
8 Ohio Law. Abs. 282 (Ohio Court of Appeals, 1929)
Nesbitt, Inc. v. Massachusetts Bonding & Insurance
49 N.E.2d 765 (Ohio Court of Appeals, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E.2d 112, 77 Ohio Law. Abs. 508, 6 Ohio Op. 2d 290, 1957 Ohio Misc. LEXIS 350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-service-co-v-american-casualty-co-ohctcomplfrankl-1957.