Joseph J. Hock, Inc. v. Baltimore Contractors, Inc.

249 A.2d 135, 252 Md. 61, 1969 Md. LEXIS 1061
CourtCourt of Appeals of Maryland
DecidedJanuary 13, 1969
Docket[No. 29, September Term, 1968.]
StatusPublished
Cited by1 cases

This text of 249 A.2d 135 (Joseph J. Hock, Inc. v. Baltimore Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph J. Hock, Inc. v. Baltimore Contractors, Inc., 249 A.2d 135, 252 Md. 61, 1969 Md. LEXIS 1061 (Md. 1969).

Opinion

Singeey, J.,

delivered the opinion of the Court.

Chapter 10 of the Laws of 1959 repealed and re-enacted Maryland Code (1957) Art. 90, § 11 (the Act) which requires principal contractors to provide performance and payment bonds on all contracts for public work which exceed $5,000 in amount in order to protect subcontractors and materialmen.

Subsection (c) of the Act permits persons who have furnished labor and material to sue on the payment bond if they have not been paid within 90 days after the last labor was done or the last material furnished.

Subsection (d) provides that “* * * no such suit shall be commenced after the term of one year after the date of final acceptance of the work performed under the contract. * * *”

On 8 August 1961, the Mayor and City Council of Baltimore (the City) entered into a contract with Baltimore Contractors, Inc. (Baltimore Contractors), a defendant below and *63 appellee here, for the construction of the Baltimore Civic Center at a cost of $7,403,000. The bond required by the statute was written by the other appellee, United States Fidelity & Guaranty Company (the Surety). One of Baltimore Contractors' subcontractors was Varsity Pre-Cast Seat Company (Varsity), to which Joseph J. Hock, Inc. (Hock), the plaintiff below and appellant here, furnished drivers and trucks during the period between 22 February and 20' August 1962. When Hock completed its contract with Varsity in August, Varsity owed Hock $6,228.32, which was not paid. On 22 August 1962, Hock notified Baltimore Contractors and the Surety of its claim, and on 25 May 1964, instituted suit against Baltimore Contractors and the Surety. From a judgment absolute in favor of the defendants for costs, Hock appealed.

The case turns on a narrow question: Was Hock’s suit, brought on 25 May 1964, barred by subsection (d) of the Act, which provides that “* * * no such suit shall be commenced after the term of one year after the date of final acceptance of the wmrk performed under the contract.” ? The lower court found that 10 April 1963 was the date when the job was completed and was the date of “final acceptance” and concluded that Hock’s suit had been brought too late.

While the entire contract between the City and Baltimore Contractors was not before the lower court and is not before us, Raughley E. Porter, the City’s Building Construction Engineer, testified that the contract contained no provision defining “final acceptance.” The contract did provide that Baltimore Contractors guarantee the work “* * * for a period of two (2) years from the date of final acceptance of the completed project by the City. * * *” (Emphasis added)

The interplay of a number of forces produced a factual situation which was, to say the least, somewhat muddled and offered the lower court a wide choice of dates on which the City did something looking toward acceptance. The earliest of these was 23 October 1962, when “conditional” acceptance was given to the portion of the Civic Center which contained the ice rink. This action appears to have been dictated by a consideration of a wholly practical character: the first ice hockey game of the season was about to be played. The acceptance was con *64 ditioned on the completion of a number of items detailed on a punch list.

As a result of an inspection of the building made on 1 February 1963, a second “conditional” acceptance was given Baltimore Contractors. This related to the remainder of the building, other than the ice rink. It was similarly conditioned on the completion of items contained in another punch list, and ultimately, apparently about 9 March, resulted in the release of $269,656.70 of the remaining contract price then being retained by the City. A balance of $100,000 was withheld until the items on the two punch lists could be completed.

By 10 April 1963, according to Mr. Porter’s testimony, the items on the two punch lists had been completed. There was a malfunctioning in the ice rink’s brine system, but this had been discovered after the preparation of the first punch list, and the correction which was required was regarded by the City as being included in the builder’s guarantee. In any event, the work could not be done until the end of the hockey season.

On 7 June, Baltimore Contractors prepared a schedule 1 detailing the release of subcontractors’ claims and the receipt of their guarantees, and sometime after 16 June the $100,000 which had been retained was released to Baltimore Contractors. It is interesting to note that the voucher which had been sent by the Bureau of Building Construction to the City’s Bureau of Accounts and Disbursements on or after 28 February, authorizing the disbursement of $269,656.70 was described as a “partial release”, while that sent on or after 11 June, authorizing the remittance of the last $100,000 was described as a “final release.”

On 2 April 1963, Baltimore Contractors had sent a letter to Mr. Porter:

“This is to advise that we have completed this project including the execution of all punch lists previously sent to us.
“We acknowledge that the repairs to one brine pipe in the ice rink area are still pending and must await *65 the end of the use of the ice rink this spring. Also, we recognize that the sound system is yet to be tested on April 8, 1963.
“In all other respects we have completed our contract work and ask that you formally accept this completed project so that we may make our final requisition for final payment of all our retainage due us.”

Gerald J. Rhein, a member of Mr. Porter’s staff, had made the following notation on the letter:

“Final acceptance of building 3/9/63 — with $100,000 withheld for correction of punch list items. Punch list items were not sufficiently completed at time of final acceptance, so the $100,000 was not released until June 10, 1963, at which time we accepted the punch list items as being complete.”

On 10 April, Mr. Porter wrote to Bernard P. Werner, the City’s Director of Public Works :

“The construction of the Baltimore Civic Center was awarded to Baltimore Contractors, Tnc., at the contract price of $7,403,000. The contractor was authorized to proceed on August 22, 1961.
“Final inspection of the project was made on February 1, 1963, and on this same date it was conditionally accepted, pending the completion of the punch list items.
“The punch list items required 37 calendar days to accomplish. . .February 1, 1963 to March 9, 1963. . . thus fulfilling all work covered by the contract.
“The specifications provide the project shall be completed on September 15, 1962, with a liquidated damage clause of $1000 per calendar day for the first 30 days and $2000. per calendar day for every day thereafter, that the work is incomplete beyond the stated time.
“The actual number of calendar days consumed for the construction'of the project is computed as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Antonio Carro, Inc. v. Jura Construction, Inc.
107 P.R. Dec. 808 (Supreme Court of Puerto Rico, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
249 A.2d 135, 252 Md. 61, 1969 Md. LEXIS 1061, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-j-hock-inc-v-baltimore-contractors-inc-md-1969.